Policy AL11: Hunston Parish

Showing comments and forms 61 to 90 of 143

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1536

Received: 07/02/2019

Respondent: Natural England

Representation Summary:

Natural England notes that the HRA states that Hunston connects to Pagham WwTW. The Examination of the Arun Local Plan concluded that the headroom at Pagham WwTW would not support all of the housing allocations in Pagham, so connections to other treatment works in Arun were needed. Natural England would not support increasing the discharge consent at Pagham WwTW due to impacts on the SPA/Ramsar. Therefore, there is likely to be a significant effect from the Hunston allocation, in combination with planned development in Arun.

Clause 9 should read 'run-off into a designated site' and include waste water quality impacts.

Full text:

Natural England notes that the HRA states that Hunston connects to Pagham WwTW. The Examination of the Arun Local Plan concluded that the headroom at Pagham WwTW would not support all of the housing allocations in Pagham, so connections to other treatment works in Arun were needed. Natural England would not support increasing the discharge consent at Pagham WwTW due to impacts on the SPA/Ramsar. Therefore, there is likely to be a significant effect from the Hunston allocation, in combination with planned development in Arun.

Clause 9 should read 'run-off into a designated site' and include waste water quality impacts.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1537

Received: 07/02/2019

Respondent: Mr David Betts

Representation Summary:

1.Planning Policy. There is no historic or current rationale for 200 houses.
2.Housing. The 200 dwellings proposed do not reflect the local need.
3.Traffic. The B2145, B2166 and A27 are inadequate. Chichester Free School added unplanned traffic. Additional housing planned for Selsey and Pagham. Traffic increases significantly in summer.
Air Pollution. Measured levels are approaching health warning status along the A27 and environs.
4.Public Open Space and Play Areas. Any development needs to take into account village needs, existing and future.
5.Detailed consideration of the impact on surrounding landscape. Proposals include building on green sites adjacent to existing properties.

Full text:

1.Planning Policy.There is no historic or current rationale for 200 houses.The local housing need is much lower.
The definition of "small development" is not pertinent to the proposed addition.

2. Housing.The 200 dwellings proposed do not reflect the local need. The proposal does not take into account the rural nature of the village and farming use.

3. Traffic. The B2145, B2166 and A27 are inadequate.Chichester Free School has added unplanned traffic, Additional housing is planned for Selsey and Pagham. Pagham is in Arun but has very significant proposed housing numbers. Traffic increases significantly in summer. The inadequacy of the A27 means a lot of traffic will seek alternative routes.
3 continued. Air Pollution. Measured levels are approaching health warning status along the A27 and environs.

4. Public Open Space and Play Areas. Any development needs to take into account village needs, existing and future,

5. Detailed consideration of of the impact on surrounding landscape.
Proposals include building on green sites adjacent to existing properties.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1562

Received: 07/02/2019

Respondent: Mr David Betts

Representation Summary:

6. Opportunities for the expansion and provision of green infrastructure etc
7. Adverse impact on nature conservation.
9. Sufficient capacity be available within sewer capacity etc
10. Infrastructure and community facilities. Schools, healthcare provision and transport provision are all at very high capacity.
11. West Sussex Minerals Plan. Ensure mineral quarrying does not impinge on residential areas.

Full text:

6. Opportunities for the expansion and provision of green infrastructure etc
7. Adverse impact on nature conservation.
9. Sufficient capacity be available within sewer capacity etc
10. Infrastructure and community facilities. Schools, healthcare provision and transport provision are all at very high capacity.
11. West Sussex Minerals Plan. Ensure mineral quarrying does not impinge on residential areas.

Support

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1565

Received: 07/02/2019

Respondent: Mr David Betts

Representation Summary:

*8. Be planned with special regard to the need to mitigate potential impacts etc
Agreed. Special attention to quality of water run off to local ponds and low lying areas.

Full text:

*8. Be planned with special regard to the need to mitigate potential impacts etc
Agreed. Special attention to quality of water run off to local ponds and low lying areas.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1577

Received: 07/02/2019

Respondent: Mrs Debbie Barnes

Representation Summary:

The fields surrounding Hunston Conservation Area, put forward by CDC are unsuitable for development, there is a flood risk 3 on the land west from this area towards the road and in Church lane itself. Access to the site would cross these Flood Risk 3 zones. Building works around HCA would have a negative impact on the area, both visually and cause serious disruption to the wildlife living in the area (eg Water voles). I believe that there are 3 main areas to be considered within the village for building houses, as mentioned in the representation.

Full text:

I object to the 200 houses that are to be imposed on a small rural service village of Hunston. Hunston can be found within both the Pagham Harbour Buffer Zone and Chichester Harbour Buffer Zone. I object to the building of any houses within at least a field's distance (an acre or more) of Hunston Conservation Area as this would be detrimental to arguably the most attractive part of Hunston, with the most historical interest.
The Conservation area has been left free from development, because of the very serious issues of flooding. In the last 20 years the lane has become a 'river' from run off at least 3 times. I have stood by number 2 Church lane and not been able to walk down the lane towards the B2145. Often, on the way to and from school my children have had to wade through the lake that has formed between Spire Cottage and Number 2 Church Lane. I have also broken down in this pool of water (even in a galaxy the water came up to the sill of the car). A tractor had to pull me out and the engine was ruined. So, I object to any changes made to lane itself, backed with evidence from the Environment Agency which shows that Church Lane is a Level 3 Flood risk from Run Off.
I also object to building works here, as the lane itself is a Conservation Area which should be kept as a pleasant quiet walk, for the enjoyment of residents of Hunston, Ramblers and people with buggies or even disabled access. Any new housing would have a detrimental visual impact on the area, not in keeping with the heritage of Hunston.
I object to any building works to the west of the Conservation Area towards the road. The fields in this area are also designated Flood Risk 3 (which states that no building work should be permitted), because the flooding will only get worse from sea level rising in the future and any access to these fields would have to cross Bremere Rife. Building on these fields west of Hunston Conservation Area would be very detrimental, as they are serious flood risk zones. "The main drainage network through the Manhood Peninsula is via a series of Rifes 3, and the majority of local ditches connect into these Rifes before discharging into the Chichester Harbour, Pagham Harbour, Medmerry re-alignment scheme, or directly to the sea. To the east of the Peninsula the Bremere Rife, Forebridge Rife, Keynor Rife and Pagham Rife4 all drain towards Pagham Harbour, which is gradually silting up and has been the subject of a study by Royal Haskoning in 2005 (see Section 3.3.3.1 for more details). These Rifes drain through a series of small settlements. As the Rifes flow through these settlements there are often significant constrictions to flow (e.g. due to the presence of culverts under driveways and highways). A specific example of this is the culverted sections of the Bremere Rife through Hunston"
www.westsussex.gov.uk/media/5607/manhood_peninsula_swmp_final_report.pdf
The single track is adequate for the small number of residents and the movement of farm vehicles, but not for larger numbers of vehicles. Any building on these fields would have a considerable disruption to Church Lane and any access to these fields would have to pass over Bremere Rife.
Another major objection to building near Hunston Conservation Area is that it is within the Buffer Zone for Pagham Harbour, Medmerry harbour and Chichester Harbour. It has a diverse and stable biodiversity (which may not been recorded until recently). We have grass snakes, adders, common lizard, barn owls, tawny owls, thrush, starling, deer, foxes, hares, badger, buzzards, sparrow hawk, kestrel and Kingfisher. We also have water voles in Bremere rife, the rife that crosses Church Lane and carries on along between the fields and the road. The habitat around the conservation area needs to be protected, otherwise the trauma and subsequent population of this area would have a catastrophic impact on the local environment.
I also object to our only area of Ancient Woodland being built next to. This would have considerable impact on the surrounding landscape and as such a rare habitat in this area have an extremely detrimental impact on Nature Conservation. The copse acts a protective area to wildlife and as a green corridor for wildlife movement across the peninsula.
I believe after these areas have been discounted for building works then it will be very hard to find enough suitable building sites within Hunston.

In summary the fields surrounding Hunston Conservation Area, put forward by CDC for development are unsuitable for development, because there is a flood risk 3 on the land west from the conservation area towards the road and in Church lane itself. There would be no suitable means of access to the site that didn't cross these Flood Risk level 3 zones. Building works around Hunston Conservation Area would have a negative impact on the area, both visually and from noise pollution and disruption from people and an adverse impact on nature and the wildlife living in the area. particularly the wildlife that is protected.
Building next to Hunston Copse would have a very detrimental impact on wildlife in the area. It is a very rare habitat in this part of West Sussex and acts as a roost, nesting area and protection from people.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1612

Received: 07/02/2019

Respondent: Mrs J Rose

Representation Summary:

I believe this plan will irrevocably change the character of this area. Hunston cannot sustain such an increased load on its limited infrastructure - the traffic is already at dangerous levels and pollution levels climbing with the addition of the houses in Farm Close. We have noticed that the drainage system can barely cope as it is. I am against this plan.

Full text:

I believe this plan will irrevocably change the character of this area. Hunston cannot sustain such an increased load on its limited infrastructure - the traffic is already at dangerous levels and pollution levels climbing with the addition of the houses in Farm Close. We have noticed that the drainage system can barely cope as it is. I am against this plan.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1696

Received: 07/02/2019

Respondent: Kirsten Lanchester

Representation Summary:

Mitigation for "traffic impacts upon the B2145 Selsey Road" should be broadened to include impacts on the B2166 to Pagham, especially within the context of the scale of development proposed in the Western Arun area.

Full text:

Mitigation for "traffic impacts upon the B2145 Selsey Road" should be broadened to include impacts on the B2166 to Pagham, especially within the context of the scale of development proposed in the Western Arun area.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1698

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

1. Provision of high quality development etc.
The proposal to build 200 houses will increase the size of the village of Hunston by 35%. This therefore cannot be seen as a 'sustainable extension of the village' or be considered to 'be able to be well integrated with the existing settlement.' Such a development would completely change the character and nature of the village. Such an 'inappropriate development' would not 'protect the landscape, character and tranquily' of the village.
Any developemnt would need to achive the highest environmental standards.

Full text:

1. Provision of high quality development etc.
The proposal to build 200 houses will increase the size of the village of Hunston by 35%. This therefore cannot be seen as a 'sustainable extension of the village' or be considered to 'be able to be well integrated with the existing settlement.' Such a development would completely change the character and nature of the village. Such an 'inappropriate development' would not 'protect the landscape, character and tranquily' of the village.
Any developemnt would need to achive the highest environmental standards.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1708

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

2. A range of types, sizes and tenures of residential accommodation etc..
Hunston has one of the highest percentage (of village population) of people on housing benefit in the area. Whist a mix of population is to be commended, hitherto it has meant that the village has received a lower grant from the district council, leaving our rates corresondingly higher.

Full text:

2. A range of types, sizes and tenures of residential accommodation etc..
Hunston has one of the highest percentage (of village population) of people on housing benefit in the area. Whist a mix of population is to be commended, hitherto it has meant that the village has received a lower grant from the district council, leaving our rates corresondingly higher.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1719

Received: 07/02/2019

Respondent: Mrs Zoe Neal

Representation Summary:

Alter Hunston AL11 as a Service Village and place in Rest of the Plan area

Agree with comments from Hunston Parish Council

Full text:

Alter Hunston AL11 as a Service Village and place in Rest of the Plan area

Agree with comments from Hunston Parish Council

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1726

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

3 Provision of sui....and securing necessary off-site improvements (including highways) to promote sustainable transport options;

The current transport system cannot cope.
The A27 is a disgrace to the city of Chichester; access from the B2145, the 4th busiest B road in the country, and the B2166 is impossible during rush hours. The situation is exacerbated by the Free School leading to long queues back into Husnton on the B2145 and along the B2166 beyond Runcton. The traffic queues, of course, get even worse in the summer. The A27 will be more at a standstill with additional cars and lorries.

Full text:

3 Provision of sui....and securing necessary off-site improvements (including highways) to promote sustainable transport options;

The current transport system cannot cope.
The A27 is a disgrace to the city of Chichester; access from the B2145, the 4th busiest B road in the country, and the B2166 is impossible during rush hours. The situation is exacerbated by the Free School leading to long queues back into Husnton on the B2145 and along the B2166 beyond Runcton. The traffic queues, of course, get even worse in the summer. The A27 will be more at a standstill with additional cars and lorries.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1734

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

4.Provision of on-site public open space and play areas;

The development needs to take into account, develop further and compliment the additional facilities ( the recreation ground and village hall) and and not be a token gesture or 'add on' by a developer. These should be suitable for the population of the entire village and be agreed by the village thorugh its Neighbourhood Plan.

Full text:

4.Provision of on-site public open space and play areas;

The development needs to take into account, develop further and compliment the additional facilities ( the recreation ground and village hall) and and not be a token gesture or 'add on' by a developer. These should be suitable for the population of the entire village and be agreed by the village thorugh its Neighbourhood Plan.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1739

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

5. Detailed consideration of the impact of development on the surrounding landscape;
Any development needs to respect the existing rural nature of the village and maintain the village's separation from the city. Views and fields therefore should be maintained.

Full text:

5. Detailed consideration of the impact of development on the surrounding landscape;
Any development needs to respect the existing rural nature of the village and maintain the village's separation from the city. Views and fields therefore should be maintained.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1741

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

6.Opportunities for the expansion and provision of green infrastructure into the wider countryside including between settlements and facilities;

As a village, of course we want to retain this.

Full text:

6.Opportunities for the expansion and provision of green infrastructure into the wider countryside including between settlements and facilities;

As a village, of course we want to retain this.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1747

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

7.Demonstration that development would not have an adverse impact on the nature conservation interest of identified sites and habitats;

The proposed 15 m margin around the ancient woodland (Hunston Copse) is insufficient properly to conserve the site.

Full text:

7.Demonstration that development would not have an adverse impact on the nature conservation interest of identified sites and habitats;

The proposed 15 m margin around the ancient woodland (Hunston Copse) is insufficient properly to conserve the site.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1748

Received: 07/02/2019

Respondent: Mr Dominic Stratton

Representation Summary:

This makes no provision for the road infrastructure impact of a further 200 dwellings onto the A259 and A27 and will impact the transport report.

Full text:

This makes no provision for the road infrastructure impact of a further 200 dwellings onto the A259 and A27 and will impact the transport report.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1759

Received: 07/02/2019

Respondent: Mrs Claire Stratton

Representation Summary:

This makes no provision for the road infrastructure impact of a further 500 dwellings onto the A259 and A27 and will impact the transport report. Unless this is adequately addressed in future iterations of the plan I will wish to raise this with the examiner at the appropriate juncture.

Full text:

This makes no provision for the road infrastructure impact of a further 500 dwellings onto the A259 and A27 and will impact the transport report. Unless this is adequately addressed in future iterations of the plan I will wish to raise this with the examiner at the appropriate juncture.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1761

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

9. Demonstration that sufficient capacity will be available within the sewer network, including waste water treatment works, to accommodate the proposed development;
It has been suggested that the sewer system, contrary to obvious responses from the provider, Southern Water, are not currently adequate, let alone with more pressure on them. Surface water in such a high water table area will increase problems and impact on the sewage network.

Full text:

9. Demonstration that sufficient capacity will be available within the sewer network, including waste water treatment works, to accommodate the proposed development;
It has been suggested that the sewer system, contrary to obvious responses from the provider, Southern Water, are not currently adequate, let alone with more pressure on them. Surface water in such a high water table area will increase problems and impact on the sewage network.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1767

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

10. Provision of infrastructure and community facilities in accordance with the most up to date Infrastructure Delivery Plan;
Comment has already been made on the already overloaded B2145, the 4th busiest B road in the country, and the impact any additional housing and subsequent traffic will have on this road, the B2166, where the two roads meet in Hunston and their impact on the already lamentable and shaming A27.

Full text:

10. Provision of infrastructure and community facilities in accordance with the most up to date Infrastructure Delivery Plan;
Comment has already been made on the already overloaded B2145, the 4th busiest B road in the country, and the impact any additional housing and subsequent traffic will have on this road, the B2166, where the two roads meet in Hunston and their impact on the already lamentable and shaming A27.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1770

Received: 07/02/2019

Respondent: Ms Charlotte Joseph

Representation Summary:

11. Provisions of the West Sussex Minerals Plan, and associated guidance, in relation to the site being within a defined Minerals Safeguarding Area.
Make sure account is taken of all facilites and the residential areas.

Full text:

11. Provisions of the West Sussex Minerals Plan, and associated guidance, in relation to the site being within a defined Minerals Safeguarding Area.
Make sure account is taken of all facilites and the residential areas.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 1849

Received: 07/02/2019

Respondent: Mr Angus Eickhoff

Representation Summary:

Object to the proposal to construct further dwellings on the Manhood Peninsular: potential to lead to severe degradation of the local environment/ increased traffic congestion. Indeed, in these circumstances, the residents are put at some risk owing to the difficulty thus presented for access by the emergency services. The situation might be relieved by the construction of new or improved roads but this will only lead to increased congestion on the southern access to Chichester itself. Moreover, building or upgrading the highway will lead to further degradation of the environment in a sensitive area

Full text:

I object to the proposal to construct further dwellings on the Manhood Peninsular as this has the potential to lead to severe degradation of the local environment and increased traffic congestion, which even at the present time, reaches almost total gridlock on sunny weekends. Indeed, in these circumstances, the residents are put at some risk owing to the difficulty thus presented for access by the emergency services. The situation might be relieved by the construction of new or improved roads but this will only lead to increased congestion on the southern access to Chichester itself. Moreover, building or upgrading the highway will lead to further degradation of the environment in a sensitive area. See for instance https://www.cpre.org.uk/resources/transport/roads/item/4543-the-end-of-the-road-challenging-the-road-building-consensus

(Alternative URL :- https://tinyurl.com/ycopaoyy )

Development in the sensitive region of the Manhood Peninsula and Selsey should only be permitted if there is a commitment to provide a light rail link to Chichester and which would connect with all the important transport hubs there (bus, rail) and include a park and ride facility off the A27. This is quite an expensive proposal but nevertheless, the traffic congestion already resulting on summer weekends is totally unacceptable, for both local residents and visitors alike. Moreover, the area is low lying, much of it being less than 10m above sea level. Thus it could be susceptible to problems with flooding should sea levels rise owing to climate change. Governments have outlined a willingness to examine transport solutions with an improved environmental impact. Now is the time to act.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2092

Received: 15/02/2019

Respondent: West Sussex County Council

Representation Summary:

Minerals and waste:
It is considered that the Joint Minerals Local Plan and Waste Local Plan are referenced, particularly with regards to safeguarding policies (M9, M10 and W2) and these documents and policies are given detailed consideration when allocating sites. Development at, adjacent or proximal to existing waste or mineral sites / infrastructure should be the subject to consultation with WSCC.

Full text:

West Sussex County Council Officer Level Response
Introduction
The Chichester Local Plan Review Preferred Approach sets out how the future development in the District will be shaped, excluding the area within the South Downs National Park, up to 2035. It includes the overall development strategy as well as relevant strategic policies to meet the future needs of the area and development management policies to help guide development over the plan period. The Local Plan helps to:
* choose where the development goes;
* protect the character and beauty of the area;
* provide job and housing opportunities so that children can continue to work and live locally;
* support and help to boost the local economy;
* help residents to maintain healthy and active lifestyles; and,
* make sure that there is adequate services, travel options and community facilities.

The Chichester Local Plan was adopted in July 2015. At that time, the Local Plan was approved, but the Government Inspector said that it had to be reviewed again within five years, to make sure that sufficient housing was planned to meet the needs of the area.

The first part of the review process was carried out in June 2017 with an Issues and Options consultation, in which comments were invited regarding the overall development strategy and possible development locations. The Local Plan Review: Preferred Approach is the second stage of the process. It sets out the proposed development strategy and policies for the area to meet future needs.


West Sussex County Council Officer Level Comments
This note sets out West Sussex County Council's (WSCC) officer response to the consultation on the draft Chichester Local Plan Review Preferred Approach. It highlights key issues and suggested changes to which Chichester District Council (CDC) is requested to give consideration. We will continue to work with CDC in preparation of the Local Plan Review and the Infrastructure Delivery Plan regarding WSCC service requirements in order to mitigate planned development.


Minerals and Waste
A steady and adequate supply of minerals and the achievement of sustainable waste management can help to achieve a District or Borough Council's goals in relation to the economy, housing, transport, communications, strategic infrastructure and the environment. Therefore, District and Borough Local Plans should recognise the importance of minerals and waste issues as relevant to the scope of their overall strategies.

We welcome the reference to the adopted Minerals and Waste Local Plans and safeguarding in the document and the requirements in policies where a site is located within a minerals safeguarding area, or near to a safeguarded waste site. There are some missing references to safeguarding of minerals and waste sites for some of the proposed allocations, set out below and request that these references are added. It is also requested that 'Joint' is added into the references for the Joint Minerals Local Plan through the document.

Policy W23 of the Waste Local Plan applies to all Districts & Boroughs, regarding waste management within development and should be referenced in the Chichester Local Plan Review.

AL3 East of Chichester
The site is to the north of the Fuel Depot site allocation in the Waste Local Plan (Policy W10) for a built waste facility as part of a comprehensive redevelopment of the site (including complimentary non-waste uses). The East of Chichester allocation is the land to the north, bisected by the railway line, of the Fuel Depot. Reference should be made to giving consideration to the allocation, and therefore its safeguarding.

AL4 Westhampnett/North East Chichester
Reference should be made to minerals safeguarding, for consistency with other allocations, as within the sharp sand and gravel safeguarding area.

AL5 Southern Gateway
Reference should be made to the mineral infrastructure safeguarding policy M10 as within 200m of the Chichester Railhead.

AL6 South-West of Chichester
Reference should be made to the mineral infrastructure safeguarding policy M10 as within 300m of the Chichester Railhead.

AL7 Highgrove Farm Bosham
Remove reference to minerals safeguarding as the site is not within the safeguarding or consultation area.

AL12 Park Farm Selsey
Reference should be made to minerals safeguarding as site is within the sharp sand and gravel safeguarding area.

Neighbourhood plan allocations
Sites are yet to be allocated though neighbourhood plans. It is considered that the Joint Minerals Local Plan and Waste Local Plan are referenced, particularly with regards to safeguarding policies (M9, M10 and W2) and these documents and policies are given detailed consideration when allocating sites. Development at, adjacent or proximal to existing waste or mineral sites / infrastructure should be the subject to consultation with WSCC.


