8.14

Showing comments and forms 1 to 9 of 9

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 3765

Received: 03/02/2023

Respondent: James Rank

Legally compliant? No

Sound? No

Duty to co-operate? No

Representation Summary:

The statement, 'There have not been any external sources of funding identified that would be able to deliver the scheme.' again implies efforts have been made to identify external sources of funding. Instead efforts have been made to remove potential external sources of funding.

Change suggested by respondent:

CDC should insist WSCC seek to have the A286 South of Chichester reinstated (after WSCC requested it be removed in March 2017 see minute 4.9 WSCC Ref No: HI29 (17/18)) as a potential scheme for consideration for funding as part of the Major Roads Network. MRN funding should be sought before CDC can say with confidence full and thorough attempts have been made to identify and secure external sources of funding for the Stockbridge Link Road.
The plan should state 'CDC will work with WSCC to promote the A286 South of Chichester for external sources of funding including within the Major Roads Network.

Full text:

The statement, 'There have not been any external sources of funding identified that would be able to deliver the scheme.' again implies efforts have been made to identify external sources of funding. Instead efforts have been made to remove potential external sources of funding.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 3834

Received: 23/02/2023

Respondent: Mrs Clare Gordon-Pullar

Legally compliant? No

Sound? No

Duty to co-operate? No

Representation Summary:

The "improvements" at Stockbridge/Whyke roundabouts will cause significant disruption. Residents will turn left and travel to either Bognor/Fishbourne roundabouts, generating more traffic on those roundabouts and roads.
This is the "trigger" for the Link Road. Leave the roundabouts alone and then the Link Road is not needed.
The Link Road will be an eyesore as it will be raised to go over the Canal, ruining the amenity of the Canal and blocking the view of the Cathedral painted by Turner.
Traffic from the south will go through the narrow North Mundham road to reach the Bognor roundabout via Vinnetrow Road

Change suggested by respondent:

The proposed changes to the A27 should be removed from the plan.
Reference should be made to the fact that local residents have already voted on these and rejected them. Given that there is little new development proposed for south of the A27, the Council should look at mitigation measures rather than building a new road or making junction approvements.

Full text:

The "improvements" at Stockbridge/Whyke roundabouts will cause significant disruption. Residents will turn left and travel to either Bognor/Fishbourne roundabouts, generating more traffic on those roundabouts and roads.
This is the "trigger" for the Link Road. Leave the roundabouts alone and then the Link Road is not needed.
The Link Road will be an eyesore as it will be raised to go over the Canal, ruining the amenity of the Canal and blocking the view of the Cathedral painted by Turner.
Traffic from the south will go through the narrow North Mundham road to reach the Bognor roundabout via Vinnetrow Road

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 3943

Received: 09/03/2023

Respondent: Fishbourne Parish Council

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

Fishbourne Parish Council is most concerned that the Stockbridge Link road is still even being considered when its environmental impact on the area and the huge financial cost would be totally unacceptable. The effect this Link Road would have on Fishbourne and the A259 has also not been considered.

Full text:

Fishbourne Parish Council is most concerned that the Stockbridge Link road is still even being considered when its environmental impact on the area and the huge financial cost would be totally unacceptable. The effct this Link Road would have on Fishbourne and the A259 has also note been considered.

Support

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 4035

Received: 13/03/2023

Respondent: Mr David Caldwell

Representation Summary:

Looking for any existing potential plans for the Stockbridge Link Road mitigation scheme as this sounds like a potential solution.

Full text:

Looking for any existing potential plans for the Stockbridge Link Road mitigation scheme as this sounds like a potential solution.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 4058

Received: 14/03/2023

Respondent: Donnington Parish Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Significant issues with delivery of the Stockbridge Link Road including:
*Building next to an AONB, SSSI, Ramsar site
*Link road would be intrusive/out of keeping with the area as it would need to be over 3m high to cross a flood plain
*Insufficient impact studies on consequences of building on the flood plain
*Impact on noise/air pollution considering prevailing south westerly winds
*Impact of road on biodiversity net gain target in local plan - removal of fertile farmland

Change suggested by respondent:

Removal of plans for Stockbridge Link Road or much better assessment of the impact of the road before it is included in the Local Plan

Full text:

Significant issues with delivery of the Stockbridge Link Road including:
*Building next to an AONB, SSSI, Ramsar site
*Link road would be intrusive/out of keeping with the area as it would need to be over 3m high to cross a flood plain
*Insufficient impact studies on consequences of building on the flood plain
*Impact on noise/air pollution considering prevailing south westerly winds
*Impact of road on biodiversity net gain target in local plan - removal of fertile farmland

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 4174

Received: 15/03/2023

Respondent: Chidham and Hambrook Parish Council

Legally compliant? Yes

Sound? Yes

Duty to co-operate? Yes

Representation Summary:

This is an admission that the A27 will be completely beyond capacity and that there are no funding sources available to carry out the necessary improvements identified to avoid this. This is irresponsible and would leave Chichester residents trapped. Another impact will be the increasing use of ‘rat runs’ through residential or rural areas to avoid the gridlock.

