Chichester Local Plan 2021 - 2039: Proposed Submission

Policy H1 Meeting Housing Needs

Representation ID: 5111

Received: 16/03/2023

Respondent: Levanter Developments Limited

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

It is not considered that the Council has justified the extent of the under supply of housing against the established housing need.

Full text:

I write in response to the regulation 19 consultation version of the Chichester Local Plan 2021-2039 in our capacity as promoters of Ansells Yard, Kirdford Road, Wisborough Green.

Conclusions
There are several concerns on the soundness of the plan in terms of whether it is effective, justified, positively prepared or consistent with national policy in accordance with paragraph 35 of the NPPF.
It is not considered that the Council has justified the extent of the under supply of housing against the established housing need. There are significant concerns over the delivery of housing from the strategic allocations within the unjustified timescales as set out within the trajectory contained in the plan.

Levanter will continue to make further representations on the deliverability of the site as part of the plan making progress.

Attachments:

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Policy H2 Strategic Locations/ Allocations 2021 - 2039

Representation ID: 5118

Received: 16/03/2023

Respondent: Levanter Developments Limited

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

There are significant concerns over the delivery of housing from the strategic allocations within the unjustified timescales as set out within the trajectory contained in the plan.

More specifically, in relation to Land West of Chichester(A6) and Tangmere SDL, neither site has outline permission. Delivery of units from both sites in a little over 5 years from Plan adoption is wholly unachievable. No evidence to justify how this timeframe would be achieved is presented. It is considered that the trajectory is unreliable as a result.

In relation to new strategic sites A11, A8, A10, A4 and A5 it is considered that the anticipated delivery from these allocations is highly ambitious and lacks any justification; planning permission is still required and the lead in time to delivery is generally longer for strategic sites of this size.

Full text:

I write in response to the regulation 19 consultation version of the Chichester Local Plan 2021-2039 in our capacity as promoters of Ansells Yard, Kirdford Road, Wisborough Green.

Conclusions
There are several concerns on the soundness of the plan in terms of whether it is effective, justified, positively prepared or consistent with national policy in accordance with paragraph 35 of the NPPF.
It is not considered that the Council has justified the extent of the under supply of housing against the established housing need. There are significant concerns over the delivery of housing from the strategic allocations within the unjustified timescales as set out within the trajectory contained in the plan.

Levanter will continue to make further representations on the deliverability of the site as part of the plan making progress.

Attachments:

Object

Chichester Local Plan 2021 - 2039: Proposed Submission

Policy H3 Non-Strategic Parish Housing Requirements 2021 - 2039

Representation ID: 5125

Received: 16/03/2023

Respondent: Levanter Developments Limited

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

The allocation for 75 dwellings to Wisborough Green is supported as the village is one of the most sustainable locations of all of the parishes/service villages

The overall strategy is highly dependent on the delivery of housing from Neighbourhood Plan areas. It is considered that this approach allows for little mitigation or alternatives should delivery not come forward.

Change suggested by respondent:

In order for the plan to be considered ‘positively prepared’ and ‘justified’ it is recommended that additional wording is added to policy H3 to state that individual planning applications can come forward on sustainable sites outside of existing settlement boundaries in parishes should delivery not come forward within the first five years of the plan period. Priority should be given to any sites already identified within draft versions of Neighbourhood Plans.

Priority consideration should be given to the proposed sites HWG0004, HWG0019 (Ansells Yard) and HWG0022, proposed for allocation in a draft Neihgbourhood Plan Review.

Full text:

I write in response to the regulation 19 consultation version of the Chichester Local Plan 2021-2039 in our capacity as promoters of Ansells Yard, Kirdford Road, Wisborough Green.

Conclusions
There are several concerns on the soundness of the plan in terms of whether it is effective, justified, positively prepared or consistent with national policy in accordance with paragraph 35 of the NPPF.
It is not considered that the Council has justified the extent of the under supply of housing against the established housing need. There are significant concerns over the delivery of housing from the strategic allocations within the unjustified timescales as set out within the trajectory contained in the plan.

Levanter will continue to make further representations on the deliverability of the site as part of the plan making progress.