Connectivity and Sustainable Travel
The County council has worked with the District Council on the preparation of the transport evidence base study undertaken by Peter Brett Associates for the District Council. The recommended transport mitigation strategy, as assessed using the Chichester Area Transport Model has been demonstrated to be capable in principle to prevent the development from resulting in severe residual cumulative impacts on the highways and transport network. However, the recommended strategy has several risks to deliverability and acceptability associated with it, which require further work to be undertaken to demonstrate that the strategy can be implemented in its current form to provide the forecasted mitigation to travel conditions.

There are three locations where new highway alignments are proposed outside of existing highways boundaries. Two of these may include significant earthworks or structures to be delivered, being Stockbridge Link Road and Terminus Road diversion. The cost of the mitigation strategy exceeds a figure which could reasonably be supported by the value of the proposed development developer contributions alone, therefore the delivery of the strategy will depend upon securing of external grant funding to top up developer contributions. WSCC will work with the District Council in supporting and or applying for funding, the District Council needing to secure Highways England to support funding applications for A27 improvements. The proposed junction designs for the A27 Stockbridge and Whyke roundabouts include bans to well used right turn movements off the Chichester A27 bypass which result in significant forecast changes to traffic flows on local roads in the south of Chichester and on the Manhood Peninsular.

There is a need to ensure the land outside the highway boundary is available and the plan should set out how this land will be acquired to deliver the measures, it may be that a commitment to use, if required, and therefore reference to CPO be made in the policy.

Funding for the mitigation strategy is uncertain. It is considered that the Plan should set out how it will deal with this uncertainty. This could include trigger points in the monitoring framework to trigger a change of approach or alternative options to deliver the required development.

These factors mean that feasibility work is necessary to be undertaken prior to Plan submission, to reduce as far as practicable risks to costs, land take, impacts and deliverability of the proposed transport strategy in order to show that the strategy can be implemented within the plan period and that the funding strategy will be sufficient to meet the design requirements. In particular the following will need to be addressed:

* Statutory undertakers equipment under the roads junctions to be impacted.
* Extent of earthworks required to create a vertical and horizontal alignment compliant with design standards. Design audit to identify any required departures from standard.
* Designing for drainage and flooding issues, including compliance with the WSCC LLFA Policy for the Management of Surface Water, November 2018.
* Designs for structures to cross watercourses - Stockbridge Link Road
* Design should include suitable provision for rights of way and footway crossings
* Scoping for whether and at what level further Environmental Impact Assessment will be required.
* Stage 1 Road safety Audit, designers response report and resulting amendments to designs.
* Land take required after feasibility level designs have been developed and availability of required land.
* Wophams Lane - impacts of forecast changes to flow patterns to take B2201 southbound traffic on requirements for highway width, alignment, footway provision and junctions with A286 Birdham Road and B2201 Selsey Road; design solution required.
* Quarry Lane, Kingsham Avenue /Road, Terminus Road; impacts of forecast flow changes on highway users, residential and commercial frontagers and measures to manage through traffic whilst maintaining local access

Sustainable transport measures will also be required to mitigate planned development. These will be identified through more detailed assessments of sites including pre-application consideration. Funding will need to be identified through development and other sources as well in some cases.

Public Rights of Way
There is support for the Local Plan Review's approach to Public Rights Of Way (PROW), not just for the potential to impact on existing public off-road access but also the opportunity it brings to enhance this access for the benefit of future residents, communities and visitors. PROW deliver benefits for personal health and wellbeing; sustainable transport; reduction of air pollution and road congestion; are able to support local economies; and they connect communities.
WSCC PROW welcomes several aspects of the Vision statement, which give support to the protection and enhancement of the PROW network, and provision of safe and convenient off-road access opportunities for residents and visitors:

* Pursue a healthy lifestyle and benefit from a sense of well-being supported by good access to education, health, leisure, open space and nature, sports and other essential facilities;
* Live in sustainable neighbourhoods supported by necessary infrastructure and facilities;
* Move around safely and conveniently with opportunities to choose alternatives to car travel.

The Local Plan Strategic Objectives offer further support to enhance off-road access, particularly to 'Encourage healthy and active lifestyles for all, developing accessible health and leisure facilities and linked green spaces'. However, the objective to 'Achieve a sustainable and integrated transport system through improved cycling networks and links to public transport' should recognise walking also as an important mode for many people; some strategic enhancements will significantly improve walkers' safety and convenience.

It is considered that West of Chichester the A259 could act as a corridor for increased volumes of non-motorised access, particularly cycling. Improvement of the existing on-road facility and development of a various 'feeder' routes to connect with the many settlements, perhaps using quiet lanes in places, would encourage cycling particularly to be a natural alternative to vehicle use. Policy S18: Integrated Coastal Zone Management for the Manhood Peninsula, gives regard to such an ambition in stating it will 'Improve infrastructure to support sustainable modes of transport, especially cycle ways, bridleways and footpaths, including the National Coastal Footpath'.

The National Planning Policy Framework (NPPF) Open Space and Recreation, para 97b) states:
the loss resulting from the proposed development would be replaced by equivalent or better provision in terms of quantity and quality in a suitable location.
The NPPF para 98 also states:
Planning policies and decisions should protect and enhance public rights of way and access, including taking opportunities to provide better facilities for users, for example by adding links to existing rights of way networks including National Trails.'
There is support for Policy S20: Design, that recognises these requirements in stating development 'is well connected to provide safe and convenient ease of movement by all users, prioritising pedestrian and cycle movements both within the scheme and neighbouring areas and ensuring that the needs of vehicular traffic does not dominate at the expense of other modes of transport, or undermine the resulting quality of places' and 'incorporates and/or links to high quality Green Infrastructure and landscaping to enhance biodiversity and meet recreational needs, including public rights of way'.


Education
As the local education authority, WSCC has the statutory duty to ensure that there is a sufficient supply of suitable school places to meet statutory requirements for early years, primary, secondary and sixth form provision (including up to age 25 for those with special educational needs and/or disabilities). Education infrastructure, or contributions to provide infrastructure, will be required in order to mitigate proposed development. We will continue to work with CDC in preparation of the Local Plan Review and the Infrastructure Delivery Plan regarding education and other service requirements in order to mitigate planned development.

The table below sets out the primary, secondary school and sixth form requirements to mitigate proposed development. SEE ATTACHMENT FOR TABLE

AL1 Land West of Chichester

It should be noted that phase one of this development will provide the primary school with the core of the building being built to the specification for a 2 form entry (FE) school and 1FE teaching accommodation. Phase 2 as per 6.10 on page 93 should include expansion of the primary school for the further 1FE of teaching accommodation.

AL2 Land at Shopwhyke (Oving Parish)

No update to original response for this allocation is required.

AL3 Land East of Chichester - previously South of Shopwhyke

At the current time pupil place planning indicates that there is insufficient space within the primary schools that serve this proposed development. Further capacity would be required to accommodate the development. Land for a 1 FE expandable to 2FE and pro rata share of the build costs would be required.

If numbers were to increase on the east side of the city, education provision will need to be reviewed, potentially a further 1FE may be required including land provision, this could be in the form of an expansion or a new school being built capable of expansion to 3FE.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL4 Land at Westhampnett / North East Chichester

The remaining 200 dwellings will impact on the education provision in the area, financial contributions towards expansion of existing or pro rata costs towards the expansion of the school within AL3.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL5 Southern Gateway

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from the strategic allocation of 350 dwellings in the Southern Gateway. However, consideration should be given to the cumulative impact of housing in the area Land South West of Chichester (AL6) to allocate land within the area for a 1FE expandable to 2FE primary school. Pro rata financial contributions towards the build costs would be sought from developers to mitigate their impact.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL6 Land South West of Chichester (Apuldram & Donnington Parishes)

It should be noted that the primary education provision in this area is either in Chichester City Centre which means crossing the main A27 or by travelling south towards the peninsula. Consideration should be given to the cumulative impact of further housing in the area along with the Southern Gateway allocation (AL5) to allocate land within the strategic allocation site for a 1FE expandable to 2FE primary school. Pro rata financial contributions towards the build costs would be sought from developers to mitigate their impact.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL7 Bosham

The current primary provision serving the area is at capacity, expansion of the school on its existing site is not possible. As part of the strategic allocation, it is proposed that land for a 2FE primary school be provided. The strategic allocation of 250 dwellings in isolation does not require a new school to be built. Certainty over the land allocation and sufficient funding will be key drivers in realising this proposal.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL9 Fishbourne

The primary school serving the area is currently at capacity, expansion of the school may be possible, feasibility / options appraisals would need to be undertaken.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of primary and secondary schools and sixth form if feasible and required.

AL8 East Wittering

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development.

Contributions would be required for expansion of primary and secondary schools if feasible and required.

AL10 Chidham and Hambrook area

The current primary provision serving the area is at capacity, expansion of the school on its existing site is not possible. As part of the strategic allocation, it is proposed that land for a 2FE primary school be provided. Certainty over the land allocation and sufficient funding will be key drivers in realising this proposal.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL11 Hunston

Any development within this area cannot currently be accommodated in the existing primary school at North Mundham. Further capacity would be required to accommodate the development, CDC will need to work with WSCC to determine how additional capacity in the area could be accommodated if land is to be allocated.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

AL12 Selsey

Further capacity would be required to accommodate the development. Contributions (and possibly land if required) would be sought to meet the pupil product from the development in the most appropriate form once this can be clarified.

At the current time pupil place planning indicates that there would be sufficient space to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

AL13 Southbourne

At the current time pupil place planning indicates that there is insufficient space within the primary schools that serve this proposed development. Further capacity would be required to accommodate the development. Land for a 2form entry expandable to 3FE primary school and pro rata share of the build costs would be required.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL14 Tangmere

The current allocation of 1,300 dwellings will bring forward the requirement for land for a 1FE expandable to 2FE and financial contributions would be sought to meet the pupil product from the development in the most appropriate form once this can be clarified.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

Footnote: - if all of the proposed sites were to come forward the secondary school and sixth form provision would be full in the Chichester Planning Area. Expansion of the secondary schools in the Chichester Planning Area to cater for the increased demand would need to be sought from the academy sponsors, where appropriate and the Local Authority.


Lead Local Flood Authority
The Lead Local Flood Authority (LLFA) is concerned about the approach being taken with regard to ensuring potential wastewater treatment for proposed new sustainable development.

Paragraph 8 of the NPPF states:
8. Achieving sustainable development means that the planning system has three overarching objectives, which are interdependent and need to be pursued in mutually supportive ways (so that opportunities can be taken to secure net gains across each of the different objectives):

a) An economic objective - to help build a strong, responsive and competitive
economy, by ensuring that sufficient land of the right types is available in the
right places and at the right time to support growth, innovation and improved
productivity; and by identifying and coordinating the provision of infrastructure;

Paragraph 20 of the NPPF states:
20. Strategic policies should set out an overall strategy for the pattern, scale and quality of development, and make sufficient provision for:
a) housing (including affordable housing), employment, retail, leisure and other commercial development;
b) infrastructure for transport, telecommunications, security, waste management, water supply, wastewater, flood risk and coastal change management, and the provision of minerals and energy (including heat);

In the LLFAs view, the Local Plan Review is not setting out an overall strategy for the pattern, scale and quality of development in relation to arrangements for wastewater management. The LLFA considers that CDC needs to go further in incorporating within the Local Plan Review how this provision is being made.


Additional Policy Comments

Policy S12: Infrastructure Provision
Support the requirement that all development must provide or fund new infrastructure, facilities and services required, both on and off-site (including full fibre communications infrastructure) as a consequence of the proposal. The explicit reference to full fibre communications infrastructure is supported as this will provide gigabit-capable and future-proofed services to all development, existing and new. The reference to provision of facilities and services on and off-site is also supported as in the case of broadband for example, all development will be adequately equipped with the necessary infrastructure installed for the purposes of connecting to full fibre gigabit-capable broadband services. This policy supports the County Council's aim for increased digital infrastructure that will provide for gigabit-capable broadband and future technologies such as 5G.

Support the reference to safeguarding educational facilities under section 3 of the policy.

The policy includes the requirement to 'Facilitate accessibility to facilities and services by a range of transport modes'. PROW can offer vital access means for walkers and cyclists, such as for employment land use (e.g. commuting by bicycle) and in support of the high street, both for employees and customers. IT is considered that this Policy, also Policy S13: Chichester City Development Principles, should aim to encourage such access to be the natural and preferred modes of access, thereby helping achieve the benefits previously described. It is noted Policy S14: Chichester City Transport Strategy, does acknowledge cycling and walking and lends support to their improvement.

The supporting text, paragraph 4.81 makes reference to the Strategic Infrastructure Package (SIP). It is requested that this wording is removed and replaced with West Sussex County Council identifies service infrastructure requirements necessary to support new and existing communities, where strategic development and growth is proposed in Local Plans. These are required to deliver the County Council's statutory responsibilities, strategic objectives and current policy and feed into the preparation of the Infrastructure Delivery Plan.


Policy S13: Chichester City Development Principles
This policy, like policy S12, it is considered should aim to encourage such access to be the natural and preferred modes of access, thereby helping achieve the benefits previously described. It is noted Policy S14: Chichester City Transport Strategy, does acknowledge cycling and walking and lends support to their improvement.


Policy S23: Transport and Accessibility
The policy and supporting text paragraphs 5.15 - 5.33 refer to Transport Infrastructure. Understandably much consideration is given to the A27 around Chichester; however, in addition to seeking new infrastructure from new development, it is recommended support in principle is given to maximising the value of existing infrastructure so as to facilitate off-road user modes accessing either side of the A27.


S24: Countryside
Supporting text paragraphs 5.34 - 5.43, acknowledges 'it is necessary to provide for the social and economic needs of small rural communities, and enable those who manage, live and work in the countryside to continue to do so'. It is recognised in para 7.205, supporting text to policy SM35 Equestrian Development, the high numbers of liveried and stabled horses. A considerable network of businesses are supported by such a high equine population, and in addition to financial value within the local community there is considerable benefit in terms of health and wellbeing of individuals. It is suggested that Policy S24: Countryside, could recognise this specifically.


S27: Flood Risk Management
Supporting text paragraph 5.54, requested amendments underlined - as a consequence of the rise in sea levels and storm surges, parts of the plan area will be at increased risk from coastal erosion, groundwater, fluvial and/or tidal flooding. Hard defences may not be possible to maintain in the long term, therefore development needs to be strongly restricted in areas at risk to flooding and erosion, whilst ensuring that existing towns and villages are protected by sustainable means that make space for water in suitable areas. Development must take account of the policies of the relevant shoreline management plan

Supporting text paragraph 5.58, requested amendments underlined - Built development can lead to increased surface water run-off; therefore new
development is encouraged to incorporate mitigation techniques in its design, such as permeable surfaces and Sustainable Drainage Systems (SuDS). Where appropriate, SuDS should be used as part of the linked green infrastructure network to provide multiple functions and benefits to landscape quality, recreation and biodiversity. This can be achieved through habitat creation, new open spaces and good design. SuDS should be designed to help cope with intense rainfall events and to overcome any deterioration in water quality status. In determining the suitability of SuDS for individual development sites, developers should refer to guidance published by the Lead Local Flood Authority (LLFA): West Sussex LLFA Policy for the Management of Surface Water: https://www.westsussex.gov.uk/media/12230/ws_llfa_policy_for_management_of_surface_water.pdf and, if necessary, seek further advice from the Lead Local Flood Authority LLFA.

S27 policy text requested amendments underlined for section 1 - a. through a sequential approach, taking into consideration all forms of flooding, it is located in the lowest appropriate flood risk location in accordance with the NPPF and the Chichester Strategic Flood Risk Assessment (SFRA); and

S27 policy text requested amendments underlined for section 2. Sustainable drainage systems (SuDS) will be required on major developments (10 or more dwellings or equivalent) and encouraged for smaller schemes. SUDS should be designed into the landscape of all new development and should be included as part of a District wide approach to improve water quality and provide flood mitigation. A site-specific Flood Risk Assessment will be required for sites within or adjacent to areas at risk of surface water flooding as identified in the SFRA. There should be no increase in either the volume or rate of surface water runoff leaving the site.

S27 policy text requested additional bullet point as number 4 - Clear management arrangements and funding for their ongoing maintenance over the lifetime of the development should be proposed. Planning conditions and / or obligations will be used to secure these arrangements.

S27 policy text requested amendments underlined for section 2, but would be section 5 - Development should not result in any property or highway, on or off site, being at greater risk of flooding than the 1 in 100 year storm return period, including an allowance for climate change.


Policy S29: Green Infrastructure
The Green Infrastructure policy is welcomed, including provision of new Green Infrastructure as an integral part of the development at Strategic Development Locations. It is recommended that measures are put in place to secure the long term management of such Green Infrastructure.


Policy S30: Strategic Wildlife Corridors
The identification of Strategic Wildlife Corridors and inclusion of a policy to safeguard them from development is welcomed. It is recommended that CDC promotes positive conservation management within these corridors to maximise their contribution to maintaining and enhancing biodiversity. As stated in Section 5.66, 'These corridors do not stop at the plan area boundaries.' Thus, it is recommended that CDC works in partnership with Chichester Harbour Conservancy and The South Downs National Park Authority to ensure that these Strategic Wildlife Corridors continue to provide effective corridors and connectivity across the wider landscape.

Section 5.66 refers to four Strategic Wildlife Corridors connecting Chichester Harbour with the South Downs National Park but it is noted that there is no mention of the Strategic Wildlife Corridors to the east of Chichester which connect Pagham Harbour with the South Downs National Park (as seen in Policy Map S30b). It is also noted that the maps referred to in Section 5.66, Maps 5.1 & 5.2 are missing.

WSCC and CDC promoted a Mitigated Northern Route for the A27 at Chichester as the preferred option, subject to the inclusion of important mitigation measures that are needed to make the scheme acceptable in environmental terms and the 'full southern route' as a reasonable alternative. Both routes could impact on the identified Strategic Wildlife Corridors. As currently drafted, Policy S30 would seem to prevent a mitigated northern route from coming forward in the future. Therefore, the District Council should consider whether the policy is overly restrictive (for example should it refer to 'significant adverse impacts' or 'unacceptable adverse impacts'?) and how it would be applied if a northern route for A27 were to come forward in the future.


Policy S31: Wastewater Management and Water Quality
S27 policy text requested amendments underlined for section 3, this - Where appropriate, development should contribute to the delivery of identified actions to deliver infiltration reduction across the catchment. Where appropriate development should contribute to the delivery of identified actions to deliver a reduction in the level of infiltration of groundwater into the sewer system.


Policy AL1: Land West of Chichester
AL1 policy text requested additional bullet point as number 8 - Increase capacity to attenuate surface water on site, thereby reducing the discharge flows off the site below current rates and reducing the risk of flooding to residential areas downstream.

AL1 policy text requested additional bullet point under 15 as 15 b- Provide mitigation for any loss of watercourse habitat resulting from culverting for highway provision in the development;

AL1 policy text in supporting 'improved cycle and pedestrian routes linking the site with the city, Fishbourne and the South Downs National Park', a new key link for cycling will be to Salthill Road, thereby enabling cyclists to benefit from the existing bridge crossing of the A27 for journeys to and from the west.


AL2: Land at Shopwyke (Oving Parish)
The policy acknowledges need 'for foot/cycle bridge across A27 to Coach Road'. There is also need for equestrian users to cross the A27 and WSCC PROW has received several enquiries seeking support for such infrastructure. Consideration could be given to the proposed bridge providing for all three modes.


AL3: East of Chichester (Oving Parish)
AL3 supporting text requested amendments underlined for paragraph 6.22 - The site is identified for 600 dwellings, however, there may be potential to deliver a large strategic development of 1000 dwellings, subject to further evidence, including the testing of additional growth on the local highway network and capacity of the site to provide flood risk attenuation for the increased housing density. The site should be master planned as a whole, and delivered through a phased development over a ten year period. Although the site is physically separated from the city by the A27 Chichester Bypass, the development should form a planned extension to the city, forming a new neighbourhood. This will involve opportunities to provide new facilities to serve the wider local community with good off-site access, particularly by walking and cycling to existing local facilities and facilities in the city.

AL3 policy requires exploring integrated green infrastructure with other strategic sites to the north east of the city, Tangmere and the wider countryside. It is considered that future residents will have expectations for provision of safe and convenient links towards Oving and also across the railway to link to the A259 cycle path and PROW south of the A259. It is considered that the policy should be strengthened to ensure such provision.


Policy AL4: Land at Westhampnett/North East Chichester
AL4 policy text requested amendments underlined for section 3 - Open space and green infrastructure, including a linear greenspace with public access along the Lavant Valley.

Taking into account the site-specific requirements, proposals for the site should satisfy the following requirements:

Policy AL4 policy, it is welcomed that 'provision should be made for green links to the South Downs National Park and Chichester City.' Safe and convenient walking and cycling to Lavant, from where people will access the South Downs, will provide for sustainable transport use.


Policy AL5 Southern Gateway
AL5 supporting text requested amendments underlined for paragraph 6.38 - The area has been identified as suitable for comprehensive regeneration with the aim being to make it a more attractive and welcoming gateway for the city, providing new housing, business and retail space and leisure and tourism facilities. Opportunities will be identified to improve transport links with a focus on cycling, walking and public transport and the removal of non-essential traffic from the area. There is also scope for significant public space enhancements and new landscaping incorporating blue / green infrastructure delivering multi-functional benefits.

AL5 policy text requested amendments underlined for section 5 - Provision of open space that:
* Is in accordance with Policy DM34, including retention of the existing playing pitch unless suitable re-provision is provided;
* Reinforces / enhances green and blue infrastructure consistent with Policy S29 and fully exploits the opportunities for sustainable drainage.


AL5 policy text requested amendments underlined for section 8 - Provision of both a surface and waste water management plan which demonstrates no net increase in flow to Apuldram Waste Water Treatment Works would result from this development, unless suitable alternative provision is agreed;


Policy AL6: Land South-West of Chichester (Apuldram and Donnington Parishes)
The LLFA has concerns regarding the lack of reference to flood risk constraints of the site in Policy AL6. There is reference to flood risk in paragraph 6.47. However, the policy itself makes no reference to these constraints.
The constraints arise from a combination of the following:

* Current tidal /fluvial flood risk extending from Chichester harbour to the west and up the River Lavant floodplain; (Map 1)
* Future tidal /fluvial flood risk associated with climate change; (Map 1)
* Constraints on infiltration of surface water run off because of high seasonal groundwater levels (<0.025m below the surface) (Map 2); and
* Constraints on gravity outfalls because of the low relief and long-term reduction in tidal window for discharge.

