Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Search representations

Results for Elivia Homes search

New search New search

Comment

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Figure 2 - Framework

Representation ID: 7692

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Representation Summary:

In principle we support the inclusion of the site within the revised Southbourne settlement boundary and its contribution to sustainable development opportunities in Southbourne, consistent with the 'Effective' soundness test which requires a plan's strategy to be deliverable over the plan period. However, the infrastructure costs must reflect the scale of the site, not the scale of the allocation.

Attachments:

Comment

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Connect new and existing

Representation ID: 7693

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Representation Summary:

Support the DPD’s overarching sustainable travel objectives (paragraphs 22‑25) of minimising need to travel and maximising sustainable and active travel modes, including the specific ambition to improve the comfort and safety of those walking and cycling on Cooks Lane, Priors Leaze Lane and Inlands Road, and recognises the identification of new pedestrian and cycle route adjacent to Cooks Lane. Support of the objectives in principle is subject to DPD adopting a proportionate and evidenced approach to how the costs of delivering them are apportioned between the principal development areas and smaller non-allocated sites such as ours.

Attachments:

Object

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Appendix A – Infrastructure Delivery Plan (IDP) Update

Representation ID: 7694

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

We object to the wording in Appendix A that appears to apportion a share of strategic infrastructure costs to our clients site; contributions should be secured through site‑specific planning obligations - namely, the delivery of pedestrian and cycle linkages within and from the Site, together with a financial contribution towards the railway footbridge (agreed in context of a planning application rather than through an allocation-wide document).

Attachments:

Object

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Policy SA1 - East of Southbourne

Representation ID: 7695

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

We object to the DPD wording used to characterise the site's delivery timing as being deferred to a 'later stage', which can undermine the deliverability case our client otherwise supports. These are objections to specific wording, not to the principle of the allocation or the objectives it pursues. Our client's Site will make a proportionate contribution to necessary infrastructure
costs taking account of its unique accessibility / infrastructure-based improvements.

Attachments:

Object

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Appendix A – Infrastructure Delivery Plan (IDP) Update

Representation ID: 7696

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

Central issue raised is proportionality. Do not object to contributing towards infrastructure that is necessary to make the development accessible in planning terms, directly-related to the development, and fairly and reasonably related in scale and kind. Objection is to any approach that would apportion a share of the strategic infrastructure costs calculated by reference to the scale of the principal allocation as a general funding tax, rather than by reference to the scale and impact of development actually proposed on the site itself. Not just a matter of viability judgement, but is also directly relevant to soundness of DPD.

Attachments:

Object

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

As part of the development

Representation ID: 7697

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Legally compliant? Not specified

Sound? Not specified

Representation Summary:

Specific concern - the footbridge entry in IDP. Do not object to principle of footbridge, but Appendix A treats the Site as a source of contribution on the same basis as the strategic allocation, when the Site's contribution should instead be secured through the site-specific planning obligations. Appendix A does not meet 122 of the CIL Regulations and p.58 of the NPPF. Willingness to contribute towards footbridge was, and remains, predicated on that contribution representing the entirety of the Site's infrastructure contribution. No further financial contribution towards other items identified in IDP would be sought.

Attachments:

Object

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Policy SA1 - East of Southbourne

Representation ID: 7698

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Legally compliant? Not specified

Sound? No

Representation Summary:

Object to the wording relating to 'number of potential development sites which may come forward at a later stage' with Fig.2 including clients site using equivalent terminology. The site being capable of contributing to delivery should not be fixed by DPD's wording, into a delivery timescale that neither reflects clients intentions nor has been tested against any actual planning application.

Attachments:

Object

Southbourne Allocation Development Plan Document - Regulation 19 Consultation

Policy SA1 - East of Southbourne

Representation ID: 8143

Received: 16/07/2026

Respondent: Elivia Homes

Agent: Luken Beck MDP Ltd

Legally compliant? Not specified

Sound? No

Representation Summary:

Do not object to Site being identified separately from the principal development areas relied upon to meet the 800-dwelling requirement, and recognise those areas perform a distinct function within the DPD's overall strategy. Concern is with specific characterisation of the Site's delivery timing as inherently deferred to a 'later stage' which risks being relied upon to resists or delay a future planning application on the Site regardless of merits of any application and clients own intentions for delivery. This consequence is neither intended nor necessary.