Southbourne Allocation Development Plan Document - Regulation 19 Consultation
Other elements in this consultation
Appendix A – Infrastructure Delivery Plan (IDP) Update
As part of the development of the Southbourne DPD, relevant infrastructure providers were contacted to provide an update to the IDP (vis-à-vis the IDP prepared in support of the CLP) for Southbourne Parish, accounting for potential funding, project, and infrastructure requirement changes. Below represents the most up to date information provided as a result of this update. The update is predicated on the specific allocation option set out in the DPD. Some new infrastructure provision has been identified, which is a result of the DPD having identified a specific allocation, generating some specific infrastructure needs, which was not something that could be established at the time the CLP was prepared, as that was based upon a Broad Location for Development, meaning some of the more site specific infrastructure needs were not yet known. This update has been factored into the viability evidence prepared in support of this DPD. Comment
|
Infrastructure Category |
Scheme (what) (Schemes marked with * are ‘new’ projects identified as part of the process of producing the Southbourne Allocation DPD) |
Justification/Rationale |
Phasing (when) |
Total Estimated Infrastructure Cost |
Sources of funding |
Delivery Lead (who/whom) |
Priority in delivering SADPD |
|
Transport |
Foot/cycle bridge over Railway line (between Cooks Lane site and Priors Orchard)* |
Modal Shift, Social cohesion and connection to wider active travel network. |
Flexible installation dependent on delivery timing of development |
£1,200,000 - £9,000,000 (depending on level of accessibility) |
S106/CIL |
Network Rail |
Essential |
|
Transport |
Inlands Road level crossing upgrade*. |
Safety – Inlands Road crossing is currently a single arm barrier. Development on the east would require upgrades to a double arm barrier to improve safety. |
Delivery when the sections of the development which have a vehicular access onto Priors Leaze Lane and Inlands Road are developed. |
Approximately £6,000,000 |
S106 |
Network Rail |
Essential |
|
Transport |
Bourne Active Travel Scheme (Previously ChEm Route) (this is an updated version of the entry in the IDP produced in support of the adopted Local Plan) |
To improve the safety of cyclists and pedestrians, whilst also maintaining the A259’s function as a strategic diversion route for the A27. To encourage active modes of travel between Chichester and Emsworth. This is a wider scheme, the expectation is that the development will make a contribution towards a part of it. |
To be completed over the Adopted Local Plan period |
Overall cost £11m to £15m |
S106 (proportionate contribution) |
WSCC |
High |
|
Transport |
Southbourne bus service improvements/extension* (this is an updated version of the entry in the IDP produced in support of the adopted Local Plan) |
To integrate bus services into the initial phases of development to help create strategic options for behavioural changes and mode choice. |
Staged infrastructure rollout dependent on delivery timing of development |
TBA following commercial engagements with operators by developers |
S106 |
WSCC, Bus Operators |
High |
|
Transport |
Southbourne train station access improvements* |
Provision of improvements to access, ensure congestion reduction and promote the shift from the use of cars to more sustainable public transport. |
Staged infrastructure dependent on delivery timing of development |
TBA following developer engagements with Network Rail. |
CIL |
Network Rail, WSCC |
High |
|
Transport |
A259 Southbourne bus stop improvements* (this is an updated version of the entry in the IDP produced in support of the adopted Local Plan) |
Potentially providing secure cycle parking and facilities such as shelters and real time information for user connectivity, comfort and convenience enabling the switch from cars to public transport for sustainability, thereby reducing congestion, air pollution and noise levels. |
Flexible installation dependent on delivery timing of development |
TBD subject to further developer engagements with bus operators. |
CIL |
WSCC |
High |
|
Upgrade of footpaths linking Nutbourne, Broadbridge, Fishbourne, Bosham, Apuldram, Westbourne, Woodmancote (with existing bridleway extension), Southbourne and Emsworth together with uncontrolled crossings at road points (IBP/1168) |
Provision of improvements to access and promote the shift from the use of cars to active travel. |
Dependent on timing of development |
TBD – depends upon exactly which routes need to be upgraded and to what extent. |
CIL |
WSCC |
Essential |
|
|
Total Transport Costs |
Up to £30,000,000 |
||||||
|
Education |
Primary Serviced Land for a 1 form entry expandable to 2FE primary school core buildings, Special Support Centre (SSC) and Early Years, and pro rata share of the build costs would be required. (this is an updated version of the entry in the IDP produced in support of the adopted Local Plan) (IBP/1027) |
Based on current figure of 800 homes, plus changes to the birthrate and other factors, the requirement for a Primary School at Southbourne has been reassessed. 2ha for school and 0.05ha for attached SSC – 2.05ha required. |
With development (after the provision of 500 units) |
£8.76m |
S106 (on site provision) |
WSCC/ Developer |
Essential – dependent on development delivery and need for places |
|
Secondary Expansion of Southbourne secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required. (IBP/1199) |