The above limits the options for how the site can be effectively drained without a step change from typically employed methods to embrace more innovative and currently expensive options e.g. blue roofs and rainwater harvesting.

The LLFA recommends that the policy sets out both the above constraints and the type of innovative drainage that will be required to achieve the development objectives for the site.



Key: Projected medium projection extent of SLR based upon 4m contour

AL6 extent

Current Flood Zone 3 extent.

Current Areas of high (1:30) surface water flood risk

Map 1 Existing and projected Tidal and surface water flood risk for AL6.

Consistent with paragraph 3.2 of the SFRA, given the high risk of flooding both now and into the future for this site, it is recommended that CDC gives consideration to the climate change maps to understand how the flood zones are predicted to change over the lifetime of the development.


Key:
AL6 boundary.

Groundwater levels are either at very near (within 0.025m of) the ground surface.

Groundwater levels are between 0.025m and 0.5m below the ground surface

Map 2 Groundwater flood risk JBA

Policy AL6 WSCC PROW considers 'necessary highway improvements to adequately mitigate the likely impacts on the highway network' to include a bridge crossing of the A27 for convenient walking and cycling access to the Terminus Road industrial estate and the city. There is an existing public footpath but, as this crosses the A27 at-grade, this will not provide the safest facility and not encourage people to minimise use of vehicles for local access. Provision of a bridge and access through the site could also establish a valuable link to the popular Salterns Way walking and cycle path. An additional link to Salterns Way should also be provided off the A286 for the benefit of Stockbridge residents as a safer alternative to the A286.


AL 7 Highgrove Farm, Bosham
The LLFA notes that the above site has the potential for a moderate risk of groundwater flooding. It is likely that this is perched groundwater draining from higher ground / springs to the north that lies in the superficial mixed sediments underlain by Lambeth Clay.


Policy AL8: East Wittering Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The policy requires 'Opportunities ... for the expansion and provision of green infrastructure into the wider countryside including between settlements and facilities'. Existing and future residents and the local visitor economy would benefit by delivery of an off-road route for walkers, cyclists and horse riders to and from the Medmerry development and towards Selsey. It is considered that Policy AL8 should aim to deliver this enhancement specifically.


Policy AL9: Fishbourne Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

It is considered that off-road cycling links to land West of Chichester (off Salthill Road) and to Bosham (off Park Lane) would benefit this community with enhanced sustainable connectivity.


Policy AL10: Chidham and Hambrook Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The policy requires 'opportunities' to develop green infrastructure and links to other communities. An opportunity, in conjunction with Highways England, exists to maximise the value of existing infrastructure by creating a new bridleway (for walkers, cyclists and horse riders) on a path using an existing A27 overbridge.


Policy AL11: Hunston Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The village is already well connected for walkers to access the surrounding countryside but there are presently no local cycling or horse riding facilities on the PROW network. A bridleway link to South Mundham (with the potential for future cycle links to Pagham and towards Bognor Regis) and to Sidlesham via the golf course and Brimfast Lane would provide residents and visitors with improved access to the countryside and services.


Policy AL12: Land North of Park Farm, Selsey
It is unclear why the policy map shows the proposed strategic allocation lies outside of the Neighbourhood Plan proposed settlement boundary. Some explanation for this anomaly would be helpful in the text.


Groundwater flood risk as depicted by JBA mapping (Brown = seasonal groundwater level lies between 0.025 and 0.5m below the surface).

The principle concern that the LLFA wishes to highlight is the need to ensure that the necessary foul sewerage infrastructure to support development is in place. It is the LLFA understanding that the Siddlesham WWTW experiences capacity issues currently, in part exacerbated by groundwater infiltration. While Policy AL12 states: Development proposals will need to demonstrate that sufficient capacity will be available within the sewer network, including waste water treatment works, to accommodate the proposed development in accordance with Policy S31.

The policy proposes only to provide 'pedestrian links between the site and new development south of Park Lane'. It is considered that cycling links should also be provided.


Policy DM8: Transport, Accessibility and Parking
The PROW network can provide vital means for communities to interact and encourage sustainable local access. The policy requirement to create 'links between new development and existing pedestrian, cycle and public transport networks' is welcomed. However, establishing links into surrounding existing development should not be overlooked also - the greater the permeability, the greater the use.


Policy DM10: New Employment Sites
Whilst mentioned earlier in the Plan in respect of a number of specific sites, this policy should specifically aim to provide, as a matter of course, suitable walking and cycling infrastructure to encourage local sustainable access. This infrastructure may need to extend outside a site boundary so as to provide safe and convenient connection to existing infrastructure. This principle should apply also to Policy DM13: Built Tourist and Leisure Development and Policy DM14: Caravan and Camping Sites.


Policy DM32: Green Infrastructure
Whilst it is recognised the policy proposes support subject to not 'dissect[ing] ... the linear network of cycle ways, public rights of way, bridleways ...', the policy could lend support to establishing new routes as part of the Green Infrastructure network itself.


Policy DM35: Equestrian Development
It is appreciated why the Plan would wish to require future equine development to be 'well related to or has improved links to the existing bridleway network'. However, this will add to the pressure of use on the existing bridleway network, which is not extensive outside of the South Downs, so will increase degradation of paths. Future developments must, therefore, accept to contribute in some way, acceptable to the local highway authority, to mitigate the additional impact to be created so all lawful users are not disadvantaged.


Policy DM29: Biodiversity
The measures to safeguard and enhance the biodiversity value of development sites are welcomed, including seeking net biodiversity gain.


Schedule of proposed changes to the policies map
S30a West of City Corridors -suggest title should be West of City Strategic Wildlife Corridors (to match S30b: East of City Strategic Wildlife Corridors. The Strategic Wildlife Corridors are depicted in different colour patterns on the two plans which is somewhat confusing.


Strategic Wildlife Corridors Local Plan Review Background Paper
Proposed Hermitage to Westbourne Strategic Wildlife Corridor
A large area depicted as Biodiversity Opportunity Area (BOA) in Fig. 1 (immediately to the south of the Rivers Ems & Meadows Local Wildlife Site, Westbourne) is in fact housing and forms part of the settlement of Westbourne. You should consider if this land should be included as having potential for biodiversity enhancement.


Glossary
Includes Sites of Nature Conservation Importance (SNCIs) but not Local Wildlife Sites (LWSs). SNCIs are now known as LWSs.

Attachments:

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2133

Received: 15/02/2019

Respondent: West Sussex County Council

Representation Summary:

Education:
Any development within this area cannot currently be accommodated in the existing primary school at North Mundham. Further capacity would be required to accommodate the development, CDC will need to work with WSCC to determine how additional capacity in the area could be accommodated if land is to be allocated.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

Full text:

West Sussex County Council Officer Level Response
Introduction
The Chichester Local Plan Review Preferred Approach sets out how the future development in the District will be shaped, excluding the area within the South Downs National Park, up to 2035. It includes the overall development strategy as well as relevant strategic policies to meet the future needs of the area and development management policies to help guide development over the plan period. The Local Plan helps to:
* choose where the development goes;
* protect the character and beauty of the area;
* provide job and housing opportunities so that children can continue to work and live locally;
* support and help to boost the local economy;
* help residents to maintain healthy and active lifestyles; and,
* make sure that there is adequate services, travel options and community facilities.

The Chichester Local Plan was adopted in July 2015. At that time, the Local Plan was approved, but the Government Inspector said that it had to be reviewed again within five years, to make sure that sufficient housing was planned to meet the needs of the area.

The first part of the review process was carried out in June 2017 with an Issues and Options consultation, in which comments were invited regarding the overall development strategy and possible development locations. The Local Plan Review: Preferred Approach is the second stage of the process. It sets out the proposed development strategy and policies for the area to meet future needs.


West Sussex County Council Officer Level Comments
This note sets out West Sussex County Council's (WSCC) officer response to the consultation on the draft Chichester Local Plan Review Preferred Approach. It highlights key issues and suggested changes to which Chichester District Council (CDC) is requested to give consideration. We will continue to work with CDC in preparation of the Local Plan Review and the Infrastructure Delivery Plan regarding WSCC service requirements in order to mitigate planned development.


Minerals and Waste
A steady and adequate supply of minerals and the achievement of sustainable waste management can help to achieve a District or Borough Council's goals in relation to the economy, housing, transport, communications, strategic infrastructure and the environment. Therefore, District and Borough Local Plans should recognise the importance of minerals and waste issues as relevant to the scope of their overall strategies.

We welcome the reference to the adopted Minerals and Waste Local Plans and safeguarding in the document and the requirements in policies where a site is located within a minerals safeguarding area, or near to a safeguarded waste site. There are some missing references to safeguarding of minerals and waste sites for some of the proposed allocations, set out below and request that these references are added. It is also requested that 'Joint' is added into the references for the Joint Minerals Local Plan through the document.

Policy W23 of the Waste Local Plan applies to all Districts & Boroughs, regarding waste management within development and should be referenced in the Chichester Local Plan Review.

AL3 East of Chichester
The site is to the north of the Fuel Depot site allocation in the Waste Local Plan (Policy W10) for a built waste facility as part of a comprehensive redevelopment of the site (including complimentary non-waste uses). The East of Chichester allocation is the land to the north, bisected by the railway line, of the Fuel Depot. Reference should be made to giving consideration to the allocation, and therefore its safeguarding.

AL4 Westhampnett/North East Chichester
Reference should be made to minerals safeguarding, for consistency with other allocations, as within the sharp sand and gravel safeguarding area.

AL5 Southern Gateway
Reference should be made to the mineral infrastructure safeguarding policy M10 as within 200m of the Chichester Railhead.

AL6 South-West of Chichester
Reference should be made to the mineral infrastructure safeguarding policy M10 as within 300m of the Chichester Railhead.

AL7 Highgrove Farm Bosham
Remove reference to minerals safeguarding as the site is not within the safeguarding or consultation area.

AL12 Park Farm Selsey
Reference should be made to minerals safeguarding as site is within the sharp sand and gravel safeguarding area.

Neighbourhood plan allocations
Sites are yet to be allocated though neighbourhood plans. It is considered that the Joint Minerals Local Plan and Waste Local Plan are referenced, particularly with regards to safeguarding policies (M9, M10 and W2) and these documents and policies are given detailed consideration when allocating sites. Development at, adjacent or proximal to existing waste or mineral sites / infrastructure should be the subject to consultation with WSCC.


Connectivity and Sustainable Travel
The County council has worked with the District Council on the preparation of the transport evidence base study undertaken by Peter Brett Associates for the District Council. The recommended transport mitigation strategy, as assessed using the Chichester Area Transport Model has been demonstrated to be capable in principle to prevent the development from resulting in severe residual cumulative impacts on the highways and transport network. However, the recommended strategy has several risks to deliverability and acceptability associated with it, which require further work to be undertaken to demonstrate that the strategy can be implemented in its current form to provide the forecasted mitigation to travel conditions.

There are three locations where new highway alignments are proposed outside of existing highways boundaries. Two of these may include significant earthworks or structures to be delivered, being Stockbridge Link Road and Terminus Road diversion. The cost of the mitigation strategy exceeds a figure which could reasonably be supported by the value of the proposed development developer contributions alone, therefore the delivery of the strategy will depend upon securing of external grant funding to top up developer contributions. WSCC will work with the District Council in supporting and or applying for funding, the District Council needing to secure Highways England to support funding applications for A27 improvements. The proposed junction designs for the A27 Stockbridge and Whyke roundabouts include bans to well used right turn movements off the Chichester A27 bypass which result in significant forecast changes to traffic flows on local roads in the south of Chichester and on the Manhood Peninsular.

There is a need to ensure the land outside the highway boundary is available and the plan should set out how this land will be acquired to deliver the measures, it may be that a commitment to use, if required, and therefore reference to CPO be made in the policy.

Funding for the mitigation strategy is uncertain. It is considered that the Plan should set out how it will deal with this uncertainty. This could include trigger points in the monitoring framework to trigger a change of approach or alternative options to deliver the required development.

These factors mean that feasibility work is necessary to be undertaken prior to Plan submission, to reduce as far as practicable risks to costs, land take, impacts and deliverability of the proposed transport strategy in order to show that the strategy can be implemented within the plan period and that the funding strategy will be sufficient to meet the design requirements. In particular the following will need to be addressed:

* Statutory undertakers equipment under the roads junctions to be impacted.
* Extent of earthworks required to create a vertical and horizontal alignment compliant with design standards. Design audit to identify any required departures from standard.
* Designing for drainage and flooding issues, including compliance with the WSCC LLFA Policy for the Management of Surface Water, November 2018.
* Designs for structures to cross watercourses - Stockbridge Link Road
* Design should include suitable provision for rights of way and footway crossings
* Scoping for whether and at what level further Environmental Impact Assessment will be required.
* Stage 1 Road safety Audit, designers response report and resulting amendments to designs.
* Land take required after feasibility level designs have been developed and availability of required land.
* Wophams Lane - impacts of forecast changes to flow patterns to take B2201 southbound traffic on requirements for highway width, alignment, footway provision and junctions with A286 Birdham Road and B2201 Selsey Road; design solution required.
* Quarry Lane, Kingsham Avenue /Road, Terminus Road; impacts of forecast flow changes on highway users, residential and commercial frontagers and measures to manage through traffic whilst maintaining local access

Sustainable transport measures will also be required to mitigate planned development. These will be identified through more detailed assessments of sites including pre-application consideration. Funding will need to be identified through development and other sources as well in some cases.

Public Rights of Way
There is support for the Local Plan Review's approach to Public Rights Of Way (PROW), not just for the potential to impact on existing public off-road access but also the opportunity it brings to enhance this access for the benefit of future residents, communities and visitors. PROW deliver benefits for personal health and wellbeing; sustainable transport; reduction of air pollution and road congestion; are able to support local economies; and they connect communities.
WSCC PROW welcomes several aspects of the Vision statement, which give support to the protection and enhancement of the PROW network, and provision of safe and convenient off-road access opportunities for residents and visitors:

* Pursue a healthy lifestyle and benefit from a sense of well-being supported by good access to education, health, leisure, open space and nature, sports and other essential facilities;
* Live in sustainable neighbourhoods supported by necessary infrastructure and facilities;
* Move around safely and conveniently with opportunities to choose alternatives to car travel.

The Local Plan Strategic Objectives offer further support to enhance off-road access, particularly to 'Encourage healthy and active lifestyles for all, developing accessible health and leisure facilities and linked green spaces'. However, the objective to 'Achieve a sustainable and integrated transport system through improved cycling networks and links to public transport' should recognise walking also as an important mode for many people; some strategic enhancements will significantly improve walkers' safety and convenience.

It is considered that West of Chichester the A259 could act as a corridor for increased volumes of non-motorised access, particularly cycling. Improvement of the existing on-road facility and development of a various 'feeder' routes to connect with the many settlements, perhaps using quiet lanes in places, would encourage cycling particularly to be a natural alternative to vehicle use. Policy S18: Integrated Coastal Zone Management for the Manhood Peninsula, gives regard to such an ambition in stating it will 'Improve infrastructure to support sustainable modes of transport, especially cycle ways, bridleways and footpaths, including the National Coastal Footpath'.

The National Planning Policy Framework (NPPF) Open Space and Recreation, para 97b) states:
the loss resulting from the proposed development would be replaced by equivalent or better provision in terms of quantity and quality in a suitable location.
The NPPF para 98 also states:
Planning policies and decisions should protect and enhance public rights of way and access, including taking opportunities to provide better facilities for users, for example by adding links to existing rights of way networks including National Trails.'
There is support for Policy S20: Design, that recognises these requirements in stating development 'is well connected to provide safe and convenient ease of movement by all users, prioritising pedestrian and cycle movements both within the scheme and neighbouring areas and ensuring that the needs of vehicular traffic does not dominate at the expense of other modes of transport, or undermine the resulting quality of places' and 'incorporates and/or links to high quality Green Infrastructure and landscaping to enhance biodiversity and meet recreational needs, including public rights of way'.


Education
As the local education authority, WSCC has the statutory duty to ensure that there is a sufficient supply of suitable school places to meet statutory requirements for early years, primary, secondary and sixth form provision (including up to age 25 for those with special educational needs and/or disabilities). Education infrastructure, or contributions to provide infrastructure, will be required in order to mitigate proposed development. We will continue to work with CDC in preparation of the Local Plan Review and the Infrastructure Delivery Plan regarding education and other service requirements in order to mitigate planned development.

The table below sets out the primary, secondary school and sixth form requirements to mitigate proposed development. SEE ATTACHMENT FOR TABLE

AL1 Land West of Chichester

It should be noted that phase one of this development will provide the primary school with the core of the building being built to the specification for a 2 form entry (FE) school and 1FE teaching accommodation. Phase 2 as per 6.10 on page 93 should include expansion of the primary school for the further 1FE of teaching accommodation.

AL2 Land at Shopwhyke (Oving Parish)

No update to original response for this allocation is required.

AL3 Land East of Chichester - previously South of Shopwhyke

At the current time pupil place planning indicates that there is insufficient space within the primary schools that serve this proposed development. Further capacity would be required to accommodate the development. Land for a 1 FE expandable to 2FE and pro rata share of the build costs would be required.

If numbers were to increase on the east side of the city, education provision will need to be reviewed, potentially a further 1FE may be required including land provision, this could be in the form of an expansion or a new school being built capable of expansion to 3FE.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL4 Land at Westhampnett / North East Chichester

The remaining 200 dwellings will impact on the education provision in the area, financial contributions towards expansion of existing or pro rata costs towards the expansion of the school within AL3.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL5 Southern Gateway

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from the strategic allocation of 350 dwellings in the Southern Gateway. However, consideration should be given to the cumulative impact of housing in the area Land South West of Chichester (AL6) to allocate land within the area for a 1FE expandable to 2FE primary school. Pro rata financial contributions towards the build costs would be sought from developers to mitigate their impact.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL6 Land South West of Chichester (Apuldram & Donnington Parishes)

It should be noted that the primary education provision in this area is either in Chichester City Centre which means crossing the main A27 or by travelling south towards the peninsula. Consideration should be given to the cumulative impact of further housing in the area along with the Southern Gateway allocation (AL5) to allocate land within the strategic allocation site for a 1FE expandable to 2FE primary school. Pro rata financial contributions towards the build costs would be sought from developers to mitigate their impact.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL7 Bosham

The current primary provision serving the area is at capacity, expansion of the school on its existing site is not possible. As part of the strategic allocation, it is proposed that land for a 2FE primary school be provided. The strategic allocation of 250 dwellings in isolation does not require a new school to be built. Certainty over the land allocation and sufficient funding will be key drivers in realising this proposal.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL9 Fishbourne

The primary school serving the area is currently at capacity, expansion of the school may be possible, feasibility / options appraisals would need to be undertaken.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of primary and secondary schools and sixth form if feasible and required.

AL8 East Wittering

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development.

Contributions would be required for expansion of primary and secondary schools if feasible and required.

AL10 Chidham and Hambrook area

The current primary provision serving the area is at capacity, expansion of the school on its existing site is not possible. As part of the strategic allocation, it is proposed that land for a 2FE primary school be provided. Certainty over the land allocation and sufficient funding will be key drivers in realising this proposal.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL11 Hunston

Any development within this area cannot currently be accommodated in the existing primary school at North Mundham. Further capacity would be required to accommodate the development, CDC will need to work with WSCC to determine how additional capacity in the area could be accommodated if land is to be allocated.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

AL12 Selsey

Further capacity would be required to accommodate the development. Contributions (and possibly land if required) would be sought to meet the pupil product from the development in the most appropriate form once this can be clarified.

At the current time pupil place planning indicates that there would be sufficient space to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

AL13 Southbourne

At the current time pupil place planning indicates that there is insufficient space within the primary schools that serve this proposed development. Further capacity would be required to accommodate the development. Land for a 2form entry expandable to 3FE primary school and pro rata share of the build costs would be required.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL14 Tangmere

The current allocation of 1,300 dwellings will bring forward the requirement for land for a 1FE expandable to 2FE and financial contributions would be sought to meet the pupil product from the development in the most appropriate form once this can be clarified.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

Footnote: - if all of the proposed sites were to come forward the secondary school and sixth form provision would be full in the Chichester Planning Area. Expansion of the secondary schools in the Chichester Planning Area to cater for the increased demand would need to be sought from the academy sponsors, where appropriate and the Local Authority.


Lead Local Flood Authority
The Lead Local Flood Authority (LLFA) is concerned about the approach being taken with regard to ensuring potential wastewater treatment for proposed new sustainable development.

Paragraph 8 of the NPPF states:
8. Achieving sustainable development means that the planning system has three overarching objectives, which are interdependent and need to be pursued in mutually supportive ways (so that opportunities can be taken to secure net gains across each of the different objectives):

a) An economic objective - to help build a strong, responsive and competitive
economy, by ensuring that sufficient land of the right types is available in the
right places and at the right time to support growth, innovation and improved
productivity; and by identifying and coordinating the provision of infrastructure;

Paragraph 20 of the NPPF states:
20. Strategic policies should set out an overall strategy for the pattern, scale and quality of development, and make sufficient provision for:
a) housing (including affordable housing), employment, retail, leisure and other commercial development;
b) infrastructure for transport, telecommunications, security, waste management, water supply, wastewater, flood risk and coastal change management, and the provision of minerals and energy (including heat);

In the LLFAs view, the Local Plan Review is not setting out an overall strategy for the pattern, scale and quality of development in relation to arrangements for wastewater management. The LLFA considers that CDC needs to go further in incorporating within the Local Plan Review how this provision is being made.


Additional Policy Comments

Policy S12: Infrastructure Provision
Support the requirement that all development must provide or fund new infrastructure, facilities and services required, both on and off-site (including full fibre communications infrastructure) as a consequence of the proposal. The explicit reference to full fibre communications infrastructure is supported as this will provide gigabit-capable and future-proofed services to all development, existing and new. The reference to provision of facilities and services on and off-site is also supported as in the case of broadband for example, all development will be adequately equipped with the necessary infrastructure installed for the purposes of connecting to full fibre gigabit-capable broadband services. This policy supports the County Council's aim for increased digital infrastructure that will provide for gigabit-capable broadband and future technologies such as 5G.

Support the reference to safeguarding educational facilities under section 3 of the policy.