Change suggested by respondent:

Reduced housing numbers.

Full text:

This is an admission that the A27 will be completely beyond capacity and that there are no funding sources available to carry out the necessary improvements identified to avoid this. This is irresponsible and would leave Chichester residents trapped. Another impact will be the increasing use of ‘rat runs’ through residential or rural areas to avoid the gridlock.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 4600

Received: 16/03/2023

Respondent: Mrs Gabrielle Abbott

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Not effective – does not provide sound transport infrastructure planning

Given that it is acknowledged that based on current forecasting junction improvements are required at Stockbridge Roundabout and Whyke Roundabout it is not clear how our highways system will be able to accommodate additional development without the requisite improvements being made here. This conflicts with the stated policy in paragraph 8.6 of the plan.

Change suggested by respondent:

A revised development/transport strategy needs to be articulated which will provide a pathway to ensuring that requisite road improvements to these junctions are made so as to be able to accommodate new development .

Full text:

Not effective – does not provide sound transport infrastructure planning

Given that it is acknowledged that based on current forecasting junction improvements are required at Stockbridge Roundabout and Whyke Roundabout it is not clear how our highways system will be able to accommodate additional development without the requisite improvements being made here. This conflicts with the stated policy in paragraph 8.6 of the plan.

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 5474

Received: 17/03/2023

Respondent: Mayday! Action Group

Number of people: 8

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

This paragraph is an admission of the fact that the A27, due to contents of this Draft Local Plan, will not be able to cope. Honesty is to be appreciated but your district residents do not deserve to be the victims of this impossible situation. Minor roads and country lanes are already used by those who cannot have their journey times delayed. The 10,350 homes target must be reduced very significantly. Residents of the Shopwyke development cannot get out of their development at peak times to access the A27. The same will be the case for all the developments due to pouring impatient vehicles on to the A259 if 2,000 homes are built during the plan period. A serious rethink is needed to come up with more options.

Full text:

Executive Summary

The Local Plan as written lacks ambition and vision, and will be detrimental to the landscape within which the district lies. It is a plan borne out of a need to produce a legal document which will satisfy the regulatory authorities. In terms of Urban Planning it fails “To meet the needs of the present without compromising the ability of future generations to meet their own needs” (NPPF).

The development that will consequentially arise from the deployment of such a made Local Plan is not sustainable. It will adversely affect the Character, Amenity and Safety of the built environment, throughout our district.

In particular, the Local Plan is inadequate for the needs of the people in the district both at present and in the future because –

1. It has been written in advance of the District having a properly formed and agreed Climate Emergency Action Plan. It is inconceivable that such a key document will not shape our Local Plan. It is this Action Plan that is needed first in order to provide the long-term strategic view as to how and what the District will look like in the future; this, in turn, will help form and shape the policies outlined in any prospective, Local Plan. The Plan as proposed is moribund, as a result of “cart before the horse” thinking.

2. The Local Plan as written does not adequately address how infrastructure, transport and services are going to be materially and strategically improved to meet the predicted growth and shift to a significantly ageing population. There is presently insufficient capacity to supply services and to have adequate people and environmentally friendly connectivity, as a direct result of decades of neglect towards investing in infrastructure and services to meet the needs of the District’s population. We are led to believe that developers through increased levies in order to gain permission to build will fulfil this need, but all that this will result in is an uncoordinated, dysfunctional mess completely lacking in any future-proof master planning approach. We contend that this will do nothing for the quality of life of Chichester District residents and it will create a vacuum whereby few if indeed any can be held accountable or indeed found liable for shortcomings in the future.

3. The Local Plan as written does not state how it will go about addressing the need to create affordable homes. The District Council’s record on this matter since the last made plan has been inadequate and now the creation of affordable homes has become urgent as political/economic/social factors drive an ever increasing rate of change within the District.

4. Flood risks assessments used in forming the Plan are out of date (last completed in 2018) and any decision to allocate sites is contrary to Environment Agency policy. Additionally, since March 2021 Natural England established a position in relationship to ‘Hold the Line’ vs. ‘Managed Retreat’ in environmentally sensitive areas, of which the Chichester Harbour AONB is a significant example. CDC have failed to set out an appropriate policy within the proposed Local Plan that addresses this requirement.

5. The A27 needs significant investment in order to yield significant benefits for those travelling through the East-West corridor; this is unfunded. Essential improvements to the A27 are key to the success of any Local Plan particularly as the city’s ambitions are to expand significantly in the next two decades. But any ambitions will fall flat if the A27 is not improved before such plans are implemented.. The A259 is an increasingly dangerous so-called ‘resilient road’ with a significant increase in accidents and fatalities in recent years. In 2011, the BBC named the road as the “most crash prone A road” in the UK. There is nothing in the Local Plan that addresses this issue. There is no capacity within the strategic road network serving our district to accommodate the increase in housing planned, and the Local Plan does not guarantee it.