WSCC calculator based |
CIL |
WSCC |
Essential |
|||
|
Sixth form Contributions would be required for expansion if feasible and required IBP/1200) |
WSCC calculator based |
CIL |
WSCC |
Essential |
|||
|
Early Years and Childcare places 60 places provided as part of the new primary school. (IBP/1028) |
At the current time early years and childcare sufficiency planning indicates that there is insufficient space within existing provision to serve this proposed development. Required as part of site allocation, 0.17ha. |
£2,520,000 |
S106 (on site provision) |
Developer |
Essential – Dependent on development delivery and need for places |
||
|
Special Educational Needs & Disability To be provided as part of the new primary school. (IBP/1092) |
£TBC |
S106 (on site provision) |
Developer |
Essential |
|||
|
Total Education Costs |
£11,280,000 |
||||||
|
Health |
See Plan Area Wide Health Infrastructure Needs |
||||||
|
Wider Plan Health Infrastructure Needs |
Improvements at Southbourne Surgery (increase number of clinic rooms by extending) (IBP/726) |
Housing increase and directly associated GP registration. Project time frame paused so as to align to Willow Park (IBP/115) delivery. |
2027-2028 |
£450,000 |
CIL |
GP Practice Manager & Integrated Care Board |
Already selected for inclusion in the CIL spending plan[5] |
|
Total Health Costs |
|||||||
|
Social Infrastructure |
1 New Community Hall of sufficient size to accommodate a variety of recreational and social activities – a minimum of 18m x 10m, capacity of around 150 – 200 seated, with small meeting room, kitchen, storage and toilet facilities commensurate with size, with provision for disabled users and car parking. Overall a net minimum of 666 sq m. Provision should be able to accommodate a badminton court. (IBP/885) |
Open Space. Indoor Sports & Playing Pitch Strategy 2024 |
£2,000,000 |
S106 (on site provision) |
Developer |
Essential |
|
|
Sport and Leisure Facilities See Plan Area Wide Social Infrastructure Needs |
|||||||
|
Total Social Infrastructure Costs |
£2,000,000 |
||||||
|
Green Infrastructure |
Allotments (IBP/1030) |
Open Space calculator based. Estimated provision of 496 sqm of allotments to meet future demand from increased population (subject to number of units applied for and the proposed housing mix) |
In line with phasing of site development |
£169,926 |
S106 (on site provision) |
Developer |
Essential |
|
Amenity/Natural open space (IBP/1031) |
Open Space calculator based. Approx Provision of 10,765 sqm of amenity green space and 19,875 sqm of natural green space to meet future demand from increased population (subject to number of units applied for and the proposed housing mix) |
In line with phasing of site development |
£299,772 |
S106 (on site provision) |
Developer |
Essential |
|
|
Parks & Recreation Grounds (IBP/1032) |
Open Space calculator based. Approx Provision of 19,874 sqm of parks and recreational grounds to meet future demand from increased population Includes sports pitches, comprising 1 full size Artificial Grass Pitch, 1 youth pitch (natural grass) and two mini/junior football pitches (natural grass) and one Multi Use Games Area. All as per Sport England cost estimates. (subject to number of units applied for and the proposed housing mix) |
In line with phasing of site development |
£3,845,964 |
S106 (on site provision) |
Developer |
Essential |
|
|
Play Space (Children & Youth) (IBP/1033*) |
Open Space calculator based. Approx Provision of 1,242 sqm of play space for children and 1,242 sqm for youth to meet future demand from increased population (subject to number of units applied for and the proposed housing mix) |
In line with phasing of site development Developer |
£389,054 |
S106 (on site provision) |
Developer |
Essential |
|
|
Total Green Infrastructure Costs |
£4,704,716 |
||||||
|
Habitats Regulations Mitigation |
Bird Aware Solent[6] |
Mitigation for the impact of recreational activities arising from development in the Special Protection Areas (Solent-wide Wardens) |
£654,323 |
S106 |
Bird Aware Solent |
Essential |
|
|
Nutrient Mitigation |
Habitats Regulations (calculation based on Local Plan nutrient budget) |
TBD |
S106 |
Developer |
Essential |
||
|
Total Habitats Regulations Mitigation |
£654,323 |
||||||
|
Public Services |
Library facilities – remodelling of existing Southbourne library (IBP/1034) |
To accommodate impact of new residents from allocation. |
£606,922 |
CIL |
WSCC |
High |
|
|
Police See Area Wide Public Services |
|||||||
|
Total Public Services Costs |
£606,922 |
||||||
|
Utility Services |
Sewerage network reinforcement |
To ensure the efficacy and resilience of the network. Southern Water have stated that this will need further consideration at the Planning Application stage. |
In line with phasing of site development |
Based on new connection charge plus site specific costs |
Southern Water |
Southern Water |
Critical |
|
Thornham Sewage Treatment Works – Capacity Increase |
Further to a report to Development Plan and Infrastructure Panel on the 15 October 2025 , and written confirmation from Southern Water and the Environment Agency, the Thornham Position Statement has been withdrawn with immediate effect because Southern Water has confirmed funding to increase treatment capacity at the Thornham Wastewater Treatment Works. This scheme is identified as a priority and must be completed before 2030. |
2025 - 2030 |
Now fully funded |
Southern Water |
Southern Water |
Critical – but now fully funded. |
|
|
Total Utility Services Costs |