The policy includes the requirement to 'Facilitate accessibility to facilities and services by a range of transport modes'. PROW can offer vital access means for walkers and cyclists, such as for employment land use (e.g. commuting by bicycle) and in support of the high street, both for employees and customers. IT is considered that this Policy, also Policy S13: Chichester City Development Principles, should aim to encourage such access to be the natural and preferred modes of access, thereby helping achieve the benefits previously described. It is noted Policy S14: Chichester City Transport Strategy, does acknowledge cycling and walking and lends support to their improvement.

The supporting text, paragraph 4.81 makes reference to the Strategic Infrastructure Package (SIP). It is requested that this wording is removed and replaced with West Sussex County Council identifies service infrastructure requirements necessary to support new and existing communities, where strategic development and growth is proposed in Local Plans. These are required to deliver the County Council's statutory responsibilities, strategic objectives and current policy and feed into the preparation of the Infrastructure Delivery Plan.


Policy S13: Chichester City Development Principles
This policy, like policy S12, it is considered should aim to encourage such access to be the natural and preferred modes of access, thereby helping achieve the benefits previously described. It is noted Policy S14: Chichester City Transport Strategy, does acknowledge cycling and walking and lends support to their improvement.


Policy S23: Transport and Accessibility
The policy and supporting text paragraphs 5.15 - 5.33 refer to Transport Infrastructure. Understandably much consideration is given to the A27 around Chichester; however, in addition to seeking new infrastructure from new development, it is recommended support in principle is given to maximising the value of existing infrastructure so as to facilitate off-road user modes accessing either side of the A27.


S24: Countryside
Supporting text paragraphs 5.34 - 5.43, acknowledges 'it is necessary to provide for the social and economic needs of small rural communities, and enable those who manage, live and work in the countryside to continue to do so'. It is recognised in para 7.205, supporting text to policy SM35 Equestrian Development, the high numbers of liveried and stabled horses. A considerable network of businesses are supported by such a high equine population, and in addition to financial value within the local community there is considerable benefit in terms of health and wellbeing of individuals. It is suggested that Policy S24: Countryside, could recognise this specifically.


S27: Flood Risk Management
Supporting text paragraph 5.54, requested amendments underlined - as a consequence of the rise in sea levels and storm surges, parts of the plan area will be at increased risk from coastal erosion, groundwater, fluvial and/or tidal flooding. Hard defences may not be possible to maintain in the long term, therefore development needs to be strongly restricted in areas at risk to flooding and erosion, whilst ensuring that existing towns and villages are protected by sustainable means that make space for water in suitable areas. Development must take account of the policies of the relevant shoreline management plan

Supporting text paragraph 5.58, requested amendments underlined - Built development can lead to increased surface water run-off; therefore new
development is encouraged to incorporate mitigation techniques in its design, such as permeable surfaces and Sustainable Drainage Systems (SuDS). Where appropriate, SuDS should be used as part of the linked green infrastructure network to provide multiple functions and benefits to landscape quality, recreation and biodiversity. This can be achieved through habitat creation, new open spaces and good design. SuDS should be designed to help cope with intense rainfall events and to overcome any deterioration in water quality status. In determining the suitability of SuDS for individual development sites, developers should refer to guidance published by the Lead Local Flood Authority (LLFA): West Sussex LLFA Policy for the Management of Surface Water: https://www.westsussex.gov.uk/media/12230/ws_llfa_policy_for_management_of_surface_water.pdf and, if necessary, seek further advice from the Lead Local Flood Authority LLFA.

S27 policy text requested amendments underlined for section 1 - a. through a sequential approach, taking into consideration all forms of flooding, it is located in the lowest appropriate flood risk location in accordance with the NPPF and the Chichester Strategic Flood Risk Assessment (SFRA); and

S27 policy text requested amendments underlined for section 2. Sustainable drainage systems (SuDS) will be required on major developments (10 or more dwellings or equivalent) and encouraged for smaller schemes. SUDS should be designed into the landscape of all new development and should be included as part of a District wide approach to improve water quality and provide flood mitigation. A site-specific Flood Risk Assessment will be required for sites within or adjacent to areas at risk of surface water flooding as identified in the SFRA. There should be no increase in either the volume or rate of surface water runoff leaving the site.

S27 policy text requested additional bullet point as number 4 - Clear management arrangements and funding for their ongoing maintenance over the lifetime of the development should be proposed. Planning conditions and / or obligations will be used to secure these arrangements.

S27 policy text requested amendments underlined for section 2, but would be section 5 - Development should not result in any property or highway, on or off site, being at greater risk of flooding than the 1 in 100 year storm return period, including an allowance for climate change.


Policy S29: Green Infrastructure
The Green Infrastructure policy is welcomed, including provision of new Green Infrastructure as an integral part of the development at Strategic Development Locations. It is recommended that measures are put in place to secure the long term management of such Green Infrastructure.


Policy S30: Strategic Wildlife Corridors
The identification of Strategic Wildlife Corridors and inclusion of a policy to safeguard them from development is welcomed. It is recommended that CDC promotes positive conservation management within these corridors to maximise their contribution to maintaining and enhancing biodiversity. As stated in Section 5.66, 'These corridors do not stop at the plan area boundaries.' Thus, it is recommended that CDC works in partnership with Chichester Harbour Conservancy and The South Downs National Park Authority to ensure that these Strategic Wildlife Corridors continue to provide effective corridors and connectivity across the wider landscape.

Section 5.66 refers to four Strategic Wildlife Corridors connecting Chichester Harbour with the South Downs National Park but it is noted that there is no mention of the Strategic Wildlife Corridors to the east of Chichester which connect Pagham Harbour with the South Downs National Park (as seen in Policy Map S30b). It is also noted that the maps referred to in Section 5.66, Maps 5.1 & 5.2 are missing.

WSCC and CDC promoted a Mitigated Northern Route for the A27 at Chichester as the preferred option, subject to the inclusion of important mitigation measures that are needed to make the scheme acceptable in environmental terms and the 'full southern route' as a reasonable alternative. Both routes could impact on the identified Strategic Wildlife Corridors. As currently drafted, Policy S30 would seem to prevent a mitigated northern route from coming forward in the future. Therefore, the District Council should consider whether the policy is overly restrictive (for example should it refer to 'significant adverse impacts' or 'unacceptable adverse impacts'?) and how it would be applied if a northern route for A27 were to come forward in the future.


Policy S31: Wastewater Management and Water Quality
S27 policy text requested amendments underlined for section 3, this - Where appropriate, development should contribute to the delivery of identified actions to deliver infiltration reduction across the catchment. Where appropriate development should contribute to the delivery of identified actions to deliver a reduction in the level of infiltration of groundwater into the sewer system.


Policy AL1: Land West of Chichester
AL1 policy text requested additional bullet point as number 8 - Increase capacity to attenuate surface water on site, thereby reducing the discharge flows off the site below current rates and reducing the risk of flooding to residential areas downstream.

AL1 policy text requested additional bullet point under 15 as 15 b- Provide mitigation for any loss of watercourse habitat resulting from culverting for highway provision in the development;

AL1 policy text in supporting 'improved cycle and pedestrian routes linking the site with the city, Fishbourne and the South Downs National Park', a new key link for cycling will be to Salthill Road, thereby enabling cyclists to benefit from the existing bridge crossing of the A27 for journeys to and from the west.


AL2: Land at Shopwyke (Oving Parish)
The policy acknowledges need 'for foot/cycle bridge across A27 to Coach Road'. There is also need for equestrian users to cross the A27 and WSCC PROW has received several enquiries seeking support for such infrastructure. Consideration could be given to the proposed bridge providing for all three modes.


AL3: East of Chichester (Oving Parish)
AL3 supporting text requested amendments underlined for paragraph 6.22 - The site is identified for 600 dwellings, however, there may be potential to deliver a large strategic development of 1000 dwellings, subject to further evidence, including the testing of additional growth on the local highway network and capacity of the site to provide flood risk attenuation for the increased housing density. The site should be master planned as a whole, and delivered through a phased development over a ten year period. Although the site is physically separated from the city by the A27 Chichester Bypass, the development should form a planned extension to the city, forming a new neighbourhood. This will involve opportunities to provide new facilities to serve the wider local community with good off-site access, particularly by walking and cycling to existing local facilities and facilities in the city.

AL3 policy requires exploring integrated green infrastructure with other strategic sites to the north east of the city, Tangmere and the wider countryside. It is considered that future residents will have expectations for provision of safe and convenient links towards Oving and also across the railway to link to the A259 cycle path and PROW south of the A259. It is considered that the policy should be strengthened to ensure such provision.


Policy AL4: Land at Westhampnett/North East Chichester
AL4 policy text requested amendments underlined for section 3 - Open space and green infrastructure, including a linear greenspace with public access along the Lavant Valley.

Taking into account the site-specific requirements, proposals for the site should satisfy the following requirements:

Policy AL4 policy, it is welcomed that 'provision should be made for green links to the South Downs National Park and Chichester City.' Safe and convenient walking and cycling to Lavant, from where people will access the South Downs, will provide for sustainable transport use.


Policy AL5 Southern Gateway
AL5 supporting text requested amendments underlined for paragraph 6.38 - The area has been identified as suitable for comprehensive regeneration with the aim being to make it a more attractive and welcoming gateway for the city, providing new housing, business and retail space and leisure and tourism facilities. Opportunities will be identified to improve transport links with a focus on cycling, walking and public transport and the removal of non-essential traffic from the area. There is also scope for significant public space enhancements and new landscaping incorporating blue / green infrastructure delivering multi-functional benefits.

AL5 policy text requested amendments underlined for section 5 - Provision of open space that:
* Is in accordance with Policy DM34, including retention of the existing playing pitch unless suitable re-provision is provided;
* Reinforces / enhances green and blue infrastructure consistent with Policy S29 and fully exploits the opportunities for sustainable drainage.


AL5 policy text requested amendments underlined for section 8 - Provision of both a surface and waste water management plan which demonstrates no net increase in flow to Apuldram Waste Water Treatment Works would result from this development, unless suitable alternative provision is agreed;


Policy AL6: Land South-West of Chichester (Apuldram and Donnington Parishes)
The LLFA has concerns regarding the lack of reference to flood risk constraints of the site in Policy AL6. There is reference to flood risk in paragraph 6.47. However, the policy itself makes no reference to these constraints.
The constraints arise from a combination of the following:

* Current tidal /fluvial flood risk extending from Chichester harbour to the west and up the River Lavant floodplain; (Map 1)
* Future tidal /fluvial flood risk associated with climate change; (Map 1)
* Constraints on infiltration of surface water run off because of high seasonal groundwater levels (<0.025m below the surface) (Map 2); and
* Constraints on gravity outfalls because of the low relief and long-term reduction in tidal window for discharge.

The above limits the options for how the site can be effectively drained without a step change from typically employed methods to embrace more innovative and currently expensive options e.g. blue roofs and rainwater harvesting.

The LLFA recommends that the policy sets out both the above constraints and the type of innovative drainage that will be required to achieve the development objectives for the site.



Key: Projected medium projection extent of SLR based upon 4m contour

AL6 extent

Current Flood Zone 3 extent.

Current Areas of high (1:30) surface water flood risk

Map 1 Existing and projected Tidal and surface water flood risk for AL6.

Consistent with paragraph 3.2 of the SFRA, given the high risk of flooding both now and into the future for this site, it is recommended that CDC gives consideration to the climate change maps to understand how the flood zones are predicted to change over the lifetime of the development.


Key:
AL6 boundary.

Groundwater levels are either at very near (within 0.025m of) the ground surface.

Groundwater levels are between 0.025m and 0.5m below the ground surface

Map 2 Groundwater flood risk JBA

Policy AL6 WSCC PROW considers 'necessary highway improvements to adequately mitigate the likely impacts on the highway network' to include a bridge crossing of the A27 for convenient walking and cycling access to the Terminus Road industrial estate and the city. There is an existing public footpath but, as this crosses the A27 at-grade, this will not provide the safest facility and not encourage people to minimise use of vehicles for local access. Provision of a bridge and access through the site could also establish a valuable link to the popular Salterns Way walking and cycle path. An additional link to Salterns Way should also be provided off the A286 for the benefit of Stockbridge residents as a safer alternative to the A286.


AL 7 Highgrove Farm, Bosham
The LLFA notes that the above site has the potential for a moderate risk of groundwater flooding. It is likely that this is perched groundwater draining from higher ground / springs to the north that lies in the superficial mixed sediments underlain by Lambeth Clay.


Policy AL8: East Wittering Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The policy requires 'Opportunities ... for the expansion and provision of green infrastructure into the wider countryside including between settlements and facilities'. Existing and future residents and the local visitor economy would benefit by delivery of an off-road route for walkers, cyclists and horse riders to and from the Medmerry development and towards Selsey. It is considered that Policy AL8 should aim to deliver this enhancement specifically.


Policy AL9: Fishbourne Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

It is considered that off-road cycling links to land West of Chichester (off Salthill Road) and to Bosham (off Park Lane) would benefit this community with enhanced sustainable connectivity.


Policy AL10: Chidham and Hambrook Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The policy requires 'opportunities' to develop green infrastructure and links to other communities. An opportunity, in conjunction with Highways England, exists to maximise the value of existing infrastructure by creating a new bridleway (for walkers, cyclists and horse riders) on a path using an existing A27 overbridge.


Policy AL11: Hunston Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The village is already well connected for walkers to access the surrounding countryside but there are presently no local cycling or horse riding facilities on the PROW network. A bridleway link to South Mundham (with the potential for future cycle links to Pagham and towards Bognor Regis) and to Sidlesham via the golf course and Brimfast Lane would provide residents and visitors with improved access to the countryside and services.


Policy AL12: Land North of Park Farm, Selsey
It is unclear why the policy map shows the proposed strategic allocation lies outside of the Neighbourhood Plan proposed settlement boundary. Some explanation for this anomaly would be helpful in the text.


Groundwater flood risk as depicted by JBA mapping (Brown = seasonal groundwater level lies between 0.025 and 0.5m below the surface).

The principle concern that the LLFA wishes to highlight is the need to ensure that the necessary foul sewerage infrastructure to support development is in place. It is the LLFA understanding that the Siddlesham WWTW experiences capacity issues currently, in part exacerbated by groundwater infiltration. While Policy AL12 states: Development proposals will need to demonstrate that sufficient capacity will be available within the sewer network, including waste water treatment works, to accommodate the proposed development in accordance with Policy S31.

The policy proposes only to provide 'pedestrian links between the site and new development south of Park Lane'. It is considered that cycling links should also be provided.


Policy DM8: Transport, Accessibility and Parking
The PROW network can provide vital means for communities to interact and encourage sustainable local access. The policy requirement to create 'links between new development and existing pedestrian, cycle and public transport networks' is welcomed. However, establishing links into surrounding existing development should not be overlooked also - the greater the permeability, the greater the use.


Policy DM10: New Employment Sites
Whilst mentioned earlier in the Plan in respect of a number of specific sites, this policy should specifically aim to provide, as a matter of course, suitable walking and cycling infrastructure to encourage local sustainable access. This infrastructure may need to extend outside a site boundary so as to provide safe and convenient connection to existing infrastructure. This principle should apply also to Policy DM13: Built Tourist and Leisure Development and Policy DM14: Caravan and Camping Sites.


Policy DM32: Green Infrastructure
Whilst it is recognised the policy proposes support subject to not 'dissect[ing] ... the linear network of cycle ways, public rights of way, bridleways ...', the policy could lend support to establishing new routes as part of the Green Infrastructure network itself.


Policy DM35: Equestrian Development
It is appreciated why the Plan would wish to require future equine development to be 'well related to or has improved links to the existing bridleway network'. However, this will add to the pressure of use on the existing bridleway network, which is not extensive outside of the South Downs, so will increase degradation of paths. Future developments must, therefore, accept to contribute in some way, acceptable to the local highway authority, to mitigate the additional impact to be created so all lawful users are not disadvantaged.


Policy DM29: Biodiversity
The measures to safeguard and enhance the biodiversity value of development sites are welcomed, including seeking net biodiversity gain.


Schedule of proposed changes to the policies map
S30a West of City Corridors -suggest title should be West of City Strategic Wildlife Corridors (to match S30b: East of City Strategic Wildlife Corridors. The Strategic Wildlife Corridors are depicted in different colour patterns on the two plans which is somewhat confusing.


Strategic Wildlife Corridors Local Plan Review Background Paper
Proposed Hermitage to Westbourne Strategic Wildlife Corridor
A large area depicted as Biodiversity Opportunity Area (BOA) in Fig. 1 (immediately to the south of the Rivers Ems & Meadows Local Wildlife Site, Westbourne) is in fact housing and forms part of the settlement of Westbourne. You should consider if this land should be included as having potential for biodiversity enhancement.


Glossary
Includes Sites of Nature Conservation Importance (SNCIs) but not Local Wildlife Sites (LWSs). SNCIs are now known as LWSs.

Attachments:

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2145

Received: 15/02/2019

Respondent: West Sussex County Council

Representation Summary:

Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The village is already well connected for walkers to access the surrounding countryside but there are presently no local cycling or horse riding facilities on the PROW network. A bridleway link to South Mundham (with the potential for future cycle links to Pagham and towards Bognor Regis) and to Sidlesham via the golf course and Brimfast Lane would provide residents and visitors with improved access to the countryside and services.

Full text:

West Sussex County Council Officer Level Response
Introduction
The Chichester Local Plan Review Preferred Approach sets out how the future development in the District will be shaped, excluding the area within the South Downs National Park, up to 2035. It includes the overall development strategy as well as relevant strategic policies to meet the future needs of the area and development management policies to help guide development over the plan period. The Local Plan helps to:
* choose where the development goes;
* protect the character and beauty of the area;
* provide job and housing opportunities so that children can continue to work and live locally;
* support and help to boost the local economy;
* help residents to maintain healthy and active lifestyles; and,
* make sure that there is adequate services, travel options and community facilities.

The Chichester Local Plan was adopted in July 2015. At that time, the Local Plan was approved, but the Government Inspector said that it had to be reviewed again within five years, to make sure that sufficient housing was planned to meet the needs of the area.

The first part of the review process was carried out in June 2017 with an Issues and Options consultation, in which comments were invited regarding the overall development strategy and possible development locations. The Local Plan Review: Preferred Approach is the second stage of the process. It sets out the proposed development strategy and policies for the area to meet future needs.


West Sussex County Council Officer Level Comments
This note sets out West Sussex County Council's (WSCC) officer response to the consultation on the draft Chichester Local Plan Review Preferred Approach. It highlights key issues and suggested changes to which Chichester District Council (CDC) is requested to give consideration. We will continue to work with CDC in preparation of the Local Plan Review and the Infrastructure Delivery Plan regarding WSCC service requirements in order to mitigate planned development.


Minerals and Waste
A steady and adequate supply of minerals and the achievement of sustainable waste management can help to achieve a District or Borough Council's goals in relation to the economy, housing, transport, communications, strategic infrastructure and the environment. Therefore, District and Borough Local Plans should recognise the importance of minerals and waste issues as relevant to the scope of their overall strategies.

We welcome the reference to the adopted Minerals and Waste Local Plans and safeguarding in the document and the requirements in policies where a site is located within a minerals safeguarding area, or near to a safeguarded waste site. There are some missing references to safeguarding of minerals and waste sites for some of the proposed allocations, set out below and request that these references are added. It is also requested that 'Joint' is added into the references for the Joint Minerals Local Plan through the document.

Policy W23 of the Waste Local Plan applies to all Districts & Boroughs, regarding waste management within development and should be referenced in the Chichester Local Plan Review.

AL3 East of Chichester
The site is to the north of the Fuel Depot site allocation in the Waste Local Plan (Policy W10) for a built waste facility as part of a comprehensive redevelopment of the site (including complimentary non-waste uses). The East of Chichester allocation is the land to the north, bisected by the railway line, of the Fuel Depot. Reference should be made to giving consideration to the allocation, and therefore its safeguarding.

AL4 Westhampnett/North East Chichester
Reference should be made to minerals safeguarding, for consistency with other allocations, as within the sharp sand and gravel safeguarding area.

AL5 Southern Gateway
Reference should be made to the mineral infrastructure safeguarding policy M10 as within 200m of the Chichester Railhead.

AL6 South-West of Chichester
Reference should be made to the mineral infrastructure safeguarding policy M10 as within 300m of the Chichester Railhead.

AL7 Highgrove Farm Bosham
Remove reference to minerals safeguarding as the site is not within the safeguarding or consultation area.

AL12 Park Farm Selsey
Reference should be made to minerals safeguarding as site is within the sharp sand and gravel safeguarding area.

Neighbourhood plan allocations
Sites are yet to be allocated though neighbourhood plans. It is considered that the Joint Minerals Local Plan and Waste Local Plan are referenced, particularly with regards to safeguarding policies (M9, M10 and W2) and these documents and policies are given detailed consideration when allocating sites. Development at, adjacent or proximal to existing waste or mineral sites / infrastructure should be the subject to consultation with WSCC.


Connectivity and Sustainable Travel
The County council has worked with the District Council on the preparation of the transport evidence base study undertaken by Peter Brett Associates for the District Council. The recommended transport mitigation strategy, as assessed using the Chichester Area Transport Model has been demonstrated to be capable in principle to prevent the development from resulting in severe residual cumulative impacts on the highways and transport network. However, the recommended strategy has several risks to deliverability and acceptability associated with it, which require further work to be undertaken to demonstrate that the strategy can be implemented in its current form to provide the forecasted mitigation to travel conditions.

There are three locations where new highway alignments are proposed outside of existing highways boundaries. Two of these may include significant earthworks or structures to be delivered, being Stockbridge Link Road and Terminus Road diversion. The cost of the mitigation strategy exceeds a figure which could reasonably be supported by the value of the proposed development developer contributions alone, therefore the delivery of the strategy will depend upon securing of external grant funding to top up developer contributions. WSCC will work with the District Council in supporting and or applying for funding, the District Council needing to secure Highways England to support funding applications for A27 improvements. The proposed junction designs for the A27 Stockbridge and Whyke roundabouts include bans to well used right turn movements off the Chichester A27 bypass which result in significant forecast changes to traffic flows on local roads in the south of Chichester and on the Manhood Peninsular.

There is a need to ensure the land outside the highway boundary is available and the plan should set out how this land will be acquired to deliver the measures, it may be that a commitment to use, if required, and therefore reference to CPO be made in the policy.