6. There is insufficient wastewater treatment capacity in the District to support the current houses let alone more. The tankering of wastewater from recent developments that Southern Water has not been able to connect to their network and in recent months the required emergency use of tankers to pump out overflowing sewers within our City/District reflects the gross weakness of short-termism dominated thinking at its worst and is an indictment of how broken our water system is. The provision of wastewater treatment is absolutely critical and essential to the well-being of all our residents and the long-term safety of our built environment. The abdication by those in authority, whether that be nationally, regionally or locally, is causing serious harm to the people to whom those in power owe a duty of care and their lack of urgency in dealing properly with this issue is seriously jeopardizing the environment in which we and all wildlife co-exist.

7. Settlement Boundaries should be left to the determination of Parish Councils to make and nobody else. The proposed policy outlined in the Local Plan to allow development on plots of land adjacent to existing settlement boundaries is ill-conceived and will lead to coalescence which is in contradiction of Policy NE3.

8. All the sites allocated in the Strategic Area Based Policies appear to be in the majority of cases Greenfield Sites. The plan makes little, if any reference to the development of Brownfield sites. In fact, there is not a Policy that relates to this source of land within the Local Plan as proposed. Whilst in the 2021 HELAA Report sites identified as being suitable for development in the District as being Brownfield sites were predicted to yield over 4000 new dwellings. Why would our Local Plan not seek to develop these sites ahead of Greenfield sites?

9. The Local Plan does not define the minimum size that a wildlife corridor should be in width. What does close proximity to a wildlife corridor mean? How can you have a policy (NE 4) that suggests you can have development within a wildlife corridor? These exceptions need to have clear measures and accountability for providing evidence of no adverse impact on the wildlife corridor where a development is proposed. Our view is quite clear. Wildlife and indeed nature in the UK is under serious and in the case of far too many species, potentially terminal threat. Natural England has suggested that a Wildlife Corridor should not be less than 100metres wide. The proposed Wildlife Corridors agreed to by CDC must be enlarged and fully protected from any development. This is essential and urgent for those Wildlife Corridors which allow wildlife to achieve essential connectivity between the Chichester Harbour AONB and the South Downs National Park.

10. Biodiversity Policy NE5 - This is an absolute nonsense. If biodiversity is going to be harmed there should be no ability to mitigate or for developers to be able to buy their way out of this situation. This mindset is exactly why we are seeing a significant decline in biodiversity in the District which should be a rich in biodiversity area and why the World Economic Forum Report (2023) cites the UK as one of the worst countries in the world for destroying its biodiversity.

11. In many cases as set out in the Policies the strategic requirements lack being SMART in nature – particularly the M Measurable. These need to be explicit and clear: “you get what you measure”.

12. 65% of the perimeter of the District of Chichester south of the SDNP is coastal in nature. The remainder being land-facing. Policy NE11 does not sufficiently address the impact of building property in close proximity to the area surrounding the harbour, something acknowledged by the Harbour Conservancy in a published report in 2018 reflecting upon how surrounding the harbour with housing was detrimental to it long-term health. And here we are 5 years on and all of the organizations that CDC are saying that they are working in collaboration with, to remedy the decline in the harbour’s condition, are failing to implement the actions necessary in a reasonable timescale. CDC are following when they should be actually taking the lead on the issue. Being followers rather than leaders makes it easy to abdicate responsibility. There must be full and transparent accountability.

13. The very significant space constraints for the plan area must be taken into account. The standard methodology need no longer apply where there are exceptional circumstances and we are certain that our District should be treated as a special case because of the developable land area is severely reduced by the South Downs National Park (SDNP) to the north and the unique marine AONB of Chichester Harbour to the south. A target of 535dpa is way too high. This number should be reduced to reflect the fact that only 30% of the area can be developed and much of that is rural/semi-rural land which provides essential connectivity for wildlife via a number of wildlife corridors running between the SDNP and the AONB. Excessive housebuilding will do irretrievable damage to the environment and lead to a significant deterioration in quality of life for all who reside within the East / West corridor.

14. Many of the sites identified in the Strategic & Area Based Policies could result in Grade 1 ^ 2 farmland being built upon. The UK is not self-sufficient in our food security. It is short-sighted to expect the world to return to what we have come to expect. Our good quality agricultural land should not all be covered with non-environmentally friendly designed homes.

Attachments:

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Representation ID: 5911

Received: 17/03/2023

Respondent: GoVia Thameslink Railway

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

8.14 Package of measures described are a waste of money. For less investment cost greater accessibility can be achieved by investing in active travel infrastructure to increase viability of local businesses, reducing the need for people to travel out of their local communities, and introducing bus priority measures to facilitate more better bus reliability, including better connectivity with the railway.

Full text:

See attached.