Chichester Local Plan 2021 - 2039: Proposed Submission

Search representations

Results for Donnington Parish Council search

New search New search

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

8.10

Representation ID: 4049

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

CATM model calibrated and validated using 2014 data not taking account of developments such as Chichester Free School adjacent to A27 Whyke roundabout. Transport assessment states "all junctions on the A27 Bypass are over capacity in one or both modelled peak hours". Only 28% of traffic growth due to Local Plan development. Improvements only to Fishbourne and Bognor Roundabouts so over capacity issues still remain at other roundabouts. Plan does not effectively mitigate the impact of additional growth and is adding further demand.

Change suggested by respondent:

Housing number should be further challenged on this basis.

Full text:

CATM model calibrated and validated using 2014 data not taking account of developments such as Chichester Free School adjacent to A27 Whyke roundabout. Transport assessment states "all junctions on the A27 Bypass are over capacity in one or both modelled peak hours". Only 28% of traffic growth due to Local Plan development. Improvements only to Fishbourne and Bognor Roundabouts so over capacity issues still remain at other roundabouts. Plan does not effectively mitigate the impact of additional growth and is adding further demand.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

8.13

Representation ID: 4056

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Improvements to the A27 contentious locally. RIS 1 consultation in 2016 resulted in no consensus . Local Plan consultation 2018, generated significant feedback particularly regarding restricting local movements at key junctions and the Stockbridge Link Road, where the proposals were similar to those options robustly rejected in the RIS 1 consultation. No details provided on representative selection for TIMG, nor how local residents will be consulted on the delivery of any changes as part of the monitor and manage process. Could present an opportunity for circumventing legitimate local concerns and feedback on any proposals to be delivered under this group.

Change suggested by respondent:

Better explanation of the setup and selection of group members and clear detail around the accountability of the group to members of District and County Council and members of the public should be included in the Local Plan.

Full text:

Improvements to the A27 contentious locally. RIS 1 consultation in 2016 resulted in no consensus . Local Plan consultation 2018, generated significant feedback particularly regarding restricting local movements at key junctions and the Stockbridge Link Road, where the proposals were similar to those options robustly rejected in the RIS 1 consultation. No details provided on representative selection for TIMG, nor how local residents will be consulted on the delivery of any changes as part of the monitor and manage process. Could present an opportunity for circumventing legitimate local concerns and feedback on any proposals to be delivered under this group.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

8.14

Representation ID: 4058

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Significant issues with delivery of the Stockbridge Link Road including:
*Building next to an AONB, SSSI, Ramsar site
*Link road would be intrusive/out of keeping with the area as it would need to be over 3m high to cross a flood plain
*Insufficient impact studies on consequences of building on the flood plain
*Impact on noise/air pollution considering prevailing south westerly winds
*Impact of road on biodiversity net gain target in local plan - removal of fertile farmland

Change suggested by respondent:

Removal of plans for Stockbridge Link Road or much better assessment of the impact of the road before it is included in the Local Plan

Full text:

Significant issues with delivery of the Stockbridge Link Road including:
*Building next to an AONB, SSSI, Ramsar site
*Link road would be intrusive/out of keeping with the area as it would need to be over 3m high to cross a flood plain
*Insufficient impact studies on consequences of building on the flood plain
*Impact on noise/air pollution considering prevailing south westerly winds
*Impact of road on biodiversity net gain target in local plan - removal of fertile farmland

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

8.11

Representation ID: 4060

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Figure 7.4 Bognor Road and Vinnetrow Road Combined Concept scheme - insufficient detail.
Figure 7.7 A250 Cathedral Way/Fishbourne Road/Terminus Road proposed mitigation "Removal of existing traffic islands to facilitate all movement crossroad junction" compromises safe access to eg supermarket
Figure 7.3 No detailed figure of the Fishbourne roundabout mitigation itself. Figure includes Stockbridge Link Road which is NOT part of the submission as it is not funded.
If the transport assessment does not have correct diagrams, does this reflect a wider issue with the document not supporting the content of the Local Plan submission?

Change suggested by respondent:

7.4 does not show or explain the impact to Chichester/Bognor Cycle Path. Has the impact of sustainable travel been considered as part of the mitigation?
7.7 Impact on pedestrian safety should be considered and explained
7.3 Correct the figure and remove the SLR.