Funding for the mitigation strategy is uncertain. It is considered that the Plan should set out how it will deal with this uncertainty. This could include trigger points in the monitoring framework to trigger a change of approach or alternative options to deliver the required development.

These factors mean that feasibility work is necessary to be undertaken prior to Plan submission, to reduce as far as practicable risks to costs, land take, impacts and deliverability of the proposed transport strategy in order to show that the strategy can be implemented within the plan period and that the funding strategy will be sufficient to meet the design requirements. In particular the following will need to be addressed:

* Statutory undertakers equipment under the roads junctions to be impacted.
* Extent of earthworks required to create a vertical and horizontal alignment compliant with design standards. Design audit to identify any required departures from standard.
* Designing for drainage and flooding issues, including compliance with the WSCC LLFA Policy for the Management of Surface Water, November 2018.
* Designs for structures to cross watercourses - Stockbridge Link Road
* Design should include suitable provision for rights of way and footway crossings
* Scoping for whether and at what level further Environmental Impact Assessment will be required.
* Stage 1 Road safety Audit, designers response report and resulting amendments to designs.
* Land take required after feasibility level designs have been developed and availability of required land.
* Wophams Lane - impacts of forecast changes to flow patterns to take B2201 southbound traffic on requirements for highway width, alignment, footway provision and junctions with A286 Birdham Road and B2201 Selsey Road; design solution required.
* Quarry Lane, Kingsham Avenue /Road, Terminus Road; impacts of forecast flow changes on highway users, residential and commercial frontagers and measures to manage through traffic whilst maintaining local access

Sustainable transport measures will also be required to mitigate planned development. These will be identified through more detailed assessments of sites including pre-application consideration. Funding will need to be identified through development and other sources as well in some cases.

Public Rights of Way
There is support for the Local Plan Review's approach to Public Rights Of Way (PROW), not just for the potential to impact on existing public off-road access but also the opportunity it brings to enhance this access for the benefit of future residents, communities and visitors. PROW deliver benefits for personal health and wellbeing; sustainable transport; reduction of air pollution and road congestion; are able to support local economies; and they connect communities.
WSCC PROW welcomes several aspects of the Vision statement, which give support to the protection and enhancement of the PROW network, and provision of safe and convenient off-road access opportunities for residents and visitors:

* Pursue a healthy lifestyle and benefit from a sense of well-being supported by good access to education, health, leisure, open space and nature, sports and other essential facilities;
* Live in sustainable neighbourhoods supported by necessary infrastructure and facilities;
* Move around safely and conveniently with opportunities to choose alternatives to car travel.

The Local Plan Strategic Objectives offer further support to enhance off-road access, particularly to 'Encourage healthy and active lifestyles for all, developing accessible health and leisure facilities and linked green spaces'. However, the objective to 'Achieve a sustainable and integrated transport system through improved cycling networks and links to public transport' should recognise walking also as an important mode for many people; some strategic enhancements will significantly improve walkers' safety and convenience.

It is considered that West of Chichester the A259 could act as a corridor for increased volumes of non-motorised access, particularly cycling. Improvement of the existing on-road facility and development of a various 'feeder' routes to connect with the many settlements, perhaps using quiet lanes in places, would encourage cycling particularly to be a natural alternative to vehicle use. Policy S18: Integrated Coastal Zone Management for the Manhood Peninsula, gives regard to such an ambition in stating it will 'Improve infrastructure to support sustainable modes of transport, especially cycle ways, bridleways and footpaths, including the National Coastal Footpath'.

The National Planning Policy Framework (NPPF) Open Space and Recreation, para 97b) states:
the loss resulting from the proposed development would be replaced by equivalent or better provision in terms of quantity and quality in a suitable location.
The NPPF para 98 also states:
Planning policies and decisions should protect and enhance public rights of way and access, including taking opportunities to provide better facilities for users, for example by adding links to existing rights of way networks including National Trails.'
There is support for Policy S20: Design, that recognises these requirements in stating development 'is well connected to provide safe and convenient ease of movement by all users, prioritising pedestrian and cycle movements both within the scheme and neighbouring areas and ensuring that the needs of vehicular traffic does not dominate at the expense of other modes of transport, or undermine the resulting quality of places' and 'incorporates and/or links to high quality Green Infrastructure and landscaping to enhance biodiversity and meet recreational needs, including public rights of way'.


Education
As the local education authority, WSCC has the statutory duty to ensure that there is a sufficient supply of suitable school places to meet statutory requirements for early years, primary, secondary and sixth form provision (including up to age 25 for those with special educational needs and/or disabilities). Education infrastructure, or contributions to provide infrastructure, will be required in order to mitigate proposed development. We will continue to work with CDC in preparation of the Local Plan Review and the Infrastructure Delivery Plan regarding education and other service requirements in order to mitigate planned development.

The table below sets out the primary, secondary school and sixth form requirements to mitigate proposed development. SEE ATTACHMENT FOR TABLE

AL1 Land West of Chichester

It should be noted that phase one of this development will provide the primary school with the core of the building being built to the specification for a 2 form entry (FE) school and 1FE teaching accommodation. Phase 2 as per 6.10 on page 93 should include expansion of the primary school for the further 1FE of teaching accommodation.

AL2 Land at Shopwhyke (Oving Parish)

No update to original response for this allocation is required.

AL3 Land East of Chichester - previously South of Shopwhyke

At the current time pupil place planning indicates that there is insufficient space within the primary schools that serve this proposed development. Further capacity would be required to accommodate the development. Land for a 1 FE expandable to 2FE and pro rata share of the build costs would be required.

If numbers were to increase on the east side of the city, education provision will need to be reviewed, potentially a further 1FE may be required including land provision, this could be in the form of an expansion or a new school being built capable of expansion to 3FE.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL4 Land at Westhampnett / North East Chichester

The remaining 200 dwellings will impact on the education provision in the area, financial contributions towards expansion of existing or pro rata costs towards the expansion of the school within AL3.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL5 Southern Gateway

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from the strategic allocation of 350 dwellings in the Southern Gateway. However, consideration should be given to the cumulative impact of housing in the area Land South West of Chichester (AL6) to allocate land within the area for a 1FE expandable to 2FE primary school. Pro rata financial contributions towards the build costs would be sought from developers to mitigate their impact.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL6 Land South West of Chichester (Apuldram & Donnington Parishes)

It should be noted that the primary education provision in this area is either in Chichester City Centre which means crossing the main A27 or by travelling south towards the peninsula. Consideration should be given to the cumulative impact of further housing in the area along with the Southern Gateway allocation (AL5) to allocate land within the strategic allocation site for a 1FE expandable to 2FE primary school. Pro rata financial contributions towards the build costs would be sought from developers to mitigate their impact.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

At the current time pupil place planning indicates that there would be expansion capacity to accommodate the child product from this proposed development for sixth form pupils. Contributions would be required for expansion of the provision if feasible and required.

AL7 Bosham

The current primary provision serving the area is at capacity, expansion of the school on its existing site is not possible. As part of the strategic allocation, it is proposed that land for a 2FE primary school be provided. The strategic allocation of 250 dwellings in isolation does not require a new school to be built. Certainty over the land allocation and sufficient funding will be key drivers in realising this proposal.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL9 Fishbourne

The primary school serving the area is currently at capacity, expansion of the school may be possible, feasibility / options appraisals would need to be undertaken.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of primary and secondary schools and sixth form if feasible and required.

AL8 East Wittering

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development.

Contributions would be required for expansion of primary and secondary schools if feasible and required.

AL10 Chidham and Hambrook area

The current primary provision serving the area is at capacity, expansion of the school on its existing site is not possible. As part of the strategic allocation, it is proposed that land for a 2FE primary school be provided. Certainty over the land allocation and sufficient funding will be key drivers in realising this proposal.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL11 Hunston

Any development within this area cannot currently be accommodated in the existing primary school at North Mundham. Further capacity would be required to accommodate the development, CDC will need to work with WSCC to determine how additional capacity in the area could be accommodated if land is to be allocated.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

AL12 Selsey

Further capacity would be required to accommodate the development. Contributions (and possibly land if required) would be sought to meet the pupil product from the development in the most appropriate form once this can be clarified.

At the current time pupil place planning indicates that there would be sufficient space to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools if feasible and required.

AL13 Southbourne

At the current time pupil place planning indicates that there is insufficient space within the primary schools that serve this proposed development. Further capacity would be required to accommodate the development. Land for a 2form entry expandable to 3FE primary school and pro rata share of the build costs would be required.

AL7, AL10 and AL13 are all within the same school planning area, the cumulative total of the strategic allocations brings forward a requirement for c3 forms of entry additional school places. The Local Plan, as currently drafted, indicates an oversupply of school places which could affect the viability of all the schools in the planning area.

Expansion of the secondary school may be possible. Contributions would be required for expansion of secondary schools if feasible and required.

AL14 Tangmere

The current allocation of 1,300 dwellings will bring forward the requirement for land for a 1FE expandable to 2FE and financial contributions would be sought to meet the pupil product from the development in the most appropriate form once this can be clarified.

At the current time pupil place planning indicates that there would be sufficient space or expansion capacity to accommodate the child product from this proposed development for secondary aged pupils. Contributions would be required for expansion of secondary schools and sixth form if feasible and required.

Footnote: - if all of the proposed sites were to come forward the secondary school and sixth form provision would be full in the Chichester Planning Area. Expansion of the secondary schools in the Chichester Planning Area to cater for the increased demand would need to be sought from the academy sponsors, where appropriate and the Local Authority.


Lead Local Flood Authority
The Lead Local Flood Authority (LLFA) is concerned about the approach being taken with regard to ensuring potential wastewater treatment for proposed new sustainable development.

Paragraph 8 of the NPPF states:
8. Achieving sustainable development means that the planning system has three overarching objectives, which are interdependent and need to be pursued in mutually supportive ways (so that opportunities can be taken to secure net gains across each of the different objectives):

a) An economic objective - to help build a strong, responsive and competitive
economy, by ensuring that sufficient land of the right types is available in the
right places and at the right time to support growth, innovation and improved
productivity; and by identifying and coordinating the provision of infrastructure;

Paragraph 20 of the NPPF states:
20. Strategic policies should set out an overall strategy for the pattern, scale and quality of development, and make sufficient provision for:
a) housing (including affordable housing), employment, retail, leisure and other commercial development;
b) infrastructure for transport, telecommunications, security, waste management, water supply, wastewater, flood risk and coastal change management, and the provision of minerals and energy (including heat);

In the LLFAs view, the Local Plan Review is not setting out an overall strategy for the pattern, scale and quality of development in relation to arrangements for wastewater management. The LLFA considers that CDC needs to go further in incorporating within the Local Plan Review how this provision is being made.


Additional Policy Comments

Policy S12: Infrastructure Provision
Support the requirement that all development must provide or fund new infrastructure, facilities and services required, both on and off-site (including full fibre communications infrastructure) as a consequence of the proposal. The explicit reference to full fibre communications infrastructure is supported as this will provide gigabit-capable and future-proofed services to all development, existing and new. The reference to provision of facilities and services on and off-site is also supported as in the case of broadband for example, all development will be adequately equipped with the necessary infrastructure installed for the purposes of connecting to full fibre gigabit-capable broadband services. This policy supports the County Council's aim for increased digital infrastructure that will provide for gigabit-capable broadband and future technologies such as 5G.

Support the reference to safeguarding educational facilities under section 3 of the policy.

The policy includes the requirement to 'Facilitate accessibility to facilities and services by a range of transport modes'. PROW can offer vital access means for walkers and cyclists, such as for employment land use (e.g. commuting by bicycle) and in support of the high street, both for employees and customers. IT is considered that this Policy, also Policy S13: Chichester City Development Principles, should aim to encourage such access to be the natural and preferred modes of access, thereby helping achieve the benefits previously described. It is noted Policy S14: Chichester City Transport Strategy, does acknowledge cycling and walking and lends support to their improvement.

The supporting text, paragraph 4.81 makes reference to the Strategic Infrastructure Package (SIP). It is requested that this wording is removed and replaced with West Sussex County Council identifies service infrastructure requirements necessary to support new and existing communities, where strategic development and growth is proposed in Local Plans. These are required to deliver the County Council's statutory responsibilities, strategic objectives and current policy and feed into the preparation of the Infrastructure Delivery Plan.


Policy S13: Chichester City Development Principles
This policy, like policy S12, it is considered should aim to encourage such access to be the natural and preferred modes of access, thereby helping achieve the benefits previously described. It is noted Policy S14: Chichester City Transport Strategy, does acknowledge cycling and walking and lends support to their improvement.


Policy S23: Transport and Accessibility
The policy and supporting text paragraphs 5.15 - 5.33 refer to Transport Infrastructure. Understandably much consideration is given to the A27 around Chichester; however, in addition to seeking new infrastructure from new development, it is recommended support in principle is given to maximising the value of existing infrastructure so as to facilitate off-road user modes accessing either side of the A27.


S24: Countryside
Supporting text paragraphs 5.34 - 5.43, acknowledges 'it is necessary to provide for the social and economic needs of small rural communities, and enable those who manage, live and work in the countryside to continue to do so'. It is recognised in para 7.205, supporting text to policy SM35 Equestrian Development, the high numbers of liveried and stabled horses. A considerable network of businesses are supported by such a high equine population, and in addition to financial value within the local community there is considerable benefit in terms of health and wellbeing of individuals. It is suggested that Policy S24: Countryside, could recognise this specifically.


S27: Flood Risk Management
Supporting text paragraph 5.54, requested amendments underlined - as a consequence of the rise in sea levels and storm surges, parts of the plan area will be at increased risk from coastal erosion, groundwater, fluvial and/or tidal flooding. Hard defences may not be possible to maintain in the long term, therefore development needs to be strongly restricted in areas at risk to flooding and erosion, whilst ensuring that existing towns and villages are protected by sustainable means that make space for water in suitable areas. Development must take account of the policies of the relevant shoreline management plan

Supporting text paragraph 5.58, requested amendments underlined - Built development can lead to increased surface water run-off; therefore new
development is encouraged to incorporate mitigation techniques in its design, such as permeable surfaces and Sustainable Drainage Systems (SuDS). Where appropriate, SuDS should be used as part of the linked green infrastructure network to provide multiple functions and benefits to landscape quality, recreation and biodiversity. This can be achieved through habitat creation, new open spaces and good design. SuDS should be designed to help cope with intense rainfall events and to overcome any deterioration in water quality status. In determining the suitability of SuDS for individual development sites, developers should refer to guidance published by the Lead Local Flood Authority (LLFA): West Sussex LLFA Policy for the Management of Surface Water: https://www.westsussex.gov.uk/media/12230/ws_llfa_policy_for_management_of_surface_water.pdf and, if necessary, seek further advice from the Lead Local Flood Authority LLFA.

S27 policy text requested amendments underlined for section 1 - a. through a sequential approach, taking into consideration all forms of flooding, it is located in the lowest appropriate flood risk location in accordance with the NPPF and the Chichester Strategic Flood Risk Assessment (SFRA); and

S27 policy text requested amendments underlined for section 2. Sustainable drainage systems (SuDS) will be required on major developments (10 or more dwellings or equivalent) and encouraged for smaller schemes. SUDS should be designed into the landscape of all new development and should be included as part of a District wide approach to improve water quality and provide flood mitigation. A site-specific Flood Risk Assessment will be required for sites within or adjacent to areas at risk of surface water flooding as identified in the SFRA. There should be no increase in either the volume or rate of surface water runoff leaving the site.

S27 policy text requested additional bullet point as number 4 - Clear management arrangements and funding for their ongoing maintenance over the lifetime of the development should be proposed. Planning conditions and / or obligations will be used to secure these arrangements.

S27 policy text requested amendments underlined for section 2, but would be section 5 - Development should not result in any property or highway, on or off site, being at greater risk of flooding than the 1 in 100 year storm return period, including an allowance for climate change.


Policy S29: Green Infrastructure
The Green Infrastructure policy is welcomed, including provision of new Green Infrastructure as an integral part of the development at Strategic Development Locations. It is recommended that measures are put in place to secure the long term management of such Green Infrastructure.


Policy S30: Strategic Wildlife Corridors
The identification of Strategic Wildlife Corridors and inclusion of a policy to safeguard them from development is welcomed. It is recommended that CDC promotes positive conservation management within these corridors to maximise their contribution to maintaining and enhancing biodiversity. As stated in Section 5.66, 'These corridors do not stop at the plan area boundaries.' Thus, it is recommended that CDC works in partnership with Chichester Harbour Conservancy and The South Downs National Park Authority to ensure that these Strategic Wildlife Corridors continue to provide effective corridors and connectivity across the wider landscape.

Section 5.66 refers to four Strategic Wildlife Corridors connecting Chichester Harbour with the South Downs National Park but it is noted that there is no mention of the Strategic Wildlife Corridors to the east of Chichester which connect Pagham Harbour with the South Downs National Park (as seen in Policy Map S30b). It is also noted that the maps referred to in Section 5.66, Maps 5.1 & 5.2 are missing.

WSCC and CDC promoted a Mitigated Northern Route for the A27 at Chichester as the preferred option, subject to the inclusion of important mitigation measures that are needed to make the scheme acceptable in environmental terms and the 'full southern route' as a reasonable alternative. Both routes could impact on the identified Strategic Wildlife Corridors. As currently drafted, Policy S30 would seem to prevent a mitigated northern route from coming forward in the future. Therefore, the District Council should consider whether the policy is overly restrictive (for example should it refer to 'significant adverse impacts' or 'unacceptable adverse impacts'?) and how it would be applied if a northern route for A27 were to come forward in the future.


Policy S31: Wastewater Management and Water Quality
S27 policy text requested amendments underlined for section 3, this - Where appropriate, development should contribute to the delivery of identified actions to deliver infiltration reduction across the catchment. Where appropriate development should contribute to the delivery of identified actions to deliver a reduction in the level of infiltration of groundwater into the sewer system.


Policy AL1: Land West of Chichester
AL1 policy text requested additional bullet point as number 8 - Increase capacity to attenuate surface water on site, thereby reducing the discharge flows off the site below current rates and reducing the risk of flooding to residential areas downstream.

AL1 policy text requested additional bullet point under 15 as 15 b- Provide mitigation for any loss of watercourse habitat resulting from culverting for highway provision in the development;

AL1 policy text in supporting 'improved cycle and pedestrian routes linking the site with the city, Fishbourne and the South Downs National Park', a new key link for cycling will be to Salthill Road, thereby enabling cyclists to benefit from the existing bridge crossing of the A27 for journeys to and from the west.


AL2: Land at Shopwyke (Oving Parish)
The policy acknowledges need 'for foot/cycle bridge across A27 to Coach Road'. There is also need for equestrian users to cross the A27 and WSCC PROW has received several enquiries seeking support for such infrastructure. Consideration could be given to the proposed bridge providing for all three modes.


AL3: East of Chichester (Oving Parish)
AL3 supporting text requested amendments underlined for paragraph 6.22 - The site is identified for 600 dwellings, however, there may be potential to deliver a large strategic development of 1000 dwellings, subject to further evidence, including the testing of additional growth on the local highway network and capacity of the site to provide flood risk attenuation for the increased housing density. The site should be master planned as a whole, and delivered through a phased development over a ten year period. Although the site is physically separated from the city by the A27 Chichester Bypass, the development should form a planned extension to the city, forming a new neighbourhood. This will involve opportunities to provide new facilities to serve the wider local community with good off-site access, particularly by walking and cycling to existing local facilities and facilities in the city.

AL3 policy requires exploring integrated green infrastructure with other strategic sites to the north east of the city, Tangmere and the wider countryside. It is considered that future residents will have expectations for provision of safe and convenient links towards Oving and also across the railway to link to the A259 cycle path and PROW south of the A259. It is considered that the policy should be strengthened to ensure such provision.


Policy AL4: Land at Westhampnett/North East Chichester
AL4 policy text requested amendments underlined for section 3 - Open space and green infrastructure, including a linear greenspace with public access along the Lavant Valley.

Taking into account the site-specific requirements, proposals for the site should satisfy the following requirements:

Policy AL4 policy, it is welcomed that 'provision should be made for green links to the South Downs National Park and Chichester City.' Safe and convenient walking and cycling to Lavant, from where people will access the South Downs, will provide for sustainable transport use.


Policy AL5 Southern Gateway
AL5 supporting text requested amendments underlined for paragraph 6.38 - The area has been identified as suitable for comprehensive regeneration with the aim being to make it a more attractive and welcoming gateway for the city, providing new housing, business and retail space and leisure and tourism facilities. Opportunities will be identified to improve transport links with a focus on cycling, walking and public transport and the removal of non-essential traffic from the area. There is also scope for significant public space enhancements and new landscaping incorporating blue / green infrastructure delivering multi-functional benefits.

AL5 policy text requested amendments underlined for section 5 - Provision of open space that:
* Is in accordance with Policy DM34, including retention of the existing playing pitch unless suitable re-provision is provided;
* Reinforces / enhances green and blue infrastructure consistent with Policy S29 and fully exploits the opportunities for sustainable drainage.


AL5 policy text requested amendments underlined for section 8 - Provision of both a surface and waste water management plan which demonstrates no net increase in flow to Apuldram Waste Water Treatment Works would result from this development, unless suitable alternative provision is agreed;


Policy AL6: Land South-West of Chichester (Apuldram and Donnington Parishes)
The LLFA has concerns regarding the lack of reference to flood risk constraints of the site in Policy AL6. There is reference to flood risk in paragraph 6.47. However, the policy itself makes no reference to these constraints.
The constraints arise from a combination of the following:

* Current tidal /fluvial flood risk extending from Chichester harbour to the west and up the River Lavant floodplain; (Map 1)
* Future tidal /fluvial flood risk associated with climate change; (Map 1)
* Constraints on infiltration of surface water run off because of high seasonal groundwater levels (<0.025m below the surface) (Map 2); and
* Constraints on gravity outfalls because of the low relief and long-term reduction in tidal window for discharge.

The above limits the options for how the site can be effectively drained without a step change from typically employed methods to embrace more innovative and currently expensive options e.g. blue roofs and rainwater harvesting.

The LLFA recommends that the policy sets out both the above constraints and the type of innovative drainage that will be required to achieve the development objectives for the site.



Key: Projected medium projection extent of SLR based upon 4m contour

AL6 extent

Current Flood Zone 3 extent.

Current Areas of high (1:30) surface water flood risk

Map 1 Existing and projected Tidal and surface water flood risk for AL6.

Consistent with paragraph 3.2 of the SFRA, given the high risk of flooding both now and into the future for this site, it is recommended that CDC gives consideration to the climate change maps to understand how the flood zones are predicted to change over the lifetime of the development.


Key:
AL6 boundary.

Groundwater levels are either at very near (within 0.025m of) the ground surface.

Groundwater levels are between 0.025m and 0.5m below the ground surface

Map 2 Groundwater flood risk JBA

Policy AL6 WSCC PROW considers 'necessary highway improvements to adequately mitigate the likely impacts on the highway network' to include a bridge crossing of the A27 for convenient walking and cycling access to the Terminus Road industrial estate and the city. There is an existing public footpath but, as this crosses the A27 at-grade, this will not provide the safest facility and not encourage people to minimise use of vehicles for local access. Provision of a bridge and access through the site could also establish a valuable link to the popular Salterns Way walking and cycle path. An additional link to Salterns Way should also be provided off the A286 for the benefit of Stockbridge residents as a safer alternative to the A286.


AL 7 Highgrove Farm, Bosham
The LLFA notes that the above site has the potential for a moderate risk of groundwater flooding. It is likely that this is perched groundwater draining from higher ground / springs to the north that lies in the superficial mixed sediments underlain by Lambeth Clay.


Policy AL8: East Wittering Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The policy requires 'Opportunities ... for the expansion and provision of green infrastructure into the wider countryside including between settlements and facilities'. Existing and future residents and the local visitor economy would benefit by delivery of an off-road route for walkers, cyclists and horse riders to and from the Medmerry development and towards Selsey. It is considered that Policy AL8 should aim to deliver this enhancement specifically.


Policy AL9: Fishbourne Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

It is considered that off-road cycling links to land West of Chichester (off Salthill Road) and to Bosham (off Park Lane) would benefit this community with enhanced sustainable connectivity.


Policy AL10: Chidham and Hambrook Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The policy requires 'opportunities' to develop green infrastructure and links to other communities. An opportunity, in conjunction with Highways England, exists to maximise the value of existing infrastructure by creating a new bridleway (for walkers, cyclists and horse riders) on a path using an existing A27 overbridge.


Policy AL11: Hunston Parish
Due to no information on where housing is going to be located so the LLFA is not in a position to comment on proposed housing allocation sites at this stage.

The village is already well connected for walkers to access the surrounding countryside but there are presently no local cycling or horse riding facilities on the PROW network. A bridleway link to South Mundham (with the potential for future cycle links to Pagham and towards Bognor Regis) and to Sidlesham via the golf course and Brimfast Lane would provide residents and visitors with improved access to the countryside and services.


Policy AL12: Land North of Park Farm, Selsey
It is unclear why the policy map shows the proposed strategic allocation lies outside of the Neighbourhood Plan proposed settlement boundary. Some explanation for this anomaly would be helpful in the text.


Groundwater flood risk as depicted by JBA mapping (Brown = seasonal groundwater level lies between 0.025 and 0.5m below the surface).

The principle concern that the LLFA wishes to highlight is the need to ensure that the necessary foul sewerage infrastructure to support development is in place. It is the LLFA understanding that the Siddlesham WWTW experiences capacity issues currently, in part exacerbated by groundwater infiltration. While Policy AL12 states: Development proposals will need to demonstrate that sufficient capacity will be available within the sewer network, including waste water treatment works, to accommodate the proposed development in accordance with Policy S31.

The policy proposes only to provide 'pedestrian links between the site and new development south of Park Lane'. It is considered that cycling links should also be provided.


Policy DM8: Transport, Accessibility and Parking
The PROW network can provide vital means for communities to interact and encourage sustainable local access. The policy requirement to create 'links between new development and existing pedestrian, cycle and public transport networks' is welcomed. However, establishing links into surrounding existing development should not be overlooked also - the greater the permeability, the greater the use.


Policy DM10: New Employment Sites
Whilst mentioned earlier in the Plan in respect of a number of specific sites, this policy should specifically aim to provide, as a matter of course, suitable walking and cycling infrastructure to encourage local sustainable access. This infrastructure may need to extend outside a site boundary so as to provide safe and convenient connection to existing infrastructure. This principle should apply also to Policy DM13: Built Tourist and Leisure Development and Policy DM14: Caravan and Camping Sites.


Policy DM32: Green Infrastructure
Whilst it is recognised the policy proposes support subject to not 'dissect[ing] ... the linear network of cycle ways, public rights of way, bridleways ...', the policy could lend support to establishing new routes as part of the Green Infrastructure network itself.


Policy DM35: Equestrian Development
It is appreciated why the Plan would wish to require future equine development to be 'well related to or has improved links to the existing bridleway network'. However, this will add to the pressure of use on the existing bridleway network, which is not extensive outside of the South Downs, so will increase degradation of paths. Future developments must, therefore, accept to contribute in some way, acceptable to the local highway authority, to mitigate the additional impact to be created so all lawful users are not disadvantaged.


Policy DM29: Biodiversity
The measures to safeguard and enhance the biodiversity value of development sites are welcomed, including seeking net biodiversity gain.


Schedule of proposed changes to the policies map
S30a West of City Corridors -suggest title should be West of City Strategic Wildlife Corridors (to match S30b: East of City Strategic Wildlife Corridors. The Strategic Wildlife Corridors are depicted in different colour patterns on the two plans which is somewhat confusing.


Strategic Wildlife Corridors Local Plan Review Background Paper
Proposed Hermitage to Westbourne Strategic Wildlife Corridor
A large area depicted as Biodiversity Opportunity Area (BOA) in Fig. 1 (immediately to the south of the Rivers Ems & Meadows Local Wildlife Site, Westbourne) is in fact housing and forms part of the settlement of Westbourne. You should consider if this land should be included as having potential for biodiversity enhancement.


Glossary
Includes Sites of Nature Conservation Importance (SNCIs) but not Local Wildlife Sites (LWSs). SNCIs are now known as LWSs.

Attachments:

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2217

Received: 07/02/2019

Respondent: Environment Agency

Representation Summary:

There are parts of Hunston that fall within flood zones 2 and 3. We would recommend that if possible the policy makes reference to the fact that built development should be located solely in Flood Zone 1. If this is not possible some reference would need to be made to flood risk and the requirement for the Neighbourhood Plan group to fully consider this through their site allocation process. If sites were to be allocated in flood zone 2 or 3 it is likely that
the Plan would need to be supported by a Level 2 SFRA or equivalent.

Full text:

Thank you for the consultation on the above document. We have reviewed the document and have the following comments to make in response.

Summary
Overall we are pleased to see that the Plan provides a framework to ensure that new
development will take place in a considered manner to address environmental constraints as well as provide policy hooks for the delivery of environmental enhancements. However, to ensure that the Plan is as effective as possible and meets necessary policy and legislative requirements we have made some recommendations for improvements. These are set out in detail below. Where we support a policy we have also highlighted this below.

We have highlighted concerns with policy AL6 - Land SW of Chichester and have made recommendations for more significant changes to policies in relation to flood risk management (both strategic and development management) and wastewater management and water quality.

As a general comment we note that a significant proportion of the housing numbers
proposed through the Local Plan will be delivered by Neighbourhood Plans. We have
highlighted key criteria for individual locations that we would wish to see considered by those Plans when allocating sites. Where possible we would wish to see these included within the Local Plan policy but as you will be aware we have produced a checklist for Neighbourhood Plan groups in your District which will guide the identification of sites and other key issues and opportunities to be addressed in their Plans.
We would be happy to meet with you to discuss further any of our comments and support the rewording of the policies prior to the production of a pre-submission Plan.

Specific comments

Strategic policies
Policy S12 - Infrastructure
Overall we support the policy. We would recommend that paragraph 3 be amended to
include reference to flood risk management infrastructure.

Policy S17 - Thorney Island
We are currently exploring opportunities for habitat creation in an area on Thorney Island. This is part of our Habitat Creation Programme which seeks to create new habitat to offset losses elsewhere as a result of sea level rise and implementation of coastal and flood risk management infrastructure.
Whilst the policy as drafted, along with other policies in the Plan, would not restrict this opportunity we would like you to consider whether further wording could be included to provide specific support for habitat creation.

Policy S18 - Integrated Coastal Zone Management
We support the continued inclusion of this policy and the specific references to key Plans.
We also support the intention that financial contributions should be sought to deliver both flood risk management infrastructure as well as improvements to the quality of watercourses in the area.

Policy S20 - Design
We support the specific requirements of this policy in point 5 and 8 with regard to green infrastructure and enhancing biodiversity and climate change resilience.

Policy S23 - Transport and Accessibility
The policy includes a new road connecting Birdham Road to the A27 Fishbourne
roundabout. The site includes areas within flood zones 2 and 3 and will cross a number of watercourse. It is essential that the requirements of the NPPF paras 157-8 are satisfied prior to the allocation. We have made detailed comments on this in relation to policy AL6 - Land South West of Chichester.

Policy S25 - The Coast
We are pleased to see the support in this policy for future habitat creation as well as the delivery of flood defences and adaptation to climate change. This supports principles of net environmental gain advocated through the NPPF and the 25 Year Environmental Plan as well as providing necessary policy hooks to support our future plans through our Habitat Creation Programme.
As we highlighted through the Issues and Options consultation this Programme was set up to deliver the compensatory habitat required to address the losses in habitat that would take place as a result of the flood and coastal risk management measures identified in the Shoreline Management Plans. There are specific locations within Chichester District which offer opportunities to provide saltmarsh and coastal grazing marsh in the medium to longer term. These locations include areas in Fishbourne, Chidham and Hambrook and on Thorney Island.

Policy S26 - Natural Environment
We would recommend that the policy wording be extended to say "protect and enhance biodiversity". This is consistent with the NPPF requirements in para 170 regarding net gain and current Government proposals to mandate biodiversity net gain for all new developments.

Policy S27 - Flood Risk Management
We support the intention of the policy, however, we would wish to see changes made to ensure the policy is as clear as possible. We would also recommend you consider what a strategic policy on flood risk management is seeking to achieve in addition to the development management policy. As drafted there are some duplications and/or inconsistencies between the two policies.
It may be more prudent to have a shorter overarching policy that seeks to ensure that flood risk will be taken account of at all stages in the planning process in order to avoid inappropriate development in areas at current or future risk (taking into account climate change) and to direct development away from areas of highest risk. Reference could and should be made to the Strategic Flood Risk Assessment to enable this. We would also support a requirement here for development to seek to achieve a reduction in flood risk for existing communities on and off site.
The principle of point 3 is supported but again should be considered whether it sits best within the development management policy.
We would recommend removing point 4. It is not clear entirely what the rationale behind this is but as drafted it suggests that development within areas with a certain level of flood risk would be approved. This should only be the case when the sequential and exception test have been satisfied in accordance with the NPPF paragraph 157- 8. I would be happy to discuss this further if the intention behind the statement is different.

Policy S29 - Green Infrastructure
We support the policy and are pleased to see specific reference to "blue" infrastructure.

Policy S30 - Strategic Wildlife Corridors
We are supportive of this policy and believe it provides a strong framework for the protection and enhancement of biodiversity within the Plan Area. In particular we support the corridors along watercourses and the links with Biodiversity Opportunity Areas.
As previously highlighted in our Issues and Options response to the Local Plan the
Environment Agency are looking to deliver more natural flood management (NFM) measures to complement and support traditionally engineered flood defenses. This is about working with natural processes in whole catchments and has the potential to help us manage and reduce flood risk in a more efficient, cost effective and sustainable way whilst securing wider environmental benefits. We would be interested to discuss whether the Strategic Wildlife Corridors Background Paper could be expanded upon to consider these opportunities.
A nationally consistent set of opportunity maps to indicate potential for natural flood
management have been produced and I have attached a briefing not which shows how you can access this screening information. The identification and safeguarding of wildlife corridors could support our further work on NFM in the Chichester District and we would welcome the opportunity to discuss this further. In particular we would be interested to discuss whether the Strategic Wildlife Corridors Background Paper could be expanded upon to consider these opportunities.

Policy S31 - Wastewater Management and Water Quality
We support the intention of this policy, however, we recommend that the policy is amended to ensure that specific issues associated with the Apuldram WwTW catchment are addressed and that wider opportunities for the necessary protection and enhancements of water quality in the catchments across the Plan area are taken forward through development. As drafted the supporting text to the policy talks primarily around wastewater treatment capacity and impacts on water quality. However, we would recommend that this is expanded to discuss wider water quality and water resources issues within the Plan area.
This should include reference to the Water Framework Directive and the South East River Basin Management Plan, for which the Council has an obligation to support their delivery.
We would wish to see the Plan include a policy that will ensure that the design and location of development will both protect and enhance water bodies, both surface and groundwater.
We are aware of a few adopted policies regarding water quality that you may wish to review ahead of the further iteration of your Plan. These include policy W DM1 - Water supply and quality in the Arun Local Plan and Policy 31 - Integrated Water Management and the water cycle in the Cambridge Local Plan. The Policy in the Arun Local Plan is subdivided in to 3 sections to cover issues of water supply, water quality and catchment specific measures.
This approach or layout may be useful for you to consider here.
You may also wish to consider whether there are elements of this policy that would be better situated in a development management policy to direct decision making on individual sites.
I would be happy to work with you further to develop this policy, however, to support this the following identifies some key wording that could be included:
"All new development must demonstrate:
* That it has no adverse impact on the quality of water bodies and groundwater, or will prevent future attainment of good status;
* That development contributes positively to the water environment and its ecology and does not adversely affect surface and ground water quality"
This will reflect that impacts on water quality will not solely relate to wastewater infrastructure but can include diffuse pollution as well as physical changes to watercourses.
With regard to the specific requirements for the Apuldram WwTW the policy as drafted broadly reflects the current adopted Plan policy. Would there be an opportunity here for the policy to reflect elements of the recently endorsed Position Statement between the Environment Agency and Southern Water in terms of managing development in the catchment?
The policy makes reference to the higher building regulations standard of 110 l per person per day. We support this standard but would recommend you consider whether this detail is needed in this strategic policy as well as development management policy DM16 - Sustainable Design and Construction.

Site Allocations
Please note we have no additional comments to make on the sites that are being taken forward from the current adopted Local Plan as we consider that the key policy criteria we sought at that stage has been transposed across. We continue to support these requirements.

Policy S32 - Design Strategies for Strategic and Major Development Proposals
We support this policy and specifically requirements for issues such as green infrastructure and SuDS to be fully considered through a Masterplan. Without this overarching vision for larger sites it is often difficult to provide a comprehensive scheme to address key environmental constraints and opportunities.

Policy AL13 - Land East of Chichester
There is a small area within the site located in Flood Zone 2, along with an additional surface water body (lake). We would recommend that the masterplan for this site fully considers these constraints in designing the site including the adopting the sequential approach. We would wish to see built development located solely within Flood Zone 1.

Policy AL 5 - Southern Gateway
We have previously made comments on the proposals for the Southern Gateway through the adopted masterplan for the site. As highlighted there are a number of constraints to development in this area, however, we are pleased to see specific criteria in the policy toensure that these key constraints to the site within our remit are fully considered.
These are:
- Bullet 8 which requires the provision of a wastewater management plan which
demonstrates no net increase in flow to the Apuldram WwTW. This is in line with the
Surface Water and Foul Drainage SPD and the Position Statement on managing new
housing development in the Apuldram (Chichester) Wastewater Treatment Works
Catchment agreed between the Environment Agency and Southern Water.
- Bullet 10 which sets out the requirement for a Flood Risk Assessment to address the
specific flood risk issues on the site. We would recommend that this policy criteria
could be expanded upon to require the sequential approach within the site and to
ensure that more vulnerable uses such as housing be located in the lowest areas of
flood risk.

Policy AL6 - Land SW of Chichester
At this stage we do not support the inclusion of this site within the Plan.
The allocation is composed of housing, employment and a road scheme. Large areas of the allocation falls within flood zones 2 and 3 and we would wish to see further evidence to support this allocation. This may be as part of a Level 2 Strategic Flood Risk Assessment for this site which would then inform a Sequential and if necessary an Exceptions Test. The assessment would need to consider how the proposals could be delivered and identify any mitigation and/or compensation measures that may be necessary to ensure that the development is safe and that there is no increase in flood risk to third parties.
Whilst we note that there are areas outside of the flood plain within the allocation and that some of the development could avoid these areas it is anticipated that the road would cross the flood plain and therefore further detailed understanding of this risk and how it would be managed should be provided.
As drafted the policy makes no reference to flood risk and we would wish to see this
amended.
With regard to housing development we would wish to ensure that all development be located in Flood Zone 1 and that the policy criteria would reflect this.
Other issues include the crossing of watercourses and impacts on biodiversity and water quality. This should be referenced within the policy criteria with requirements for any watercourse crossings to be clear span in design. This will ensure that flood water conveyance is not impeded and protect the habitat associated with those watercourses.
In addition to flood risk we also have concerns with regard to where the sites wastewater would drain to. In line with our Position Statement on managing new housing development in Apuldram (Chichester) Wastewater Treatment Works Catchment allocations within the Local Plan should not drain to the Apuldram WwTW but be directed to alternative WwTW catchments, notably Tangmere WwTW via the new sewer pipeline connection once operational.
It is difficult to understand how this site would connect to an alternative WwTW and therefore would question whether the site would be deliverable.

Policy AL9 - Fishbourne
Fishbourne parish falls within the Apuldram WwTW catchment and we would recommend that the policy makes specific reference to the issues that the Neighbourhood Plan group should consider when identifying sites for their Local Plan.
We would also recommend that specific reference is made to the Source Protection Zone that covers part of the parish in order to ensure that the groundwater, and in turn the drinkingwater supply, is protected.

Policy AL11 - Hunston
There are parts of Hunston that fall within flood zones 2 and 3. We would recommend that if possible the policy makes reference to the fact that built development should be located solely in Flood Zone 1. If this is not possible some reference would need to be made to flood risk and the requirement for the Neighbourhood Plan group to fully consider this through their site allocation process. If sites were to be allocated in flood zone 2 or 3 it is likely that the Plan would need to be supported by a Level 2 SFRA or equivalent.

Policy AL13 - Southbourne Parish
Point 16 identifies the need to ensure that sufficient capacity is available at the relevant Wastewater Treatment Works prior to the delivery of development. This could be expanded to include sewer network capacity. Liaison with Southern Water regarding any necessary phasing of development would be encouraged.

Development Management Policies

Policy DM5 - Accommodation for GTTTS
We support the specific criteria in this policy to ensure that GTTS sites are not located in areas at risk of flooding.

Policy DM14 - Caravan and Camping Sites
We support the particular reference to restricting the occupancy of these sites in flood risk areas. However, there is no specific mention that flood risk areas should be avoided where possible. We would recommend that this should be included within the policy criteria.

Policy DM15 - Horticultural Development
We are pleased to see specific reference to the need to demonstrate adequate water
resources are available and/or water efficiency measures.

Policy DM16 - Sustainable Design and Construction
We support the requirement for new development to achieve a water usage of a maximum of 110litres per head per day.
For completeness we recommend that point 5 should be expanded to include compensation as well as make reference to net gain. This is in line with NPPF para 170.
We support the requirement in point 8 with regard to measures to adapt to climate change.

Policy DM18 - Flood Risk and Water Management
para. 7.115 - reference to the Environment Agency should be removed from this sentence.
The responsibility for surface water drainage and consideration of SuDS sits with West Sussex County Council as the Lead Local Flood Authority for this area.
para. 7.116 - vulnerability - it should be noted that not all development types would be appropriate in all flood zones. Basement dwellings would not be supported in flood zone 3. This paragraph should be amended to reflect this.
We would recommend that you review this policy alongside the strategic policy on flood risk to ensure that they are complementary. Whilst the intention of the policy is good some further clarity could be provided to ensure that all sources of flood risk are considered through decision making.
As drafted there is no reference to the Sequential Test which is a key step in decision
making with regard to proposals in a flood zone. It appears that a number of the criteria included in policy 42 of the current adopted Local Plan have been stripped out. We would recommend further consideration of this for the next iteration of the Plan.
We note that the policy also makes reference to wider water management and does refer tothe South East River Basin Management Plan, however, as per our comments on policy S31 we would wish to see a specific policy that provides for the protection and enhancement of water quality. It may be prudent to consider whether an overarching strategic policy to address flood risk and water management would be best with separate detailed development management policies for each topic.
We would be happy to work with you regarding this detail.

Policy DM20 - Development around the coast
We support this policy and the requirement to safeguard a strip of land behind existing or proposed sea defence or coastal works. Please note that the Environment Agency would seek a 16 metre buffer behind any of our tidal defences.
We support the specific requirement to ensure that development for boat or marine use would not be detrimental to water quality.

Policy DM24 - Air Quality
We are pleased to see that this policy recognises that new development may be located near to existing uses that may be potentially polluting to housing. It is important that the onus should be on the developer/applicant to manage any impact to ensure that they don't leave the existing user affected, e.g. by complaints.

Policy DM26 - Contaminated Land
We support this policy as drafted.

Policy DM29 - Biodiversity
We support this policy as drafted and are pleased to see that specific reference has been
provided to ensure that net gain in biodiversity is actively pursued. Consideration should be
given to the current Government consultation on mandating biodiversity net gain in all new
development and whether this may require further strengthening of the policy wording.
Policy DM32 - Green Infrastructure
We support policy.

Attachments:

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2272

Received: 01/02/2019

Respondent: Historic England

Representation Summary:

Historic England has no comments on the principle of land being allocated in the revised Hunston Neighbourhood Plan.

However, we note that one of the specific issues that need to be taken into account in planning for development at Hunston identified in paragraph 6.77 of the Plan is "Respecting the setting of listed buildings and the Hunston conservation area".

We welcome the recognition and identification of this issue, but we consider that it should be included as a specific requirement in Policy AL11.

Full text:

Paragraph 1.5 of the Local Plan Review states "This Plan seeks to balance the economic, social and environmental dimensions of sustainable development". "Balance" implies some gains and some losses. However, this does not reflect the four bullet points that follow this sentence.
In addition, Paragraph 8 of the National Planning Policy Framework explains that;
"Achieving sustainable development means that the planning system has three overarching objectives, which are interdependent and need to be pursued in mutually supportive ways (so that opportunities can be taken to secure net gains across each of the different objectives)".

We therefore suggest that "balance" is not the most appropriate word.