Revisit the Assessment for consistency with the plan

Full text:

Figure 7.4 Bognor Road and Vinnetrow Road Combined Concept scheme - insufficient detail.
Figure 7.7 A250 Cathedral Way/Fishbourne Road/Terminus Road proposed mitigation "Removal of existing traffic islands to facilitate all movement crossroad junction" compromises safe access to eg supermarket
Figure 7.3 No detailed figure of the Fishbourne roundabout mitigation itself. Figure includes Stockbridge Link Road which is NOT part of the submission as it is not funded.
If the transport assessment does not have correct diagrams, does this reflect a wider issue with the document not supporting the content of the Local Plan submission?

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Policy NE16 Water Management and Water Quality

Representation ID: 4072

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Apuldram WwTW is already currently inadequate per CDC's own admission. Southern Gateway Strategic Allocation AL5 drains to Apuldram WwTW. There are environmental constraints which restrict its capacity to accommodate any further development. Concern about permitting more homes before upgrades to infrastructure are complete. Clear these are necessary for housing growth whilst maintaining and improving water quality of receiving waters. Recent flooding illustrates urgency of upgrades. Southern Water's plans are optimistic and we have concerns this will actually be delivered within 10 years. Across the district the lack of sewage provision is set to worsen until the substantial improvements are delivered.

Change suggested by respondent:

No further development until the necessary infrastructure improvements are delivered.

Full text:

Apuldram WwTW is already currently inadequate per CDC's own admission. Southern Gateway Strategic Allocation AL5 drains to Apuldram WwTW. There are environmental constraints which restrict its capacity to accommodate any further development. Concern about permitting more homes before upgrades to infrastructure are complete. Clear these are necessary for housing growth whilst maintaining and improving water quality of receiving waters. Recent flooding illustrates urgency of upgrades. Southern Water's plans are optimistic and we have concerns this will actually be delivered within 10 years. Across the district the lack of sewage provision is set to worsen until the substantial improvements are delivered.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Policy H1 Meeting Housing Needs

Representation ID: 4134

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

CATM model calibrated and validated using 2014 data not taking account of developments such as Chichester Free School adjacent to A27 Whyke roundabout. Transport assessment states "all junctions on the A27 Bypass are over capacity in one or both modelled peak hours". Only 28% of traffic growth due to Local Plan development. Improvements only to Fishbourne and Bognor Roundabouts so over capacity issues still remain at other roundabouts. Plan does not effectively mitigate the impact of additional growth and is adding further demand.

Change suggested by respondent:

Housing number should be further challenged on this basis.

Full text:

CATM model calibrated and validated using 2014 data not taking account of developments such as Chichester Free School adjacent to A27 Whyke roundabout. Transport assessment states "all junctions on the A27 Bypass are over capacity in one or both modelled peak hours". Only 28% of traffic growth due to Local Plan development. Improvements only to Fishbourne and Bognor Roundabouts so over capacity issues still remain at other roundabouts. Plan does not effectively mitigate the impact of additional growth and is adding further demand.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Policy A5 Southern Gateway – Police Field, Kingsham Road

Representation ID: 6097

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Not specified

Sound? No

Duty to co-operate? Not specified

Representation Summary:

Apuldram WwTW is already currently inadequate per CDC's own admission. Southern Gateway Strategic Allocation AL5 drains to Apuldram WwTW. There are environmental constraints which restrict its capacity to accommodate any further development. Concern about permitting more homes before upgrades to infrastructure are complete. Clear these are necessary for housing growth whilst maintaining and improving water quality of receiving waters. Recent flooding illustrates urgency of upgrades. Southern Water's plans are optimistic and we have concerns this will actually be delivered within 10 years. Across the district the lack of sewage provision is set to worsen until the substantial improvements are delivered.

Change suggested by respondent:

No further development until the necessary infrastructure improvements are delivered

Full text:

Apuldram WwTW is already currently inadequate per CDC's own admission. Southern Gateway Strategic Allocation AL5 drains to Apuldram WwTW. There are environmental constraints which restrict its capacity to accommodate any further development. Concern about permitting more homes before upgrades to infrastructure are complete. Clear these are necessary for housing growth whilst maintaining and improving water quality of receiving waters. Recent flooding illustrates urgency of upgrades. Southern Water's plans are optimistic and we have concerns this will actually be delivered within 10 years. Across the district the lack of sewage provision is set to worsen until the substantial improvements are delivered.

For instructions on how to use the system and make comments, please see our help guide.