The three overarching objectives include; "c) an environmental objective - to contribute to protecting and enhancing our natural, built and historic environment......". We therefore welcome the fourth bullet point of paragraph 1.5; "Protecting and enhancing the unique and special qualities of our environment".

Reword the first sentence of paragraph 1.5 as; "This Plan seeks to deliver the economic, social and environmental dimensions of sustainable development in mutually supportive ways".

Paragraph 1.16 explains that the National Planning Policy Framework reiterates the importance of significantly boosting the supply of new dwellings, whilst ensuring provision for other development needs including economic growth.
Whilst not untrue, we consider that this does not fully represent the Government's objectives and policies as set out in the Framework and therefore gives the misleading impression that the Framework is only about housing supply and economic development.
In fact, the protection and enhancement of the natural, built and historic environment is also identified as important in the Framework e.g. in the environmental overarching objective for the planning system as set out in paragraphs 8, 11b)i and 20 d).
Reword the final sentence of paragraph 1.16 as:
"The importance of significantly boosting the supply of new dwellings is reiterated, whilst ensuring provision for other development needs including economic growth and protecting and enhancing the natural, built and historic environment".
Paragraph 31 of the National Planning Policy Framework requires "The preparation and review of all policies should be underpinned by relevant and up-to-date evidence". We previously expressed our concerns about the historic evidence base for the policy framework for the district when commenting on the Issues and Options stage of the Local Plan Review;
"We are aware of the Council's series of Conservation Area Character Appraisals, The Future Growth of Chichester Study and the Landscape Capacity Studies. However, the Council's "Supporting documents" webpage has no historic environment documents and we are not clear if the Council has other historic environment evidence e.g. is there an extensive urban survey of Chichester or other townscape or characterisation study ? Is there an urban archaeological database ? Is there a list of locally important heritage assets ? Has the Council undertaken a survey of grade II buildings at risk ?".
However, looking at the Council's Local Plan Review Preferred Approach Plan - Evidence Base - December 2018 webpage, the only specific historic environment evidence base document identified is the Chichester Historic Environment Strategy and Action Plan. Whilst we welcome the Strategy, we have previously expressed the view that we do not consider that it forms, by itself, an adequate historic environment evidence base for the Local Plan Review.
We are aware that the Council has a list of locally important buildings, but that Chichester was not covered by the West Sussex Extensive Historic Town Surveys - perhaps as it was thought a candidate for the more intensive approach of an Urban Archaeological Database (UAD). However, we are not aware that such a UAD exists, and whilst we are aware of the Council's Historic Environment Record (the availability of which accords with paragraph 187 of the National Planning Policy Framework), we do wonder if the archaeological evidence and significance of the city is fully understood and readily available. We suggested that the Historic Environment Strategy could set out actions to enhance understanding and management of the archaeological resource of the historic city and we would be pleased to discuss how we might be able to assist with this.
We will expect the Council to have an adequate, up-to-date and relevant historic environment evidence base and to demonstrate in the Pre-Submission Local Plan how that historic evidence base has informed and influenced the Plan's policies and site allocations.
The historic environment evidence base for the Local Plan Review should be set out on the Council's Evidence Base webpage. If there are indeed gaps in that evidence base, then these should be filled and that evidence taken on board in preparing the Pre-Submission Local Plan Review document.
Historic England welcomes and supports the reference to the historic environment of Chichester district, and the heritage assets therein, in paragraphs 2.27 and 2.28 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.

Historic England welcomes and supports, in principle, the identification of "Protect the area's valuable heritage and historic assets" as one of the challenges faced by the Plan.
However, the National Planning Policy Framework requires local plans to deliver an environmental overarching objective which includes "to contribute to conserving and enhancing our natural, built and historic environment" (paragraph 8 c)) and to include strategic policies to make sufficient provision for "conservation and enhancement of the natural, built and historic environment" (our underlining).
The Framework therefore requires local planning authorities, through their local plans, to do more than just conserve the historic environment i.e. to enhance it as well. This should be identified as a challenge (although it is also an opportunity).
Reword the last bullet point of paragraph 2.28 as; "Protect and enhance the area's valuable heritage and historic assets".
Historic England welcomes, in principle, as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework, the reference to the historic environment in paragraph 3.1;

"It is the intention of the Council to enable the delivery of infrastructure, jobs, accessible local services and housing for future generations while supporting the historic and natural environment".

However, the National Planning Policy Framework refers to "conserving and enhancing our natural, built and historic environment" (paragraph 8 c)) and the "conservation and enhancement of the natural, built and historic environment". We therefore suggest that "supporting" should be "conserving and enhancing" as terminology more consistent with the Framework and possibly ambiguous than "supporting".

Reword the first sentence of paragraph 3.1 as;
"It is the intention of the Council to enable the delivery of infrastructure, jobs, accessible local services and housing for future generations while conserving and enhancing the historic, built and natural environment".
Historic England welcomes the inclusion of "Have a quality of life that is enriched through opportunities to enjoy our local culture, arts and a conserved and enhanced heritage;" in the Vision as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes "As an historic walled cathedral city, its rich cultural and architectural heritage will be conserved, enhanced and promoted together with the views and landscape value afforded by its setting" in paragraph 3.4 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports "The conservation and enhancement of the historic environment, the high quality landscapes and the agricultural and other rural activities that support it will remain paramount" in paragraph 3.14 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports, in principle, the Strategic Objective "Conserve and enhance landscape and heritage" as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework. However, we suggest that it could be rather more ambitious e.g. "Conserve, enhance, increase appreciation and enjoyment of and access to heritage"
Paragraph 4.2 states that; "New development must achieve sustainable development principles and must not adversely affect the character, quality, amenity or safety of the built environment, wherever it occurs". The implication is that this is a requirement of the National Planning Policy Framework, but we cannot find this exact wording in the Framework.

However, paragraph 127 of the Framework does set out what planning policies and decisions should ensure of developments, including "are sympathetic to local character and history" and "establish or maintain a strong sense of place". In addition, paragraph 185 of the Framework requires plans to set out a positive strategy for the conservation and enjoyment of the historic environment, which should take into account "the desirability of new development making a positive contribution to local character and distinctiveness".

We therefore consider that the final sentence of paragraph 4.2 should be revised to more closely reflect the requirements of the National Planning Policy Framework.

Reword the final sentence of paragraph 4.2 as ""New development must achieve sustainable development principles, must not adversely affect the history, quality, amenity or safety of the natural, built and historic environment and should make a positive contribution to local character and distinctiveness and establish or maintain a sense of place". (Alternatively, these could be set out as bullet points for clarity).
Historic England welcomes and supports "enhance the quality of the built, natural, historic, social and cultural environments" in Policy S2 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Although the historic environment is not identified as a constraint or as an opportunity for enhancement in paragraph 4.12 as a factor in the definition of the Settlement Hierarchy, we note that paragraph 4.14 does explain that consideration has been given to other factors in determining whether a settlement is a suitable location for additional housing growth. We would like to think that these other factors include the potential effects on the historic environment.
Historic England welcomes and supports "where possible enhances the character, significance and setting of heritage assets" as one of the considerations to guide potential discussions on a possible site for a new settlement in paragraph 4.33 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports "it is acknowledged that new development needs to be planned sensitively with special regard to the unique character of the city's historic environment and setting, and should be underpinned by historic characterisation assessments" in paragraph 4.90 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Nevertheless, we suggest that reference should also be made to heritage impact assessments to underpin the planning of new development.
Reword paragraph 4.90 to read;
"it is acknowledged that new development needs to be planned sensitively with special regard to the unique character of the city's historic environment and setting, and should be underpinned by historic characterisation assessment and heritage impact assessments".
Historic England welcomes and supports "such development will need to be sensitive to the
historic character of the city" in paragraph 4.91 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports "conserve and enhance the city's historic character and heritage", "Enhance the city's existing heritage, arts and cultural facilities", "Protect views of the cathedral" and "All development will be required to have special regard to the city's historic character and heritage. Development proposals should be underpinned by historic characterisation assessments and make a positive contribution to the city's unique character and distinctiveness" in Policy S13 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Nevertheless, we would like to see a reference to heritage impact assessments to underpin development proposals.
We also wonder if it would be helpful to have a specific policy to protect important views, allied to or combined with a policy for tall buildings in the historic city ?
Reword Policy SP13 to read "Development proposals should be underpinned by historic characterisation assessment and a heritage impact assessment......".
Historic England welcomes and supports "Any development proposals within the vicinity of the site must clearly demonstrate how the development would protect, and where possible enhance, the operation and heritage of the site as a motor-circuit and airfield" in Policy S15 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports "All proposals must ensure that the cultural and historical significance of the military facilities (and any other significant archaeological assets) located on the site, are understood and inform the scope of future development of that site" in Policy S17 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
However, we would prefer "significant archaeological assets" to be retained in situ.
Reword Policy S17 as;
"All proposals must ensure that the cultural and historical significance of the military facilities (and any other significant archaeological assets) located on the site, are understood and inform the scope of future development of that site, with any significant archaeological assets retained in situ".
Paragraph 2.2 of the Plan notes that the North of the Plan Area has "rich cultural and heritage assets". We are surprised, therefore, that paragraph 4.128 has no mention of these assets.
Reword paragraph 4.128 "This part of the plan area is predominantly rural with few sizeable settlements, characterised by undulating countryside with a high proportion of woodland, typical of the Low Weald landscape. Conserving the rural character of the area, with its high quality landscape and natural and historic environment, is a key objective".
Historic England welcomes and supports "Conserve and enhance the rural character of the area, the quality of its landscape and the natural and historic environment;" in Policy S19 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes paragraph 5.1 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Strictly-speaking, historic parks and gardens are registered for their special historic interest rather than their protection per se, but one of the purposes of Registration is to encourage appropriate protection and inclusion on the Register is a material consideration in the determination of planning applications.
Historic England welcomes paragraph 5.5 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports Policy S20, particularly the references to history, historic character and local identity in clause 1, sense of place in clause 2, character in clause 8 and high quality public realm in clause 11 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
However, we would also like to see a specific clause relating to heritage assets.
Add a new clause; "conserves or enhances the significance, special interest, character and appearance of heritage assets".
Historic England welcomes and supports paragraph 5.12 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes, in principle, paragraph 5.13 states that "Where development proposals might affect a heritage asset the Council will identify and assess the particular significance of the heritage asset and seek to avoid or minimise any conflict between the conservation of the heritage asset and any aspect of the proposal" as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
This very largely reflects paragraph 190 of the National Planning Policy Framework, but the Framework requires local planning authorities to take the particular significance of any heritage asset that might be affected by a proposal into account when considering the impact of a proposal on a heritage asset, "to avoid or minimise any conflict between the heritage asset's conservation and any aspect of the proposal". The requirement is clear - any conflict should be avoided or minimised; it is not sufficient to merely "seek to" avoid or minimise that conflict.

In addition, paragraph 189 of the Framework states;

"In determining applications, local planning authorities should require an applicant to describe the significance of any heritage assets affected, including any contribution made by their setting......Where a site on which development is proposed includes, or has the potential to include, heritage assets with archaeological interest, local planning authorities should require developers to submit an appropriate desk-based assessment and, where necessary, a field evaluation.

There is, therefore, a clear onus to be placed upon the applicant/developer to identify and describe the significance of any heritage assets affected.

Paragraphs 193, 194, 195 and 196 of the Framework set out how local planning authorities should consider the impact of a proposed development on the significance of a designated heritage asset. We believe that this could usefully be summarised in the Plan.

Reword paragraph 5.13;
"Where development proposals might affect a heritage asset the Council will identify and assess the particular significance of the heritage asset and take that significance into account when considering the impact of a proposal on a heritage asset, to avoid or minimise any conflict between the heritage asset's conservation and any aspect of the proposal".
Add new paragraphs;
"For applications which affect, or have the potential to affect, heritage assets the applicant will be expected to describe the significance of the asset and its setting, using appropriate expertise; at a level of detail proportionate to its significance and sufficient to understand the potential impact of the proposal; using appropriate references such as the Historic Environment Record and, if necessary, original survey (including, for assets of archaeological interest, an appropriate desk-based assessment and, where necessary, a field evaluation)";
"When considering the impact of a proposed development on the significance of a designated heritage asset, the Council will give great weight to the asset's conservation. Any harm to, or loss of, the significance of a designated heritage asset (from its alteration or destruction, or from development within its setting), will require clear and convincing justification"; and

"The Council will refuse proposals that would lead to substantial harm to (or total loss of significance of) a designated heritage asset unless it can be demonstrated that the substantial harm or total loss is necessary to achieve substantial public benefits that outweigh that harm or loss, or all of the circumstances in paragraph 195 of the National Planning Policy Framework apply. For proposals that would lead to less than substantial harm to the significance of a designated heritage asset, the Council will weigh this harm against the public benefits of the proposal".

Historic England welcomes and supports Policy S22, which we consider complies with the requirements of paragraphs 17 and 20 of the National Planning Policy Framework to contain strategic policies and for those strategic policies to make sufficient provision for the conservation and enhancement of the historic environment.

We also consider that the policy forms part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework. We consider that the word "positive" is significant, and we believe that the Plan (and Council) should be proactive in the conservation and enhancement of the historic environment. National Planning Practice Guidance states "Such a [positive] strategy should recognise that conservation is not a passive exercise".
We therefore consider that the positive strategy for the conservation and enjoyment of the historic environment is not a passive exercise but requires a plan for the maintenance and use of heritage assets and for the delivery of development including within their setting that will afford appropriate protection for the asset(s) and make a positive contribution to local character and distinctiveness. We therefore look to local plans to contain commitments to positive measures for the historic environment. We therefore welcome the commitments within Policy S22 to positive actions, including heritage at risk, which paragraph 185 requires to be part of that positive strategy for the conservation and enjoyment of the historic environment. However, we do feel that the supporting text could helpfully explain a little more about the Council's approach to heritage at risk, perhaps borrowing some text from the Chichester Historic Environment Strategy and Action Plan.
We also consider that the positive strategy should comprise recognition throughout the Plan of the importance of the historic environment, of the historic environment's role in delivering the Plan's vision and the wider economic, social and environmental objectives for the Plan area, and of the potential impacts of the Plan's policies and proposals on the historic environment.
We are pleased to have identified a number of references throughout the Plan to the historic environment and we therefore consider that the Plan sets out an adequate positive strategy for the conservation and enjoyment of that historic environment as required by paragraph 185 of the National Planning Policy Framework and that the Plan is therefore compliant with that paragraph.

Add a new paragraph explaining what "heritage at risk" is and the Council's approach to assets at risk e.g.

"Unfortunately, heritage assets can be at risk from neglect, decay or other threats. Designated assets at risk, with the exception of Grade II secular buildings and Grade II places of worship used less than six times a year, are identified on the Historic England Heritage at Risk Register. Within the district outside the South Downs National Park, six assets are on the Register (February 2018): three scheduled monuments, two listed buildings and one conservation area. The Council will actively seek to address threats to heritage assets by recording and monitoring Heritage at Risk in Chichester District, publishing it on our website and working with the owners of heritage assets at risk to find solutions and secure repairs to bring them back into active use, including where appropriate viable new uses and/or proposals for enabling development so they are preserved for future generations."

Historic England suggests that paragraph 5.37 could also refer to the range of heritage assets to be found in the countryside of the Plan area.
Reword paragraph 5.37 as;

"It is valued for many reasons, including agriculture and community food production, its landscape qualities including the special characteristics of Chichester Harbour and Pagham Harbour, the setting it provides for Chichester City and other towns and villages, its range of heritage assets, including historic landscapes, and the opportunities it provides for recreation and biodiversity".
Historic England welcomes and supports clause d of Policy S32; "integrate with the surrounding built, historic and natural environments" as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
As noted in paragraph 6.12, the Chichester Entrenchments Scheduled Monument lies partly within and partly immediately to the north of the site. Paragraph 194 of the National Planning Policy Framework identifies Scheduled Monuments as being assets "of the highest significance", substantial harm to or loss of which should be wholly exceptional.

We have previously commented (as English Heritage) on the allocation of this site during the consultation on the Key Policies. We explained that development close to the earthworks might harm the historical value of the heritage asset by interrupting views between its parts and introducing incongruous land-use in its immediate surroundings. This in turn would make it difficult to appreciate the asset's open rural setting, its extensive linear nature and its purpose of enclosing large areas of open land.

Accordingly, we initially objected to the form of the allocation in the Key Policies, but subsequently withdrew that objection following amendments to the boundary of the Strategic Development Location on its northern side so that the boundary ran along the south edge of the belt of woodland in which the scheduled monument sits, thereby entirely excluding the monument from the SDL, and the allocation of the northern area of the amended site as open space.
We are therefore pleased to see that the Strategic Site Allocation still excludes the scheduled monument. We also welcome and support the following requirements of Policy AL1, which we consider provide, in principle, adequate protection for the Scheduled Monument in accordance with the National Planning Policy Framework:
6. Landscaped to protect priority views of Chichester Cathedral spire;
7. Keep land north of the B2178 in open use, free from built development, to protect the natural history interest of both Brandy Hole Copse, and the setting of the Chichester Entrenchments Scheduled Monument;
8. Conserve, enhance and better reveal the significance of the Chichester Entrenchments Scheduled Monument and other non-designated heritage assets and their settings and to record and advance understanding of the significance of any heritage assets to be harmed or lost;
However, this comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Historic England makes no comment on the principle of the Shopwyke Strategic Site Allocation, which we note is an existing allocation.
However, the Grade II listed barn at Greenway Farm is located to the south-west of the site and the Grade II listed Shopwyke Grange and the Grade II* listed Shopwyke Hall are located to the south-east. Paragraph 194 of the National Planning Policy Framework states "Any harm to, or loss of, the significance of a designated heritage asset (from its alteration or destruction, or from development within its setting), should require clear and convincing justification". The paragraph identifies Grade II* buildings as assets of the "highest significance".

Historic England therefore welcomes and supports, in principle, the following requirement of Policy AL2, which we consider provide, in principle, adequate protection for the listed barn and Shopwyke Hall in accordance with the National Planning Policy Framework:
7. Protect existing views of Chichester Cathedral spire and conserve and enhance the historic significance of the listed barn at Greenway Farm and the cluster of buildings associated with the grade II* listed Shopwhyke Hall, which should be analysed at an early stage of the masterplan.
However, we consider that reference should also be made to the Grade II listed Shopwyke Grange. This comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Reword criterion 7;"Protect existing views of Chichester Cathedral spire and conserve and enhance the historic significance of the listed barn at Greenway Farm, the listed Shopwyke Grange and the cluster of buildings associated with the grade II* listed Shopwhyke Hall which should be analysed at an early stage of the masterplan".
According to our records there are no designated heritage assets on this site, although the Grade II listed Shopwyke Grange and Grade II* listed Shopwyke Hall lie to the north-east of the allocated area, Paragraph 194 of the National Planning Policy Framework states "Any harm to, or loss of, the significance of a designated heritage asset (from its alteration or destruction, or from development within its setting), should require clear and convincing justification". The paragraph identifies Grade II* buildings as assets of the "highest significance".

We note that criterion 7 of Policy AL2 requires the development of the Shopwyke Strategic Site Allocation to ".......conserve and enhance the historic significance of the......cluster of buildings associated with the grade II* listed Shopwhyke Hall, which should be analysed at an early stage of the masterplan. We have suggested in our comments on this policy that it include reference to the listed Shopwyke Grange, and we consider that this requirement should also be included in Policy AL3 to provide, in principle, adequate protection for the listed barn and Shopwyke Hall in accordance with the National Planning Policy Framework.

Historic England welcomes and supports criterion 8 of Policy AL2; "Existing views of Chichester Cathedral spire are to be protected". However, this comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Reword criterion 8 as;
"Protect existing views of Chichester Cathedral spire and conserve and enhance the historic significance of the listed Shopwyke Grange and the cluster of buildings associated with the grade II* listed Shopwhyke Hall which should be analysed at an early stage of the masterplan".
Historic England makes no comment on the principle of the two sites at Land at Westhampnett/North East Chichester Strategic Site Allocation, which we note were part of a broad strategic development location in the adopted Local Plan.
However, the site abuts the Graylingwell Hospital Conservation Area, the buildings of the former 'pauper lunatic asylum' (including the Grade II listed chapel), the Grade II listed Summersdale Farmhouse and a Grade II registered park and garden. Paragraph 194 of the National Planning Policy Framework states "Any harm to, or loss of, the significance of a designated heritage asset (from its alteration or destruction, or from development within its setting), should require clear and convincing justification".
Historic England therefore welcomes and supports, in principle, the following requirement of Policy AL4, which we consider provide, in principle, adequate protection for these designated assets in accordance with the National Planning Policy Framework:
9. Development should be designed with special regard to the Graylingwell Hospital
Conservation Area, the buildings of the former 'pauper lunatic asylum' and the Grade II registered park and garden in which they sit, and to other listed buildings in the vicinity of the site and their settings. Important views of Chichester Cathedral spire from the area should be protected;
This comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Historic England makes no comment on the principle of the Southern Gateway Strategic Site Allocation.
However, the site includes a row of Grade II listed buildings on Southgate and a number of non-designated heritage assets (the southern gateway of the city had Roman roads converging upon it and this is likely to result in enhanced archaeological potential in this part of the city. The development of suburbs in the medieval and later periods is a further factor with both the canal and railway as examples of later uses of the area. There are a number of buildings of interest, including the former Law Courts and Bus Garage). Part of the site lies within the Chichester Conservation Area and there are listed buildings adjacent to the site.
Paragraph 184 of the National Planning Policy Framework states heritage assets "are an irreplaceable resource, and should be conserved in a manner appropriate to their significance, so that they can be enjoyed for their contribution to the quality of life of existing and future generations". Paragraph 194 of the Framework states "Any harm to, or loss of, the significance of a designated heritage asset (from its alteration or destruction, or from development within its setting), should require clear and convincing justification".

Historic England therefore welcomes and supports, in principle, the following requirements of Policy AL5;

3. Respect for the historic context and make a positive contribution towards protecting and enhancing the local character and special heritage of the area and important historic views, especially those from the Canal Basin towards Chichester Cathedral;
9. Include an archaeological assessment to define the extent and significance of any
archaeological remains and reflect these in the proposals, as appropriate;
However, we consider that these requirements should be strengthened to ensure that they provide adequate protection for these assets in accordance with the National Planning Policy Framework. In addition, we consider that Policy AL5 should promote more strongly the opportunity to use the heritage of the area to help define its character and the desirability of new development making a positive contribution to local character and distinctiveness as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
These comments are without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Reword clause 2 as follows;
Proposals should include a high quality distinctive design response appropriate to this gateway location and based on the character and heritage of the area, which establishes a clear hierarchy of streets and spaces, active frontages of buildings which front streets and spaces with clearly defined building lines;
Reword clause 3 as follows;
3. Respect for the historic context and make a positive contribution towards protecting and enhancing the local character and special heritage of the area, including the Conservation Area, listed buildings (both on and adjacent to the site), non-designated buildings of historic interest and important historic views, especially those from the Canal Basin towards Chichester Cathedral;
Reword clause 9 as follows;
9. Include an archaeological assessment to define the extent and significance of any
archaeological remains and reflect these in the proposals;
According to our records, the site Land South-West of Chichester (Apuldram and Donnington Parishes) contains no designated heritage assets. We therefore have no comment on the principle of the allocation, although we would expect its potential for non-designated archaeology to have been assessed, with reference to the Council's Historic Environment Record, in accordance with paragraph 187 of the National Planning Policy Framework which states;
Local planning authorities should maintain or have access to a historic environment record. This should contain up-to-date evidence about the historic environment in their area and be used to:
a) assess the significance of heritage assets and the contribution they make to their environment; and
b) predict the likelihood that currently unidentified heritage assets, particularly sites of historic and archaeological interest, will be discovered in the future.
Historic England welcomes and supports clause 3:
3. Protect existing views of Chichester Cathedral spire and the setting of the Chichester Harbour Area of Outstanding Natural Beauty which should be analysed at an early stage of the masterplan;
This comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
According to our records, the site at Highgrove Farm, Bosham, contains no designated heritage assets. We therefore have no comment on the principle of the allocation, although we would expect its potential for non-designated archaeology to have been assessed, with reference to the Council's Historic Environment Record, in accordance with paragraph 187 of the National Planning Policy Framework which states;
Local planning authorities should maintain or have access to a historic environment record. This should contain up-to-date evidence about the historic environment in their area and be used to:
a) assess the significance of heritage assets and the contribution they make to their environment; and
b) predict the likelihood that currently unidentified heritage assets, particularly sites of historic and archaeological interest, will be discovered in the future.
This comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.

Historic England has no comments on the principle of land being allocated in the revised Fishbourne Neighbourhood Plan for a minimum of 250 dwellings.
However, we note that one of the specific issues that need to be taken into account in planning for development at Fishbourne identified in paragraph 6.65 of the Plan is "Protecting the heritage assets of Fishbourne and their setting".
We welcome the recognition and identification of this issue, but we consider that it should be included as a specific requirement in Policy AL9, to ensure that the allocation of the site or sites in the Neighbourhood Plan conforms with the National Planning Policy Framework, particularly paragraphs 184 and 194.
Add the following clause to Policy AL9;
"Demonstration that the development would not have an adverse impact on the significance of heritage assets, including listed buildings and the Fishbourne Roman site Scheduled Monument, or the character or appearance of the Fishbourne Conservation Area".
Historic England has no comments on the principle of land being allocated in the revised Chidham and Hambrook Neighbourhood Plan for a minimum of 500 dwellings.
However, we consider that Policy AL10 should include a specific requirement to ensure that the allocation of the site or sites in the Neighbourhood Plan conforms with the National Planning Policy Framework, particularly paragraphs 184 and 194.
Add the following clause to Policy AL10;
"Demonstration that the development would not have an adverse impact on the significance of heritage assets.
Historic England has no comments on the principle of land being allocated in the revised Hunston Neighbourhood Plan for a minimum of 250 dwellings.
However, we note that one of the specific issues that need to be taken into account in planning for development at Hunston identified in paragraph 6.77 of the Plan is "Respecting the setting of listed buildings and the Hunston conservation area".
We welcome the recognition and identification of this issue, but we consider that it should be included as a specific requirement in Policy AL11, to ensure that the allocation of the site or sites in the Neighbourhood Plan conforms with the National Planning Policy Framework, particularly paragraphs 184 and 194.
Add the following clause to Policy AL11;
"Demonstration that the development would not have an adverse impact on the significance of heritage assets, including listed buildings, or on the character or appearance of the Hunston Conservation Area."
According to our records, the site Land north of Park Farm, Selsey, contains no designated heritage assets. We therefore have no comment on the principle of the allocation, although we would expect its potential for non-designated archaeology to have been assessed, with reference to the Council's Historic Environment Record, in accordance with paragraph 187 of the National Planning Policy Framework which states;
Local planning authorities should maintain or have access to a historic environment record. This should contain up-to-date evidence about the historic environment in their area and be used to:
a) assess the significance of heritage assets and the contribution they make to their environment; and
b) predict the likelihood that currently unidentified heritage assets, particularly sites of historic and archaeological interest, will be discovered in the future.

This comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Historic England has no comments on the principle of land being allocated in the revised Southbourne Neighbourhood Plan for a minimum of 1,250 dwellings.
However, we consider that a specific requirement should be included in Policy AL13 to ensure that the allocation of the site or sites in the Neighbourhood Plan conforms with the National Planning Policy Framework, particularly paragraphs 184 and 194.
Add the following clause to Policy AL13;
"Demonstration that the development would not have an adverse impact on the significance of heritage assets, including listed buildings, or on the character or appearance of the Prinsted Conservation Area."
Historic England has no comments on the principle of the allocation Land West of Tangmere.

However, the site is close to the Tangmere Conservation Area and a number of listed buildings, including the Grade I listed Church of St Andrew. Paragraph 194 of the National Planning Policy Framework states "Any harm to, or loss of, the significance of a designated heritage asset (from its alteration or destruction, or from development within its setting), should require clear and convincing justification". The paragraph identifies Grade I buildings as assets of the "highest significance".

Historic England therefore welcomes, in principle, clauses 5 and 8 of Policy AL14

5. Protect existing views of Chichester Cathedral spire and reduce any impact on views from within the National Park;
8. Conserve and enhance the heritage and potential archaeological interest of the village, surrounding areas and World War II airfield, including the expansion or relocation of the Tangmere Military Aviation Museum.
However, we consider that clause 8 should be strengthened to ensure that it provides adequate protection for these assets in accordance with the National Planning Policy Framework. In addition, we note that paragraph 6.95 of the Plan identifies, as one of the specific issues need to be taken into account in planning the development and site layout at Tangmere, "Conserving and enhancing the setting of the historic village (particularly the Conservation Area"). We consider that this should be included within Policy AL14.
This comment is without prejudice to any comments we may wish to make on any planning application that may be submitted for the development of this site.
Reword criterion 8 as follows:

8. Conserve and enhance the heritage and potential archaeological interest of the village, surrounding areas and World War II airfield, particularly the Conservation Area and the Grade I listed Church of St Andrew and including the expansion or relocation of the Tangmere Military Aviation Museum.
Add a new criterion as follows:
""Conserve and enhancie the setting of the historic village, particularly of the Conservation Area".
Historic England welcomes and supports clause b of Policy DM3 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports clauses 1 c and 2 e of Policy DM5 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes, in principle, clause 2 of Policy DM13 but considers that the policy should be, in the first instance, to avoid adverse impact on the historic environment as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework. We consider that the wording used in Policies DM3 and DM5 would be appropriate.
Reword clause 2 of Policy DM13 as:
"Is located so as not compromise the essential features of nationally designated areas of landscape, historic environment or nature conservation protection".
Historic England welcomes and supports clause 1 of Policy DM17 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports clause b of Policy DM20 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Historic England welcomes and supports paragraph 7.129 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Many farm buildings that are now redundant for modern farming needs are likely to be of historic interest - it is acknowledged that farm buildings are generally under-represented on the National Heritage List for England. Historic England considers that Policy DM21 should include stronger protection for such buildings as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.
Add a new criterion to Policy DM21 as follows:

"Features of architectural or historic significance are retained and, where the building forms part of a historically significant complex of buildings, consideration is given to the future use(s) of those buildings and the impact of the proposal on the integrity and character of the complex".
Historic England welcomes and supports, in principle, paragraphs 7.154 - 7.161.
However, we consider that paragraph 7.154 should be reworded to clarify the distinction between designated and non-designated heritage assets (the latter including buildings on the Local Buildings List for Chichester).
Reword paragraph 7.154 as follows:
"There are a large number of "Heritage Assets" (as defined in the National Planning Policy Framework), both designated and non-designated, in the plan area. Designated assets are Listed Buildings, Scheduled Monuments, Conservation Areas and Registered Historic Parks and Gardens. Non-designated assets include archaeological sites (although the remains may be of national significance equivalent to scheduled monuments, and which should be considered subject to the policies for scheduled monuments) and non-listed buildings which have been identified as locally important, such as those on the Local Buildings List for Chichester City and 'positive' buildings within Conservation Areas."
Historic England welcomes and supports in principle, Policy DM27 both as part of the positive strategy for the conservation and enjoyment of the historic environment as required by paragraph 185 of the National Planning Policy Framework and also as a non-strategic policy for the conservation and enhancement of the historic environment as suggested by paragraph 28 of the Framework.
However, we consider that clause e. should specify the (wholly) exceptional circumstances in which permission for a proposed development that would lead to substantial harm to (or total loss of significance of) a designated heritage asset would be granted i.e. where it can be demonstrated that the substantial harm or total loss is necessary to achieve substantial public benefits that outweigh that harm or loss, or all of the circumstances in paragraph 195 of the National Planning Policy Framework apply.

We would also welcome the policy being more detailed in terms of the considerations to be taken into account when assessing development proposals affecting the different types of heritage asset, as do, for example, Policies EH10, EH11, EH14 and EH15 of the West Oxfordshire Local Plan 2031. These policies were developed with Historic England and the Inspector that examined the Local Plan 2031 shared our concern that the historic environment policy in the Local Plan 2031 provided inadequate locally specific detailed policy guidance and considered the more detailed policies necessary for the Plan to be sound.

(However, we do acknowledge that the Inspector that examined the Key Policies development plan document considered the modified historic environment policy (Policy 47) put forward by the Council with our support was sufficient for the Plan to be sound, and that Policy DM27 in the Local Plan Review very largely repeats Policy 47).

Reword clause e. of Policy DM27 as follows;
"Development involving substantial harm to or loss of designated heritage assets will
only be granted in exceptional circumstances (wholly exceptional circumstances for
designated assets of the highest significance) i.e. where it can be demonstrated that the substantial harm or total loss is necessary to achieve substantial public benefits that outweigh that harm or loss, or all of the circumstances in paragraph 195 of the National Planning Policy Framework apply.

More details of the considerations to be taken into account when assessing development proposals affecting the different types of heritage asset. We would be pleased to work with the Council on a revised policy or policies.

Paragraph 7.195 of the Plan notes that the remnants of canals "are important early 19th Century historic features in the landscape of the coastal plain and warrant protection".
Historic England agrees with this statement, but Policy DM33 makes no mention of protecting the historic significance of the remaining canal sections.
Reword the first paragraph of Policy DM33 as follows;
"Development that makes provision of through navigation or enhancement of the Chichester Ship Canal and the Wey and Arun Canal will be supported where it meets environmental, ecological, historical and transport considerations."
Historic England welcomes and supports clause 3 of Policy DM34 as part of the positive strategy for the conservation and enjoyment of the historic environment required by paragraph 185 of the National Planning Policy Framework.

Comment

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2311

Received: 07/02/2019

Respondent: Portsmouth Water Ltd

Representation Summary:

Policy AL11 'Hunston' allocation is not site specific.

Full text:

Spatial Vision
Portsmouth Water note that there are significant additional housing allocations to the west of Chichester and on the coastal strip. These sites will need to be assessed for water supply and funding included in the Infrastructure Charging scheme. (See Map 4.1 Key Diagram)

It is not clear what water storage capacity is being referred to in Section 3.19. Portsmouth Water will review the provision of Service Reservoirs, for day to day use, and has re-started development of a large raw water storage reservoir at Havant Thicket. The reservoir, when combined with Portsmouth Water's existing sources and enhancements to its groundwater sources, would create sufficient
surplus to support an additional flexible daily transfer of treated water from Portsmouth Water are to Southern Water without detriment to Portsmouth Water's resilience.

Southern Water requires this transfer to help meet a significant deficit in its Southampton East, Southampton West and Isle of Wight resource zones. This deficit arose after Southern Water agreed to reduce its abstraction licences on the Rivers Test and River Itchen at a public inquiry in March 2018, to help protect the environment.

It is not clear that the water demands of the Horticultural Development Areas have been assessed. It is possible that these businesses will rely on rainwater harvesting and storage but changes in licencing regulations mean that 'Trickle Irrigation' is no longer exempt from abstraction licencing.

Groundwater abstraction in the coastal plain will require an impact assessment under the Habitats Regulations. (Section 4.75)

Spatial Strategy

Policy S12 sets out how development can make effective use of existing infrastructure. Portsmouth Water agree that the siting and timing of development can assist with the economic provision of water resource infrastructure. It also states that safeguarding existing infrastructure, such as water mains and aquifers, is important. Portsmouth Water would urge developers to check for existing infrastructure and for source protection zones that may limit development options.
Water infrastructure is not funded through CIL but a separate 'Infrastructure Charge' payable for each individual house. This is designed to pay for all off-site water infrastructure such as mains reinforcements, service reservoirs and supply. Development to an agreed program will help this system work effectively.

Strategic Policies

Policy S27 'Flood Risk Management' refers to Sustainable Drainage Systems (SuDS) and the need to control surface water run-off. It should also refer to aquifer protection and the need for caution when using infiltration systems especially deep bore systems. This applies particularly when the site is in, or close to, a source protection zone.

Policy S31 'Wastewater Management and Water Quality' refers to higher standards in the Building Regulations for water consumption to reduce pollution in the harbours. Portsmouth Waters 'Water Resources Management Plan' is based on lower per capita consumption and we have an aspiration for all customer to reach 100 litres/head/day by 2050. This is no substitute for reducing overall flows
to sewage treatment works by the control of groundwater infiltration and surface water drainage.

Strategic Site Allocations

Policy AL1 'West of Chichester' does not mention water supply so we assume that the site has reverted to a conventional system with sewerage pumped to Tangmere WWTW and water supplied by us. Portsmouth Water has provided provisional designs for this system and there are no existing large diameter water mains on the site. Costs for reinforcement of the water mains will be recovered by the new Infrastructure Charge and on site mains are likely to be provided by a third
party. Information on how reinforcement of the water mains is recovered by the Infrastructure Charge can be found in Portsmouth Water's Developer Charging Arrangements on our website under https://www.portsmouthwater.co.uk/developers/.

Policy AL2 'Shopwyke' is already under construction and has a conventional water supply system with all elements provided by us. Costs are being recovered via the Infrastructure Charge and on-site charges.

Policy AL3 'East of Chichester' is a new strategic site and there are no large diameter mains crossing it. This is an old landfill and may contain material that can damage plastic pipes. On site mains may need to be protected or be more expensive to ensure water quality is maintained.

Policy AL4 'Westhampnett' Phase 1 is already under construction and account has been taken of the large diameter main that crosses the site. Phase 2 is an extension of the existing Greylingwell site but it is not clear if this has been allowed for in the design of this 'Inset Appointment'. Portsmouth Water do not own the mains and there may be a single point of supply.

Policy AL5 'Southern Gateway' is an inner city development with a good water supply system. The reference to the 'efficient use of water' is confusing because many of the other strategic development sites also drain to Apuldram WWTW. All sites need to be water efficient but not follow the example of the 'Code for Sustainable Homes'. Sites were developed in Chichester that used rainwater harvesting to meet the Code objectives but were able to use higher water use fittings such as power showers. This led to properties producing more sewage than equivalent water efficient homes. This did not achieve the objective at Apuldram. An alternative provision might be to reduce infiltration but it is not clear how this would be funded or who would carry out the work.

Policy AL6 'South West Chichester' is crossed by a large diameter main that will have to be reflected in the road layout or diverted. The proposed link road may offer an alternative route for the main.

Policy AL7 'Bosham' is situated on the old A27 and there are no large diameter mains in the area.

Policy AL8 'East Wittering' is at the extremity of the distribution system and may be expensive to supply.

Policy AL9 'Fishbourne' allocation is not site specific and it is difficult to comment on the feasibility of water supply. Any off site costs will be recovered via the new Infrastructure Charge. Portsmouth Water have public water supply abstractions in the area and development is likely to be located in a source protection zone for our Fishbourne public water supply abstraction. Under this policy, where development is in a source protection zone, the policy should also refer to groundwater quality
protection and the additional requirements when using infiltration systems in particular deep bore systems. Further guidance on Portsmouth Water's preferred approach to development relating to groundwater quality within our catchments can be found within 'Portsmouth Water's Groundwater Protection Guidance notes' which are attached to this response and also available to view on our website under https://www.portsmouthwater.co.uk/developers/groundwater-protection/.

Policy AL10 'Chidham and Hambrook' is a large site and may need to be considered in combination with 'Southbourne' and 'Bosham'. There are no large diameter mains in the area and mains reinforcements may be required.

Policy AL11 'Hunston' allocation is not site specific.

Policy A12 'Selsey' is at the extremity of the distribution system and has seen previous housing growth. Reinforcement of the water mains may need to be provided.

Policy AL13 'Southbourne' is supplied from a different distribution system to Chichester. This is a very large housing allocation and this may need to be considered in combination with 'Hambrook' and 'Bosham'. There are sufficient water resources for all the housing allocated to Portsmouth Water's area of supply. It is the location of the housing site in relation to existing trunk mains and
service reservoirs that determines the cost to supply. Local reinforcement of the water mains may be required.

Policy AL14 'Tangmere' housing allocation has increased by 30% and we may need to repeat the modelling that has already been done. There is also uncertainty about the water supply to the HDA which seems to rely on rainwater harvesting for future growth. The housing development and the HDA could have an impact on our source protection zone. Under this policy, where development is in a source protection zone, the policy should also refer to groundwater quality protection and the
additional requirements when using infiltration systems in particular deep bore systems. Guidance should be sought from Portsmouth Water's Groundwater Protection Guidance for development.

Policy AL15 'Land at Chichester Business Park, Tangmere' Portsmouth Water have public water supply abstractions in the area and the site allocation is likely to be within a source protection zone for our Aldingbourne public water supply abstraction. As above, where development is in a source protection zone, the policy should also refer to groundwater quality protection and the need for caution when using infiltration systems in particular deep bore systems. Please refer to Portsmouth Water's Groundwater Protection Guidance for further information.

Development Management

Policy DM10: 'New Employment Sites' Development proposal should be compatible with other policies in the Plan, in particular DM9 'Existing Employment Sites' to ensure that the development is otherwise acceptable. Policy DM9 states that development should 'not generate unacceptable levels of water pollution' and this should include groundwater pollution. This requirement should also be applied to Policy DM10, especially when the site is in, or close to, a source protection zone.

Policy DM15 'Horticultural Development' Developments at Tangmere HDA have relied on infiltration to dispose of excess surface water. This policy states that development should 'not generate unacceptable levels of water pollution' and this should include groundwater pollution. Portsmouth Water have public water supply abstractions in the area and the potential impacts must be assessed for any SUDS. The EA 'Abstraction Licencing Strategy' (ALS) may give an indication about the
availability of groundwater but it does not cover the derogation of existing supplies.

Policy DM16 'Sustainable Design and Construction' covers the use of Building Regulations to control water use. Portsmouth Water have an aspiration to reduce overall water use to 100 litres/head/day and this policy will help to achieve that aim.

Policy DM18 'Water Management' using SUDS needs to take account groundwater quality and should avoid direct infiltration into the chalk aquifer. This is especially important within the source protection zones.

Policy DM29 'Biodiversity' Portsmouth Water has legal duties to protect and where practical enhance biodiversity and has an active program of work on it's own land. This work is now expanding to include projects on other people's land in association with 'Catchment Management' activities. We would look to CDC for support in areas such as Bosham Stream, Lavant Stream and Fishbourne Stream where schemes could be developed in partnership with local housing developments.

Policy DM35 'Equestrian Development' can have a direct impact on water quality including groundwater quality. Portsmouth Water support the protection of water courses and aquifers.

Appendix 'E' Monitoring Framework

Policy S12 covers the provision of infrastructure but it is not clear how records of completed projects will be collected or stored.

Policy S26 covers biodiversity improvements and Natural England should be consulted on priorities and record keeping.

Policy S31 covers water consumption which is only available for the whole Company area in the WRMP Annual Review.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2340

Received: 20/01/2019

Respondent: Mr Andrew Sabin

Representation Summary:

S23. The proposed increase in housing in Hunston of 200 will have further detrimental impact on the B2145. The road is already far beyond it's capacity and the combination of the additional congestion resulting from the Free School, and development further down the road towards and including Selsey, means that the village will be impacted with a significant increase in road movements. We already have slow moving/stationary traffic during peak hours and the additional pollution and risk to pedestrians is unacceptable.

Full text:

The proposed increase in housing in Hunston of 200 will have further detrimental impact on the B2145. The road is already far beyond it's capacity and the combination of the additional congestion resulting from the Free School, and development further down the road towards and including Selsey, means that the village will be impacted with a significant increase in road movements. We already have slow moving/stationary traffic during peak hours and the additional pollution and risk to pedestrians is unacceptable.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2341

Received: 20/01/2019

Respondent: Mr Andrew Sabin

Representation Summary:

S30. There is a rich and varied number of wildlife in Hunston and the surrounding areas but the proposed development in Hunston would have a serious negative impact on the current wildlife corridors. The canal already acts as a hard North/South border to wildlife movement and the proposed development would only further impede wildlife movement.

Full text:

There is a rich and varied number of wildlife in Hunston and the surrounding areas but the proposed development in Hunston would have a serious negative impact on the current wildlife corridors. The canal already acts as a hard North/South border to wildlife movement and the proposed development would only further impede wildlife movement.

Object

Local Plan Review: Preferred Approach 2016-2035

Representation ID: 2342

Received: 20/01/2019

Respondent: Mr Andrew Sabin

Representation Summary:

S28. The B2145 already has very high traffic levels and the combination of the congestion from the new Free School and the proposed development down the B2145 will lead to a significant increase in the slow moving and stationary traffic during peak times with a corresponding increase in pollution levels during those periods.

Full text:

The B2145 already has very high traffic levels and the combination of the congestion from the new Free School and the proposed development down the B2145 will lead to a significant increase in the slow moving and stationary traffic during peak times with a corresponding increase in pollution levels during those periods.